Activities at Singatac
Activities at Singatac
ACTIVITIES AT SINGATAC
no Date Time Activities
1 16-Nov-23 08.00 - 12.00 - Security Check
-Safety Induction
-PPE
13.00 - 18.00 -Performed visual inspection and DFT check
on 2 unit Grillage at white tent
2 17-Nov-23 08.30 - 09.40 Performed Visual inspection and DFT check 2 nd coat
on 5 bundles plate
10.00 - 12.00 Performed Visual inspection and DFT check internal
final inspection on 2 unit grillage at white tent
13.00 - 14.30 Pull off test Batch 1 and 3
14.30 - 17.00 Performed visual inspection and dft check at blasting
chamber after application 2nd coat on stairs,bundle
plate and various small items
17.00 - 18.00 Installed dolly for test panel batch 2
3 18-Nov-23 08.30 - 09.30 Performed visual inspection and dft check for internal
final inspection on 5 bundle plate after rectifying
09.30 - 12.00 Performed visual inspection and dft check for internal
on Base Frame for station 1 at jetty
13.30 - 14.30 Performed visual inspection and dft check for internal
on Base Frame for station 2 at jetty
14.30 - 16.00 Assissted inspection final top coat at warehouse
on 2 unit grillage type 1
16.00 - 18.00 Assissted inspection visual and dft check
on base frame for station 1 and 2 at jetty
5 20-Nov-23