Project Name: Design & Build Data Centers -Tier III- in Riyadh & Jeddah”
Project Code : 068/2022
DCRJ-RIY3-DOC-EL-029 DCRJ-RIY3-ELEC. SHOP DRAWING SCHEDULE -01-231119
19-Nov-23
Project Engineer Project Manager Date Name Signature Date
Contractor Highlights
SHOP Earthing & Lightning Protection Earthing & Lightning Protection Earthing & Lightning protection schematic diagrams are
13- 00 Electrical EGEC C Included MMR
DWG System Floor Plans System Floor Plans missed.
SHOP
14- Lighting System Floor Plans Lighting System Floor Plans 00 Lighting Control Schematic Diagram is missed. Electrical EGEC C Included MMR
DWG
SHOP
15- Central Battery System Floor Plans Central Battery System Floor Plans 00 Central Battery System Calculations are missed. Electrical EGEC C Included MMR
DWG
SHOP
16- Builder Work Builder Work 00 Builder work Layouts for upper floors are missed. Electrical EGEC C Included MMR
DWG
The following calculations are missed:
SHOP a. LV Cable Sizing Calculations.
17- Calculations Calculations 00 Electrical EGEC C Included MMR
DWG b. Cable Tray & Cable Trunking Calculations.