Professional Documents
Culture Documents
RA For HV and MV Installation Rev0
RA For HV and MV Installation Rev0
Below is assessment for hazards/risks defined for the safe working method for EXCAVATION, FORMATION, PIPE LAYING AND BACKFILLING FOR
HV and MV cable installation Assessment consulted by
Construction Manager.
1. QA / QC Manager/Engineer
2. Site Supervisor
3. Safety Manager / Officer and
4. Operators and Crew.
while it was prepared by the engineer executing the work with safety manager aid, and finally reviewed and approved by project manager.
Sequence of Work:
Excavation, pulling cable and Backfilling for HV and MV installation executed as per following sequence of work:
1. Trial Hole
2. Trench Excavation
3. cable Laying
4. Backfilling
Hence, following risk assessment prepared to evaluate and control related risks and following conditions shall be considered:
1. Once the Risk Assessment/ Method of statement will be approved it shall be circulated and record training to all relevant personnel to the work.
2. In case of any changes to the working procedures, or involving any new equipment, the document shall be revised.
3. In case of any accident/ incident relevant to the task, the risk assessment shall be reviewed.
Related Documents:
Risk Matrix:
PROBABILITY Severity
Insignificant (1) Minor (2) Moderate (3) Major (4) Catastrophic (5)
Rare (1) 1 2 3 4 5
Possible (2) 2 4 6 8 10
Likely (3) 3 6 9 12 15
Often (4) 4 8 12 16 20
Frequent/Almost Certain
5 10 15 20 25
(5)
Absolutely Unacceptably High
15 - 25 Extreme Risk
Activity or industry should not proceed in current form
Unacceptably High
8 - 12 High Risk Activity or industry should be modified to include remedial planning and action and be subject to detailed HSE
assessment
Acceptable but must be managed at “As Low as Reasonably Practicable” (ALARP)
4–6 Moderate Risk
Activity or industry can operate subject to management and / or modification
Acceptable without required further action.
1 -3 Low Risk
No action required unless escalation of risk is possible
R/
Personne Risk Respo
A Hazard Res.
Activity Risk l involve Ratin Control Measure nsabili
R Risk
d g ty
ef.
00 General Comply with the legal, contract, local, authorities, and best practices for severe weather conditions.
Mandatory PPE (Helmet, Hand Gloves, Reflective vest, Eye protection and Safety shoes) (EN/CE standard) t
PAGE \* MERGEFORMAT 2 | Page
For Official Use Only (FOUO)
o be provided for all site personnel, and specific to task to be provided for concerned personnel.
Training / TBT to be given to all involved personnel regarding (risk assessment, weather forecast, PPE, emer
gency procedure and evacuation plan) and to be recorded through the site superintendence in presence of E
HS rep.
Maintain adequate work supervision.
Reduce the human involvement for all the tasks as low as reasonably practical.
Don’t use any homemade tools, platform, unauthorized connection.
All tools, equipment, plants should possess valid documentation as per local authority.
Comply with any instructions from engineer, contractor EHS representative.
Emergency contact details/ procedure shall be fixed at all working areas.
Adequate signage should be fixed all areas of works, and to be in adequate languages can be understood by
workforce.
During unfavourable weather condition (Humidex exceeding 54 C⁰ (TWL < 115)/ Wind speed exceeding 38 K
ph/ Visibility less than 50 m/ heavy rains) works should be suspended or break should be implemented as per
OSHAD requirements.
Prepared By
Reviewed By
Approved By