BD Manager: Conrad/Shrinath Garg P.C.Shukla A Mahendra Lead Engg: CS Pradhymuna Saroj Kazi Project Procurement Bino Baby Legal : Sayak Chandra Sunita Thawani Financial Manager Abhishek Chatterjee Accounts Manager Shweta Gupta Construction Repr. T.Rajesh / Sivaji priya Date of Technical Bid Submission: 7/09/10 ; Date of Price Bid Submission: 7/09/10 : 13:00 hrs @ Mangalore S No. Description Responsibility Follow-up & Date Checked by
1. Approval from MD for EMD , Participation and AB AM/SK 27.08.10
signing of bid by GM 2. Preparation of Bid security in the form of BG for AB/SG SK 2.09.10 an amount of Rs.4000000/- (forty laks only) validity for 150 days. 3. Understanding of scope of work and deciding the AV/RB PCS/AM/SK 29.08.10 packages /AB/SG/SK/MBKR/CEF/shrinath 4. Study of Tender Documents. AB/SG PCS/AM/SK 27.08.10 PKB/MBKR/CSP/RB/CEF/shrinath /SK
5. Queries from all department to be submitted to AB/CEF/Shrinath PCS/AM 29.08.10
BD for collation 6. Due diligence to Site and its report AB/ /Shrinath/CSP PCS/AV 29.08.10 to 01.09.10 7. Prebid Meeting AB/Shrinath/CSP PCS/AM 31.08.10 8. Request for Legal Vetting and preparation of AB/Shrinath SK/AM 25.08.10 POA 9. Risk Analysis AB/CEF/SK/SD/TR/Shrinath MD/PCS/AM 3.09.10 10. MD presentation on Major packages, DD finding, AB/SK/SD/CEF/AM/Shrinath/AC MD/PCS/UM/ 3.09.10 Tax structure, Competition, Strategy. VS/AV/Sunita Thawani/Rituraj Sinha 11. Preparation of Technical Bid AV/CSP/AB/SG/RB PCS/SK 5.09.10 a. Arrangement of Certificates/Credentials as per CEF/Shrinath PCS/AM 2.09.10 Project Charter for MSEZL Marine Outfall Pipeline System , at Mangalore Bid Manager: Ambhrin Bhattacharyya Mentors : Manish Sharma BD Manager: Conrad/Shrinath Garg P.C.Shukla A Mahendra Lead Engg: CS Pradhymuna Saroj Kazi Project Procurement Bino Baby Legal : Sayak Chandra Sunita Thawani Financial Manager Abhishek Chatterjee Accounts Manager Shweta Gupta Construction Repr. T.Rajesh / Sivaji priya Date of Technical Bid Submission: 7/09/10 ; Date of Price Bid Submission: 7/09/10 : 13:00 hrs @ Mangalore the requirements of Qualification Criteria b. Filling up Forms as per the Formats given in the SG/RB/AB SK 5.09.10 Tender Documents (Technical/Financial/Qualification) 12. This is an Item rate contract however BOQ given AV/CSP/UKS AV 31.08.10 by the client to be vetted by the design team. 13. Drawings and technical write up.
Deatails technical specification
Layout drawings with elevations and sections showing
Bidder’s proposed arrangement of plant. CSP/UKS /KK AV 3.09.10 Architectural drawings.
Terminal points.
General arrangement drawings of equipment.
Write ups of the work methodology AD/CSP/KK/MA AV 2.08.10
14. Enquiry for all Bought-Out Items AB/RB/SG/MBKR/JP SK 31.08.10 15. Receipt of comments and rates from approved AB/MBKR/SK/BB PCS 2.09.10 vendors for Bought-Out Items 16. Negotiation with vendors/package suppliers for PCS/SK/VS MD 5.09.10 major packages/high value supply items. 17. Preparation of Comparative Statement of the rates AB/MBKR/RB/SG PCS/SK 4.09.10 received from the Vendors Project Charter for MSEZL Marine Outfall Pipeline System , at Mangalore Bid Manager: Ambhrin Bhattacharyya Mentors : Manish Sharma BD Manager: Conrad/Shrinath Garg P.C.Shukla A Mahendra Lead Engg: CS Pradhymuna Saroj Kazi Project Procurement Bino Baby Legal : Sayak Chandra Sunita Thawani Financial Manager Abhishek Chatterjee Accounts Manager Shweta Gupta Construction Repr. T.Rajesh / Sivaji priya Date of Technical Bid Submission: 7/09/10 ; Date of Price Bid Submission: 7/09/10 : 13:00 hrs @ Mangalore 18. Pre-Bid Tie-up/ MOU with the approved vendors AB/SK/BB PCS 5.09.10 19. Enquiry to contractors and receipt of rates from AB/RB/SG SK 31.08.10 them 20. Rate analysis for pipe laying job (based on the DD PKB/AB/RB 1.09.10 report) 21. Negotiation with the pipe laying and civil BB/AB/SK/SD /VS MD/PCS 4.09.10 contractor 22. Pre-bid Tie-up with the contractor if reqd. AB/BB/SK PCS 5.09.10 23. Comparative Statement for rates of brought out AB/RB/SG SK 5.09.10 items and civil rates with existing Contract rates, Market rates, Dept. Estimate and SOR Rates 24. Tax structure for Estimation to be approved by AC PCS/UM 31.09.10 CFO 25. Collection of internal Estimate and the probable CEF/Shrinath AM 2.09.10 competitors. 26. Competitors activity and analysis of competition CEF/Shrinath AM/PCS 3.09.10 27. Preparation of Final Costing taking Tax Part & AB SK/AC 5.09.10 Overhead 28. Preparation of Profitability Statement and Final AB SK/AC 5.09.10 Pricing 29. Joint checking of price build up with FA AB/AC UM/PCS 6.09.10 30. Pricing decision by GM, WSD/MD MD/PCS 6.09.10 31. Management Approval for Final Price indicating PCS MD 6.09.10 the name of other intending bidders 32. Final Bid- Technical + Price Bid AB/SG 6.09.10 a. Technical Bid Finalisation SG/RB AB/SK 5.09.10 Verification with check list and list of submittals Project Charter for MSEZL Marine Outfall Pipeline System , at Mangalore Bid Manager: Ambhrin Bhattacharyya Mentors : Manish Sharma BD Manager: Conrad/Shrinath Garg P.C.Shukla A Mahendra Lead Engg: CS Pradhymuna Saroj Kazi Project Procurement Bino Baby Legal : Sayak Chandra Sunita Thawani Financial Manager Abhishek Chatterjee Accounts Manager Shweta Gupta Construction Repr. T.Rajesh / Sivaji priya Date of Technical Bid Submission: 7/09/10 ; Date of Price Bid Submission: 7/09/10 : 13:00 hrs @ Mangalore Verification of EMD b. Price Bid Finalisation AB PCS 6.09.10 33. Physical Submission of the Bid at Mangalore AB SK 7.09.10 AB = Ambhrin Bhattacharya AC = Abhishek Chatterjee AD = Amlan Dutta AKC = Ashok Kumar Chauhan AM = A Mahendra AV = Arvind Verma BC = B Chandrasekhar JP = Jayant Papneja KK = Kundan Kanth MBK = MBK Raju PCS= P C Shukla RB = Rajat Banerjee SB = Satyajit Bakshi SD = Sumit De SK = Saroj Kazi UM = U Mishra VS = Viren Sinha SKM = Smar Kumar Mitra DK = Debashis Karmakar MC = Manas Chakraborty BRP = Bipul Ranjan Pal AM = Abhishek Mukherjee PS = Pradipta Sarkar GD = Goutam Das SS = Sudip Sengupta Project Charter for MSEZL Marine Outfall Pipeline System , at Mangalore Bid Manager: Ambhrin Bhattacharyya Mentors : Manish Sharma BD Manager: Conrad/Shrinath Garg P.C.Shukla A Mahendra Lead Engg: CS Pradhymuna Saroj Kazi Project Procurement Bino Baby Legal : Sayak Chandra Sunita Thawani Financial Manager Abhishek Chatterjee Accounts Manager Shweta Gupta Construction Repr. T.Rajesh / Sivaji priya Date of Technical Bid Submission: 7/09/10 ; Date of Price Bid Submission: 7/09/10 : 13:00 hrs @ Mangalore KH = Kashinath Haldar BB = Bino Baby MA = Manish Abhishek CEF = Conrad Fernades