Professional Documents
Culture Documents
3rd Quiz
3rd Quiz
3rd Quiz
Good Luck
First Name *
mahmoud
Family Name *
kassab
SID *
Please, enter your student ID number
A00460292
https://docs.google.com/forms/d/e/1FAIpQLSdHOnDhTsPxj3gKitkGBf1PWaz1V2zq-6CMfLPOfqp6qFDx5g/viewscore?pli=1&pli=1&pli=1&viewscore=… 1/13
7/5/23, 11:40 AM 3rd Quiz
The construction foreman posted a large sign requiring all work site *2/2
visitors to don a hard hat and safety glasses. He also purchased copious
quantities of both items and made them readily available at the entrance.
The foreman is engaged in
risk identification.
risk mitigation.
What is the total project budget for design in this time-phased budget? * 1/1
$152,000
$106,000
$57,000
$34,00
https://docs.google.com/forms/d/e/1FAIpQLSdHOnDhTsPxj3gKitkGBf1PWaz1V2zq-6CMfLPOfqp6qFDx5g/viewscore?pli=1&pli=1&pli=1&viewscore=… 2/13
7/5/23, 11:40 AM 3rd Quiz
Each project team member had a backup that could fill in at a moment's *0/1
notice should another team member fall by the wayside. The project was
able to mitigate risks in this fashion thanks to an aggressive
mentoring program.
cross-training program.
duplication program.
featherbedding program
Three workers complete a full 8-hour day finishing concrete for a terrace. *0/2
All three workers are paid $12 an hour and the job bills to the customer
for $450. What are the total direct labor costs?
$450
$12
$288
$96
https://docs.google.com/forms/d/e/1FAIpQLSdHOnDhTsPxj3gKitkGBf1PWaz1V2zq-6CMfLPOfqp6qFDx5g/viewscore?pli=1&pli=1&pli=1&viewscore=… 3/13
7/5/23, 11:40 AM 3rd Quiz
Ray's shipment of materials hit every red light and traffic jam on the way *0/2
to the site. Upon arrival, half of the material was judged defective,
necessitating a trip back to the supplier, and then the same arduous
journey back to the site once the new materials were loaded. Traffic was
a little better on the second round but the flat tire and subsequent repair
caused as much if not more delay than the first trip. In the final analysis
The project activity of Material Delivery was pretty close to the optimistic estimate.
The project activity of Material Delivery was pretty close to the most likely estimate.
The project activity of Material Delivery had a much higher variance than
anticipated.
The project activity of Material Delivery was pretty close to the pessimistic
estimate.
What is the late finish time for Activity D given the activity times and *2/2
precedence requirements shown in the table?
14
13
12
11
https://docs.google.com/forms/d/e/1FAIpQLSdHOnDhTsPxj3gKitkGBf1PWaz1V2zq-6CMfLPOfqp6qFDx5g/viewscore?pli=1&pli=1&pli=1&viewscore=… 4/13
7/5/23, 11:40 AM 3rd Quiz
personnel training
outplacement services
logistics
You are probably looking at a bill for a variable cost when you are paying *1/1
for:
salaries.
materials.
health insurance.
parametric.
comparative.
definitive.
ballpark.
https://docs.google.com/forms/d/e/1FAIpQLSdHOnDhTsPxj3gKitkGBf1PWaz1V2zq-6CMfLPOfqp6qFDx5g/viewscore?pli=1&pli=1&pli=1&viewscore=… 5/13
7/5/23, 11:40 AM 3rd Quiz
Once most of the design work is complete, at a point when the scope and *1/1
capabilities of the project are quite well understood, a __________ may be
developed.
definitive estimate
comparative estimate
a parametric estimate
a non-parametric estimate
Use the network diagram and activity lengths in the nodes to determine *0/2
the late start time for activity F.
21
24
26
23
https://docs.google.com/forms/d/e/1FAIpQLSdHOnDhTsPxj3gKitkGBf1PWaz1V2zq-6CMfLPOfqp6qFDx5g/viewscore?pli=1&pli=1&pli=1&viewscore=… 6/13
7/5/23, 11:40 AM 3rd Quiz
Use the network diagram and activity lengths in the nodes to determine *0/2
the slack time for activity D.
https://docs.google.com/forms/d/e/1FAIpQLSdHOnDhTsPxj3gKitkGBf1PWaz1V2zq-6CMfLPOfqp6qFDx5g/viewscore?pli=1&pli=1&pli=1&viewscore=… 7/13
7/5/23, 11:40 AM 3rd Quiz
Use the information in the table to determine the slack time for Activity B. * 0/2
6 days
4 days
2 days
0 days
Forms
https://docs.google.com/forms/d/e/1FAIpQLSdHOnDhTsPxj3gKitkGBf1PWaz1V2zq-6CMfLPOfqp6qFDx5g/viewscore?pli=1&pli=1&pli=1&viewscore=… 8/13
7/5/23, 11:40 AM 3rd Quiz
https://docs.google.com/forms/d/e/1FAIpQLSdHOnDhTsPxj3gKitkGBf1PWaz1V2zq-6CMfLPOfqp6qFDx5g/viewscore?pli=1&pli=1&pli=1&viewscore=… 9/13
7/5/23, 11:40 AM 3rd Quiz
https://docs.google.com/forms/d/e/1FAIpQLSdHOnDhTsPxj3gKitkGBf1PWaz1V2zq-6CMfLPOfqp6qFDx5g/viewscore?pli=1&pli=1&pli=1&viewscore… 10/13
7/5/23, 11:40 AM 3rd Quiz
https://docs.google.com/forms/d/e/1FAIpQLSdHOnDhTsPxj3gKitkGBf1PWaz1V2zq-6CMfLPOfqp6qFDx5g/viewscore?pli=1&pli=1&pli=1&viewscore… 11/13
7/5/23, 11:40 AM 3rd Quiz
https://docs.google.com/forms/d/e/1FAIpQLSdHOnDhTsPxj3gKitkGBf1PWaz1V2zq-6CMfLPOfqp6qFDx5g/viewscore?pli=1&pli=1&pli=1&viewscore… 12/13
7/5/23, 11:40 AM 3rd Quiz
https://docs.google.com/forms/d/e/1FAIpQLSdHOnDhTsPxj3gKitkGBf1PWaz1V2zq-6CMfLPOfqp6qFDx5g/viewscore?pli=1&pli=1&pli=1&viewscore… 13/13