SAFE WORK METHOD STATEMENT PMAC-HBS-SWMS-007

REV – NO- 00

COMPANY NAME : CLIENT NAME :


M/S. PRECISION MACHINE & AUTO COMPONENTS PRIVITE LIMITED.
M/S. HANSEM BUILDING SYSYTEMS INDIA PRIVATE LIMITED
PMSC:
NO.114, SHREE ARTHANARI TOWERS,
M/S. CBRE South Asia Pvt Ltd | Project Management Group– India
6TH FLOOR, RACE COURSE,
NO.200/1A,2A3A,
COIMBATORE -641018
VAYALUR,

THIRUVALLUR,

TAMIL NADU – 602105


JOB DETAILS : SHEETING CONTAINER UNLOADING WORK
EQUIPMENTS & TOOLS AND TACKELS :

1. Farana 16 T /20T
2. Wire Rope for Guide Line Purpose – 12 mm
MATERIALS DETAILS : 3. Web Sling – ( 5T * 6 M)
4. Bow Shackles – (9.5 T)
5. Ledder - ( 3 to 4 M Length)
1. Container -40 f – 7 T

Mandatory PPE’s: Safety Helmets, Reflective jacket, , Hand gloves, Safety shoe, Safety Harness, Nose mask, Shoulder Pad and (Task Specific Tools)

E - Extreme Risk: The hazard has the potential to kill or permanently disable a person H - High Risk: The hazard has the potential to cause a LTI ≥ 7 days
M - Medium Risk: The hazard has the potential to cause a LTI < 7 days L - Low Risk: The hazard has the potential to cause a minor injury that will not disable a person (i.e.: Nil LTI)
PREPARED BY REVIWED BY APPROVED BY Page No.
1 of 8
SAFE WORK METHOD STATEMENT PMAC-HBS-SWMS-007

REV – NO- 00

Procedure (in steps) Possible Hazards/Risk Risk Control Measures Controlled risk Person who will
Rating (Describe what action or procedure will be taken to score ensure this
(Break the job down into steps. (Identify the hazards (See eliminate or minimize the risk of injury or damage. Use the happens
Each step should accomplish associated with each below) Hierarchy of Controls below as a guide
some major task and be in step. Examine each to • Eliminate the Hazard
logical sequence.) find possibilities that • Substitute the material or equipment
could lead to an accident • Isolate the hazard
or potential harm • Implement Engineering control
arising.) • Implement Administrative control
• PPE
1. Entering the trailers with • Struck by other M
• Before enter the gate vechile physical condition must be
Siteengineer, Operator,
Container gate to unloading work L Safety officer
vehicles, checked
site.
• Hit hazrds • Ensure the overhead electrical line.
• Ensure the vechile access levelled and proper
• vehcile topple
compacted.
• Traffic • Communicate to the drivers and helpers regard site logistic
• Over speeding route, parking facilties and road condition
• Equipments failures • Communicate to driver about speed limit (15Km/h) within
premises
• Equipments topples
• Vehicle must be march under guidance of Flagman.
• Scotch block to be use with hand brake while vehicle in
parking condition.
• Ensure to proper PPES provided to drivers.
(Helmet,Jacket,Safety shoe,)

E - Extreme Risk: The hazard has the potential to kill or permanently disable a person H - High Risk: The hazard has the potential to cause a LTI ≥ 7 days
M - Medium Risk: The hazard has the potential to cause a LTI < 7 days L - Low Risk: The hazard has the potential to cause a minor injury that will not disable a person (i.e.: Nil LTI)
PREPARED BY REVIWED BY APPROVED BY Page No.
2 of 8
SAFE WORK METHOD STATEMENT PMAC-HBS-SWMS-007

REV – NO- 00

Procedure (in steps) Possible Hazards/Risk Risk Control Measures Controlled risk Person who will
Rating (Describe what action or procedure will be taken to score ensure this
(Break the job down into steps. (Identify the hazards (See eliminate or minimize the risk of injury or damage. Use the happens
Each step should accomplish associated with each below) Hierarchy of Controls below as a guide
some major task and be in step. Examine each to • Eliminate the Hazard
logical sequence.) find possibilities that • Substitute the material or equipment
could lead to an accident • Isolate the hazard
or potential harm • Implement Engineering control
arising.) • Implement Administrative control
• PPE
2.Mobilation of Farana 16 T/20 T • Damaged equipment M
• Before enter the gate vechile physical condition must be
L Siteengineer, Operator,
gate to unloading area. Safety officer
checked.
• Unauthorized
operators • Ensure the overhead electrical line.
• Ensure the vechile access levelled and proper
• Equipments failures compacted.
• Ensure the TPI certificate and legal documents for
• Equipments topples
equipments. (RC,TPI,INSURANCE,POLITION,DRIVER
• Poor access LICENCE,)
• Communicate to driver about speed limit (15Km/h) within
premises
• Vehicle must be march under guidance of Flagman.

• Equipment check list must be filled before start the


work.
• Before start the work site induction should be done for
operators.
• Opertors should be submitted to medical eye vision
certificate.
• Valid work permit will be taken from authorized person.
• Ensure to proper PPES provided to drivers.
(Helmet,Jacket,Safety shoe,)

E - Extreme Risk: The hazard has the potential to kill or permanently disable a person H - High Risk: The hazard has the potential to cause a LTI ≥ 7 days
M - Medium Risk: The hazard has the potential to cause a LTI < 7 days L - Low Risk: The hazard has the potential to cause a minor injury that will not disable a person (i.e.: Nil LTI)
PREPARED BY REVIWED BY APPROVED BY Page No.
3 of 8
SAFE WORK METHOD STATEMENT PMAC-HBS-SWMS-007

REV – NO- 00

Procedure (in steps) Possible Hazards/Risk Risk Control Measures Controlled Person
Rating (Describe what action or procedure will be taken to eliminate or minimize the risk who will
(Break the job down into steps. (Identify the hazards (See risk of injury or damage. Use theHierarchy of Controls below as a guide score ensure
Each step should accomplish some associated with each step. below) • Eliminate the Hazard this
major task and be in logical Examine each to find • Substitute the material or equipment happens
sequence.) possibilities that could lead • Isolate the hazard
to an accidentor potential • Implement Engineering control
harm arising.) • Implement Administrative control
• PPE
3. Unloading the sheeting container and • Struck by other H • Ensure only trained and authorized workers involved the unloading work. L Siteengineer,
shifting to required place.(Tantem lifting) vehicles, • Before start the work should be done barricaded to working area. Operator,
• Hit hazrds • Only experienced person will operate the vechile. With vaild site id card. Safety officer
• vehcile topple • Only third party certified equipment will be used at site.
• Traffic • Ensure the job leader only guide the unloading work.
• Over • Vehicle must be march under guidance of Flagman.
speeding • Ensure the vechile access levelled and proper compacted.
• Trailer • Operators not to allowed overload
topples • Ensure do not drag the sling.
• Equipments • Only experience rigger must be appointed to do all rigging work.
topples • Proper communication system shall be used for the lifting operations in blind
• Hid hazards spot.
• Poor access • Ensure should not be allowed any unauthorized person moving in erection
area.
• No one is allowed to enter the suspended load area.
• Material should be placed on evensurface.
• Material to be stacked on minimum 300 mm height only.
• Two guide ropes of minimum three meter length must be use to guide the
material during shifting.
• The position of person holding guide rope should be out of material &
equipment reach
• Check the swinging area of material,there should not be any hid drance.
• Ensure to proper PPES provided to workers.
(Helmet,Jacket,Safety shoe,Goggles,Handgloves,)

E - Extreme Risk: The hazard has the potential to kill or permanently disable a person H - High Risk: The hazard has the potential to cause a LTI ≥ 7 days
M - Medium Risk: The hazard has the potential to cause a LTI < 7 days L - Low Risk: The hazard has the potential to cause a minor injury that will not disable a person (i.e.: Nil LTI)
PREPARED BY REVIWED BY APPROVED BY Page No.
4 of 8
SAFE WORK METHOD STATEMENT PMAC-HBS-SWMS-007

REV – NO- 00

Procedure (in steps) Possible Risk Control Measures Controlled Person who will
Hazards/Risk Ratin (Describe what action or procedure will be taken to riskscore ensure this
(Break the job down into steps. g(See eliminate or minimize the risk of injury or damage. Use happens
Each step should accomplish (Identify the hazards below theHierarchy of Controls below as a guide
some major task and be in associated with each ) • Eliminate the Hazard
logical sequence.) step. Examine each to • Substitute the material or equipment
find possibilities that • Isolate the hazard
could lead to an • Implement Engineering control
accidentor potential • Implement Administrative control
harm arising.) • PPE
4.De- slinging of container and proper • Silp and trip M • Ensure the all workers must be done the site L Site engineer, Operator,
stacking hazard induction. Safety officer
• Improper • Ensure only trained and authorized workers involved
slinging the unloading work.
• Damage • Access purpose ladder should be used.
lifting tools • Ladder should be holded on ground level person.
and tackles • Slinging must be done by trained and experienced
• Equipments person.
topples • Safe method of De- slinging should be discussed in
daily toolbox meeting.
• Hid hazards
• SWL of the sling must be matched according to the
material weight.
• Lifting tool & tackles must be checked before use.
• Only third party certified lifting tool& tackles should
be use.
• Check the capacity of tool & tackles before lifting.
• Packing must be provided in between material & sling
to protect from sharpedges
• Material should not be foul with boom during
lifting/shifting.
• Only one trained signal man will give signal to the
operator.
• Ensure to proper PPES provided to workers.
(Helmet,Jacket,Safety shoe,Goggles,Handgloves,)

E - Extreme Risk: The hazard has the potential to kill or permanently disable a person H - High Risk: The hazard has the potential to cause a LTI ≥ 7 days
M - Medium Risk: The hazard has the potential to cause a LTI < 7 days L - Low Risk: The hazard has the potential to cause a minor injury that will not disable a person (i.e.: Nil LTI)
PREPARED BY REVIWED BY APPROVED BY Page No.
5 of 8
PMAC-HBS-SWMS- 007
SAFE WORK METHOD STATEMENT
REV.NO: 001

Personnel Summary

SUPERVISOR’S DETAILS
Site Engineer Name & Name: G.TAMIL PRIYAN
Qualifications: Experience: 14 YEARS
Qualifications: BE.
MECHNAICAL
Site Engineer Responsibilities: 1) Hand tools and Equipment inspections.
2) Collect relevant information from the subcontractor with respect to work, equipment and personnel.
3) Check suitable safety requirements in place during operation of the works.
4) Implementation and follow up the PERMIT System
5) Conduct tool box meeting
6) Periodic testing of tools, safety harness and ladder
7) Signages..
DESCRIPTION OF TRAINING THAT HAS BEEN GIVEN TO PEOPLE INVOLVED WITH THE WORK

H&S GENERAL INDUCTION: All workers must have successfully completed site induction training

WORK ACTIVITY TRAINING: All workers need to have been trained in the activities outlined in this safe work method statement.

SITE INDUCTION: HSE induction : All workers are to be site inducted by the Principal Contractor, prior to commencing work on site.

OTHER:(List other training undertaken by workers): (eg: Height work traning,Lifting work traning, Manual Handling, Traffic Control etc)

TICKETS, PERMITS or LICENCES REQUIRED undertaking this work (i.e. Certificates of Competency, Height work etc.):

N.B. - Copies of the above must be shown to the Principal Contractor during site induction.
LEGISLATION, CODES OF PRACTICE and GUIDELINES applicable to this work

All work to comply with the Client &CBRE requirements and also BOCW Acts and Regulations

Additional IS Codes and Standards applicable to this trade: IS : 3764

PREPARED BY REVIWED BY APPROVED BY Page No.


6 of 8
PMAC-HBS-SWMS-007
SAFE WORK METHOD STATEMENT REV – NO -00

Equipment & Material Summary

PLANT and EQUIPMENT use and MAINTENANCE FREQUENCY:

Maintenance/service records and log books sighted


Government Plant Hazards by Principle Contractor prior to equipment being
Contractor identified and
Serial Plant/Equipment Registration No. used on site?
controlled within
(Where applicable) WMS?
Yes No Sign Date

ELECTRICAL EQUIPMENT USED DURING THE WORKS (Attach Electrical Equipment Register if applicable):
Item Tag/Item Testers Name & Signature License Number Test Date Result Test Date Result
Number
/ / / /

/ / / /
HAZARDOUS SUBSTANCES or DANGEROUS GOODS USED IN THE WORKS and anticipated volumes (Attach MSDS if applicable):
MSDS
Date on Purpose Location & Volume Controls
Date Left Site Product Name MSDS Date Attached
Site (ie. Application on site) Used on Site (& PPE to be worn)
(Y/N)
/ / / / / /

/ / / / / /

/ / / / / /
N.B. - All workers must be trained in the safe use of all chemicals and provided with the PPE required when using and storing these chemicals. Disposal is to be
as per the waste disposal methods in the MSDS. Spillage and leaks are to be cleaned up as per the spill/leak procedures identified in the MSDS.

PREPARED BY REVIWED BY APPROVED BY Page No.


7 of 8
PMAC-HBS-SWMS-007
SAFE WORK METHOD STATEMENT REV – NO -00

We agree that we have been consulted in the hazards and control measures and agree to complete the work in accordance with our Work Method Statement
(WMS).
We have been provided with training in all tasks outlined in our WMS and in the Codes of Practice applicable to our work.

Employee / Worker Signature Date Employee / Worker Signature Date


1. / / 8. / /
2. / / 9. / /
3. / / 10. / /
4. / / 11. / /
5. / / 12. / /
6. / / 13. / /

Reviewed by: Signature: Date:


(Principal Contractor’s Representative)

Any changes, additions or deletions made to this WMS are to be covered with the above personnel and the Principal Contractor’s representative at a Toolbox
meeting (Record date and time of Toolbox meeting below):

Date: Time:
Comments:

A copy of the Toolbox Meeting must be attached to this SWMS.

PREPARED BY REVIWED BY APPROVED BY Page No.


8 of 8