Professional Documents
Culture Documents
Wk2 - Project Management - Introduction + Project Initiation
Wk2 - Project Management - Introduction + Project Initiation
1
Introduction
2
Construction Project Management
❖ Project Management provides an organization with powerful tools that improve its ability to plan,
implement, and control its activities as well as the ways in which it utilizes its people and resources.
❖ The Project Management Institute (PMI) was founded in 1969 to foster the growth of project
management.
❖ Budget refers to costs, measured in dollar ( Or any other currency) and/or labor-hours of work..
❖ Schedule refers to the logical sequencing and timing of the work to be performed.
❖ The quality of a project must meet the owner's satisfaction. Quality is an element that is integrated
into and between all parts of a project: scope, budget, and schedule. Quality is the responsibility of all
participants in a project.
4
Definition of the Project
❖ The PMI has defined a project as “A temporary endeavor undertaken to create a unique product or
service”
❖ A construction Project could be: residential, healthcare, educational, industrial, infrastructure, plant.
❖ A project is usually a one-time activity with well-defined set of desired end results. It can be divided into
subtasks that must be accomplished in order to achieve the project goals.
❖ The project is complex enough that the subtasks require careful coordination and control in terms of timing,
precedence, cost and performance.
❖ Our terminology follows in this order: program, project, task, work package, work unit.
❖ Like organic entities, projects have life-cycle. From a slow beginning they progress to a build-up of size, then
peak, begin to decline, and finally must be terminated. Projects often start slowly, build-up speed while using
considerable resources, and then slow down as a completion nears.
5
Projects life-cycle
6
Projects life-cycle
7
Glossary
Project Management :The means, techniques, and concepts used to run a project and achieve its objectives.
Program: Often not distinguished from a project, but frequently meant to encompass a group of similar projects
oriented toward a specific goal.
Task: Set of activities compromising a project
Work Package: Division of tasks
Work Unit: Division of work packages
Trade-off: Taking less on one measure, such as performance, in order to do better on another, such as schedule
or cost.
Stakeholder: Parties-at-interest. Individuals or groups with a special interest in a project, usually the project
team, client, senior management, etc.
Interdependencies: Relations between organizational functions where one function or task is dependent on
8
others
9
Project Management
❖ Project management is the art and science of coordinating people, equipment, materials, money, and schedules to
complete a specified project on time and within approved cost.
❖ Throughout the project management process there are four questions that must be addressed: Who? Does what?
When? and How much?
❖ Project management requires a multi-discipline focus to coordinate the overall needs of a project with reliance on
others to provide the technical expertise.
❖ A fundamental principle of project management is to organize the project around the work to be accomplished.
10
Project Management Processes
The management of a project generally follows these steps:
Step 1: Project Definition (to meet the needs of the end user) Intended use by the owner upon completion of
construction Conceptual configurations and components to meet the intended use.
Step 2: Project Scope (to meet the project definition) Define the work that must be accomplished Identify the
quantity, quality, and tasks that must be performed.
Step 3: Project Budgeting (to match the project definition and scope) Define the owner's permissible budget,
Determine direct and indirect costs plus contingencies.
Step 4: Project Planning (the strategy to accomplish the work) Select and assign project staffing Identify the tasks
required to accomplish the work.
11
Project Management Processes
Step 5: Project Scheduling (the product of scope, budgeting, and planning) Arrange and schedule activities in a
logical sequence Link the costs and resources to the scheduled activities.
Step 6: Project Tracking (to ensure the project is progressing as planned) Measure work, time, and costs that are
expended Compare "actual" to "planned work, time, and cost.
Step 7: Project Close Out (final completion to ensure owner satisfaction) Perform final testing and inspection,
archive documents, and confirm payments, and turn over the project to the owner.
Hint: The topic of project management is further complicated because the responsibility for these steps usually involves many
parties.Thus, the above steps must all be integrated together to successfully manage a project.
12
Projects Parties-at-interest
1. Owner (Client)
The owner is responsible for setting the operational criteria for the completed project. Owners also need to identify
their level of involvement in the project, e.g., the review process, required reports, and the levels of approval. The owner
is also responsible for setting parameters on total cost, payment of costs, major milestones, and the project completion
date.
1. Setting the operational criteria for the completed project as usage of the building.
2. Define any special equipment, material, or company standards that are to apply to the project
3. The owner is also responsible for setting parameters on total cost, payment of costs, major milestones, and the
project completion date.
4. Provide site with suitable access to contractor
5. Provide adequate information and instruction for the contractor to start work
6. Pay the contractor in accordance with that mentioned in contract.
13
Projects Parties-at-interest
2. Engineer; Designer, Consultant and Architect
The Engineer is responsible for;
1. Producing design alternatives, computations, drawings, and specifications that meet the needs of the owner.
2. Delegated to the designer by the owner, e.g., on-site or periodic inspection, review of shop drawings, and in some
instances the acquisition of land and/or permits.
3. Produce a project design that meets all federal, state, and local codes; standards; and environmental and safety
regulations.
4. Prepare the budget for the design along with a design schedule that matches the owner's schedule.
5. Revise the design to eliminate defects and errors.
6. Provide a proper estimate of quantity and reasonable cost of the construction of a project
7. Review and approval of contractor submittals.
14
Projects Parties-at-interest
3. Contractor
The contractor duties are;
1. To complete the works in accordance with the contract documents, plans, drawings, specifications and bill of quantity
on time that specified in the contract.
2. To coordinate between all parties of the construction works to complete the project,
3. To ensure that the construction works performing in a safe manner
4. The contractor must prepare an accurate estimate of the project, develop a realistic construction schedule, and
establish an effective project control system for cost, schedule, and quality.
15
Roles and responsibilities of a project manager
▪ Defining scope
▪ Activity planning and sequencing
▪ Resource planning
▪ Developing schedules
▪ Time estimating
▪ Cost estimating
▪ Developing a budget
▪ Documentation
▪ Risk Analysis
▪ Managing risks and issues
▪ Monitoring and reporting progress
▪ Team leadership
▪ Business partnering
▪ Working with vendors
▪ Controlling quality
▪ Benefits realization
16
WHY PROJECT MANAGEMENT?
▪ Better control
▪ Better customer relations
▪ Shorter development times
▪ Lower costs
▪ Higher quality and reliability
▪ Higher profit margins
▪ Sharper orientation toward results
▪ Better interdepartmental coordination
▪ Higher worker morale
17
THE PROJECT LIFECYCLE
Stages of a Conventional Project:
▪ Slow beginning
▪ Buildup of size
▪ Peak
▪ Begin a decline
▪ Termination
18
THE PROJECT LIFECYCLE
Risk during project life cycle
▪ With most projects there is some uncertainty about the ability to meet project goals
▪ Uncertainty of outcome is greatest at the start of a project
▪ Uncertainty decreases as the project moves toward completion
20
Planning Design Construction O&M
Handover Termination
21
THE PROJECT MANAGEMENT LIFECYCLE
1. Initiating
22
THE PROJECT MANAGEMENT LIFECYCLE
2. Planning
23
THE PROJECT MANAGEMENT LIFECYCLE
3. Executing
▪ Launch project
▪ Bring resources on-board
▪ Get resources settled in
▪ Explain rules that will be used to run the project
▪ Put plan to action
24
THE PROJECT MANAGEMENT LIFECYCLE
4. Monitoring and Controlling
25
THE PROJECT MANAGEMENT LIFECYCLE
5. Closing
26
SUMMARY
The three primary forces behind project management are:
Terminology follows in this order: program, project, task, work package, work unit
▪ Projects are characterized by a singleness of purpose, a definite life cycle, complex interdependencies,
some or all unique elements, and an environment of conflict
▪ Project management, though not problem-free, is the best way to accomplish certain goals
27
CHAPTER 2. FIRST THINGS FIRST
PROJECT INITIATION
28
PROJECT INITIATION
Project initiation starts with
29
PROJECT INITIATION
▪ Realism - The model should reflect the reality of the firm’s decision situation, especially the
multiple objectives of both the firm and its managers, bearing in mind that without a common
measurement system, direct comparison of different projects is impossible. The model should
also take into account the realities of the firm’s limitations on facilities, capital, personnel, and
so forth, and include factors that reflect project technical and market risks: performance, cost,
time, customer rejection, and implementation.
▪ Capability- The model should be sophisticated enough to deal with the relevant factors:
multiple time periods, situations both internal and external to the project (e.g., strikes, interest
rate changes), and so on.
▪ Flexibility - The model should give valid results within the range of conditions that the firm
might experience. It should be easy to modify in response to changes in the firm’s
environment; for example, tax law changes, new technological advancements that alter risk
levels, and, above all, organizational goal changes.
31
PROJECT INITIATION
Criteria for Project Selection Models
▪ Ease of Use - The model should be reasonably convenient, not take a long time to execute,
and be easy to use and understand. It should not require special interpretation, data that are
difficult to acquire, excessive personnel, or unavailable equipment.
▪ Cost - Data-gathering and modeling costs should be low relative to the cost of the project
and less than the potential benefits of the project. All costs should be considered, including the
costs of data management and of running the model
▪ Easy Computerization - It should be easy and convenient to gather and store the
information in a computer database, and to manipulate data in the model through use of a
widely available, standard computer package such as Excel
32
PROJECT INITIATION
Nature of Project Selection Models
33
PROJECT INITIATION
Nonnumeric Models
▪ Sacred Cow - project is suggested by a senior and powerful official in the organization.
The project is “sacred” in the sense that it will be maintained until successfully concluded,
or until the boss, personally, recognizes the idea as a failure and terminates it.
▪ Operating Necessity - the project is required to keep the system running. If a flood is
threatening the plant, a project to build a protective dike does not require much formal
evaluation, which is an example of this scenario.
▪ Product Line Extension - projects are judged on how they fit with current product line,
fill a gap, strengthen a weak link, or extend the line in a new desirable way.
▪ Comparative Benefit Model - several projects are considered and the one with the
most benefit to the firm is selected.
34
PROJECT INITIATION
Non-Discounting Discounted
35
PROJECT INITIATION
Pay Back Period
As large majority of all firms using project evaluation and selection models use profitability as
the sole measure of acceptability.
▪ Payback period - The payback period for a project is the initial fixed investment in the
project divided by the estimated annual net cash inflows from the project. The ratio of these
quantities is the number of years required for the project to repay its initial fixed investment.
▪ For example, assume a project costs $100,000 to implement and has annual net cash inflows
of $25,000. Then ˃ Payback period $100,000/$25,000 = 4 years
▪ This method assumes that the cash inflows will persist at least long enough to payback the
investment, and it ignores any cash inflows beyond the payback period. The method also serves
as an (inadequate) proxy for risk.
▪ The faster the investment is recovered, the less the risk to which the firm is exposed. 36
PROJECT INITIATION
Pay Back Period
Machine A Machine B
Initial Investment = 150,000 JOD Initial Investment = 200,000 JOD
Cash Inflows = 50,000 JOD Cash Inflows = 55,000 JOD
PPP= Initial Investment / Cash Inflows PPP= Initial Investment / Cash Inflows
PPP = 150,000/50,000 = 3 Yrs PPP= 200,000/55,000 = 3.6 Yrs
An industry is considering investment in a project which costs 600,000 JOD. Cash inflows are
120,000, 140,000, 180,000, 200,000 and 250,000 . When they will get their cash back?
Years Cash flows Cumulative Cash flow
0 - 600,000 - 600,000
1 120,000 - 480,000
2 140,000 - 340,000
3 180,000 - 160,000
4 200,000 40,000
5 250,000
We stop when we reach the positive value which means that we will get our cash back between 3
& 4 year. But when exactly.
NPV is a discounted cash flow method that considers time value of money in evaluating capital
investments
Let me ask you a question. Which is better to have 500 JOD now in your hand or to have the
same 500 JOD a year later in future?
In financial management, anything we are going to receive in future is discounted to present value
using a discounting factor/percentage
39
PROJECT INITIATION
Numeric Models: Profit/Profitability
PV FV
Discounting Rate
? 500 JOD
1 Year Later
10%
1
𝑃𝑉 = 𝐹𝑉 𝑥
(1 + 𝑟)𝑛
1
𝑃𝑉 = 500 𝑥
(1 + 0.10)1
= 455 JOD
40
PROJECT INITIATION
Numeric Models: Profit/Profitability
NPV is a method of calculating the present value of cash flows (inflows & outflows) of an
investment proposal using the cost of capital as an appropriate discounting rate.
Format
Years Cash flows Discounting rate Present Value
0 (Initial Investment)
1
2 NPV XXXXXXXXXX
If there are more than one project, select the project with the highest NPV 41
PROJECT INITIATION
Numeric Models: Profit/Profitability
Example: calculate the NPV of the two projects and suggest which of the two projects should
be accepted assuming discount rate @ 10%
Project X Project Y
Initial Investment 40,000 JOD 60,000 JOD
Estimated Life 5 Yrs 5 Yrs
Salvage Value 2,000 JOD 4,000 JOD
Cash flows:
1 2 3 4 5
Project X 10,000 20,000 20,000 6,000 4,000
Project Y 40,000 20,000 10,000 6,000 4,000
42
PROJECT INITIATION
Numeric Models: Profit/Profitability
Years 1 2 3 4 5
Discounting 0.909 0.826 0.751 0.683 0.621
factor @ 10%
1/(1+r)^1 +1/(1+r)^2+………1/(1+r)^n
43
PROJECT INITIATION
Numeric Models: Profit/Profitability
Project X
44
PROJECT INITIATION
Numeric Models: Profit/Profitability
Project Y
Which means that we will select Project Y over project X as it has a higher NPV
45
PROJECT INITIATION
Numeric Models: Profit/Profitability
▪ Internal Rate of Return - If we have a set of expected cash inflows and cash outflows, the
internal rate of return is the discount rate that equates the present values of the two sets of
flows. If At is an expected cash outflow in the period t and Rt is the expected inflow for the
period t, the internal rate of return is the value of k that satisfies the following equation (note
that the A0 will be positive in this formulation of the problem):
▪ IRR – represents the discount rate of which the NPV of an investment is Zero
▪ It is a discounted cash flow technique which takes into account the time value money
46
PROJECT INITIATION
Numeric Models: Profit/Profitability
𝑁𝐿
𝐼𝑅𝑅 = 𝐿 + 𝑥 (𝐻 − 𝐿)
𝑁𝐿 − 𝑁𝐻 47
PROJECT INITIATION
Calculate NPV
- NPV 0 + NPV
48
PROJECT INITIATION
Numeric Models: Profit/Profitability
Calculate the IRR of an investment of JOD 136,000 which yields the following cash flow
49
PROJECT INITIATION
Numeric Models: Profit/Profitability
To calculate IRR we need 2 values of NPV, one negative and one positive. Let us start with 10%
50
PROJECT INITIATION
Numeric Models: Profit/Profitability
51
PROJECT INITIATION
Numeric Models: Profit/Profitability
Interpolate
𝑁𝐿
𝐼𝑅𝑅 = 𝐿 + 𝑥 (𝐻 − 𝐿)
𝑁𝐿 − 𝑁𝐻
2280
𝐼𝑅𝑅 = 10 + 𝑥 (12 − 10)
2280 − (−4190)
IRR = 10.70 %
▪ Profitability Index - Also known as the benefit–cost ratio, the profitability index is the net
present value of all future expected cash flows divided by the initial cash investment. (Some
firms do not discount the cash flows in making this calculation.) If this ratio is greater than 1.0,
the project may be accepted.
Let us assume that we want to invest JOD 25,000 and the cash inflows will be 8,000, 10,000, and
13,000 with discounting rate 5%
0 1 2 3
56
PROJECT INITIATION
ANALYSIS UNDER UNCERTAINTY — THE MANAGEMENT OF RISK
▪ For the most part, risk has been interpreted as being unsure about project task durations
and/or costs, but uncertainty plagues all aspects of the work on projects and is present in all
stages of project life cycles.
▪ Uncertainty - when a decision maker has information that is not complete and therefore
cannot determine the expected value of each alternative
57
PROJECT INITIATION
ANALYSIS UNDER UNCERTAINTY — THE MANAGEMENT OF RISK
Risk Analysis
▪ Principal contribution of risk analysis is to focus the attention on understanding the nature
and extent of the uncertainty associated with some variables used in a decision-making
process. Usually understood to use financial measures in determining the desirability of an
investment project.
▪ Probability distributions are determined or subjectively estimated for each of the “uncertain”
variables. The probability distribution for the rate of return (or net present value) is then
found by simulation. Both the expectation and its variability are important criteria in the
evaluation of a project
58
PROJECT INITIATION
Feasibility Study
59
PROJECT INITIATION
How To Conduct A Feasibility Study
▪ What
✓ An assessment of the practicality of a proposed plan or method.
✓ Is this “Feasible” ?
• Do we have what is needed to do this?
• Will we get our Return On Investment (ROI)?
▪ When
✓ During a project lifecycle
✓ After the business case
▪ Why
✓ Determine the factors that will make the business opportunity a success
60
PROJECT INITIATION
How To Conduct A Feasibility Study
▪ How
▪ Feasibility Report
✓ Conduct a preliminary analysis
✓ Executive summary
✓ Prepare a projected income statement
✓ Description of project
✓ Conduct a market survey (is this a demand?
✓ Market place
Is there a market for this?)
✓ Marketing strategy
✓ Plan business origination & operations
✓ Required resources
(what kind of resources do we need)
✓ Schedule
✓ Prepare an opening day balance sheet
✓ Financial projections
(inflows and outflows to determine if we
✓ Findings and recommendations
are going to make our ROI)
✓ Review and analyze all data
✓ Make Go/No-Go decision
61
PROJECT INITIATION
2. Selecting a Project Manager
62
2. Selecting a Team for designing a hospital building
▪ We assign the PM
✓ Architect … Functional Manager ……Team
✓ Structure ….. Functional Manager ……Team
✓ MEP …. Functional Manager ……Team
✓ ID …. Functional Manager ……Team Project Team
✓ Health care planner
✓ Health care equ. Provider
✓ Cost engineers ( budget +QS) …. Functional Manager ……Team
✓ H&S specialist
✓ Lighting specialist
63
PROJECT INITIATION
2. Selecting a Project Manager
64
PROJECT INITIATION
2. Selecting a Project Manager
65
PROJECT INITIATION
2. Selecting a Project Manager
✓ The career path often starts with participation in small projects, and later in larger projects,
until the person is given control over small, then larger projects
66
PROJECT INITIATION
2. Selecting a Project Manager
67
PROJECT INITIATION
2. Selecting a Project Manager
70
PROJECT INITIATION
2. Selecting a Project Manager
71
PROJECT INITIATION
2. Selecting a Project Manager
72
PROJECT INITIATION
2. Selecting a Project Manager
▪ Breadth of Communication
✓ Most of the project manager’s time is spent communicating with the many groups interested
in the project
✓ Considerable time must be spent selling, reselling, and explaining the project
✓ Interested parties include:
• Top management
• Functional departments
• Clients
• Members of the project team
✓ To effectively deal with the demands, a project manager must understand and deal with certain
fundamental issues:
• Critical to have the support of top management
• Build and maintain a solid information network
• Must be flexible in many ways, with as many people, and about as many activities as
possible throughout the life of the project
73
PROJECT INITIATION
2. Selecting a Project Manager
74
PROJECT INITIATION
2. Selecting a Project Manager
75
PROJECT INITIATION
2. Selecting a Project Manager
76
PROJECT INITIATION
2. Selecting a Project Manager
77
How organizational structure affects projects
78
How organizational structure affects projects
79
How organizational structure affects projects
80
How organizational structure affects projects
1. Functional Organizational Structure
Advantages of using the functional elements of the parent organization as the administrative
home for a project include:
81
How organizational structure affects projects
1. Functional Organizational Structure
There are also disadvantages to housing the project in a functional area:
82
How organizational structure affects projects
1. Functional Organizational Structure
83
How organizational structure affects projects
84
How organizational structure affects projects
2. Project Based Organizational Structure
Advantages of a pure project organization:
✓ The project manager has full line authority over the project
✓ All members of the project workforce are directly responsible to the project manager
✓ When the project is removed from the functional division, the lines of communication are
shortened
✓ When there are several successive projects of a similar kind, the pure project organization can
maintain a permanent cadre of experts who develop skills in specific technologies
✓ A project team that has a strong and separate identity and develops a high level of commitment
from its members
✓ Because the authority is centralized, the ability to make a swift decision is enhanced
✓ Unity of command exists
✓ Pure project organizations are structurally simple and flexible, which makes them relatively easy
to understand and implement
✓ The organizational structure tends to support a holistic approach to the project
85
How organizational structure affects projects
86
How organizational structure affects projects
2. Project Based Organizational Structure
87
How organizational structure affects projects
2. Project Based Organizational Structure
88
How organizational structure affects projects
3. Matrix Organizational Structure
Matrix organizations blend features of project-based and functional organizational structures.
The key challenge with a matrix organization is that every employee has two (or more) managers
they report to, their Functional Manager and the Project Manager. If they are working on multiple
projects, they may have even more managers to report to.
– Project manager has some authority
– Resources report to two managers
– Project manager and staff work full time in a strong matrix
There are three types of matrix organizations:
▪ Weak Matrix
▪ Balanced Matrix
▪ Strong Matrix
89
How organizational structure affects projects
Weak Matrix
A weak matrix organizational structure maintains many of the features of the functional
organizational structure. The role of the Project Manager is more that of a Project Coordinator.
Their ability to make or enforce decisions is low and most of the authority remains with the
Functional Manager.
90
How organizational structure affects projects
Balance Matrix:
A balanced matrix organizational structure recognizes the need for a Project Manager. However,
the Project Manager does not have full authority over the project, project staff or project budget.
91
How organizational structure affects projects
Strong Matrix:
A strong matrix organizational structure has many of the features of the projectized organizational
structure. They have full-time Project Managers and project administrative staff. Project Managers
have considerable authority over the project in this organizational structure.
92
How organizational structure affects projects
3. Matrix Organizational Structure
As with other organizational forms, the matrix organization has its own unique advantages:
93
How organizational structure affects projects
3. Matrix Organizational Structure
There are also disadvantages to using the matrix organization; most involve conflict between the
functional and project managers:
✓ The balance of power between the project and functional areas is very delicate
✓ The movement of resources from project to project may foster political infighting
✓ Problems associated with shutting down projects can be as severe as in a pure project
organization
94
How Organizational Structure Influences Project
Management:
Two of the key project aspects affected by organizational structure types are Project Manager Authority and Resource
Availability.
95
How Organizational Structure Influences Project
Management:
96
How Organizational Structure Influences Project
Management:
97
How Organizational Structure Influences Project
Management:
98
PROJECT INITIATION
3. Prepare the project charter
▪ A project charter is a vital document that formally authorizes the existence of a project. A
project charter depicts how the success of a project will be measured
▪ In reality, no one embarks on a journey without a clear direction, the same principle is applicable
in Project Management. A project manager that embarks on a project without the project
charter is bound to fail.
▪ As a project manager, you must painstakingly prepare your project charter before the project is
kick-started, and by doing so, you are assured of achieving mind-blowing success.
99
PROJECT INITIATION
3. Prepare the project charter
▪ Overview of the project: this addresses the name of the project, author of the charter,
creation date, project manager, and the purpose of the project.
▪ Project details: in this is the detailed project description which includes the project’s
mission, the general scope of the project, relevant stakeholders, and clients.
▪ Project scope: this highlights how the project will be executed. In a project charter scope
example, you have the details such as project objectives, goals, deliverables, assumptions, risks,
and other constraints.
▪ Project team organization: in this, you have the list of the team members that will be
involved in the execution of the project. It can also include their roles in the project.
100
PROJECT INITIATION
3. Prepare the project charter
▪ Project resource planning: this states the resources that will be used in the implementation of
the project.
▪ Project communication plan: this helps in explaining the communication plan that will be used
to manage the changes that could arise in the project to ensure that the set goals and objectives
are achieved.
▪ Project timeline: this helps you to have an idea of what the timeline of the project will look like.
This assists in the thorough management of the project schedules.
101