Professional Documents
Culture Documents
Construction Report of The New MPA Hotel, Lahore (Building Construction and Technology Course)
Construction Report of The New MPA Hotel, Lahore (Building Construction and Technology Course)
Construction Report of The New MPA Hotel, Lahore (Building Construction and Technology Course)
SURVEY REPORT
ADVISOR: DR. MUHAMMAD YOUSAF
2.1 Major Building Components ........................... 5 2.12.7 CCTV Cameras & HT LT Panels .............. 11
2.1.3 Storage Tank for Fire Fighting ................. 5 2.13.1 Punctured Slab ...................................... 11
2.1.4 Over Head Water Tank............................ 6 2.13.2 Chilling Units and Exhausts ................... 11
2.2 Main Building Covered Area ........................... 7 3.2 Rendering and Floor Finishing ...................... 12
2.5 Lift Details ....................................................... 8 3.5 Material and Machinery Used ...................... 13
2.6 Two Towers and Elevation .............................. 9 3.6 Compression Test Reports ............................ 14
1
1 INTRODUCTION TO PROJECT
Project is named as “CONSTRUCTION OF MPA's HOSTEL LAHORE, PHASE-II”. On February 9th, 2022, Chaudhry Parvez Elahi,
the Acting Governor of Punjab, initiated the construction of MPAs Hostel Phase-II, located next to the existing MPAs
Hostel. The project has been estimated to cost 2500 million as said by the Project SDO Moeed.
1
1.3 EXISTING MPA HOSTEL
In 1988, a project was initiated to build housing for members of the Assembly, with architect Nayyar Ali Dada appointed
as consultant. The construction was planned for the western lawn of the Assembly building, with Block A as a semicircular
building and Block B as rectangular. Block A was divided into two phases, with Phase I consisting of a basement, ground
floor, and four residential floors containing 36 suites. Construction of Phase I began in 1988 and was completed in 1992.
Phase II was originally planned for 72 residential units but was later revised to 40 suites, each consisting of a lounge,
bedroom, office, kitchen, and two bathrooms.
2
1.5 PROJECT SUMMARY
Following is the project briefing as specified by the site engineer and data available on official website.
The project faced further challenges due to political interventions and changes in government, and inflation affected the
import of machinery from Japan and Europe. Operating the 2000-ton plant was also difficult which causes the entire
structure to vibrate. Warranty was also an issue due to a lack of knowledge in how to work with the imported machinery.
It just deteriorated over time and was out of use when the project was started again.
3
1.7 CONSERVATION OF INTERNATIONAL HERITAGE
The building of Provincial Assembly of the Punjab was built on Shahrah-e-Quaid-e-Azam, (The Mall) Lahore. It is an
archeological declared building, and it is under UNESCO. Sandstone has been imported from Jaipur, India in the style of
an old building in the front of the new building of the assembly. Sandstone has higher costs. RAJHISTAN and Aagra
sandstone was utilized in the construction before partition.
After partition, it must be renovated. From India, it was exported to Dubai and then to Karachi port from where it was
brought to Lahore. It has been maintained by CNW. We can't change color without permission or Punjab assembly will be
cased for such act. For International heritage conservation, we don't have experts for the design and guidance so that they
can give better suggestions and ideas. In 1934, British had the concept of central air conditioning system and it's not new
for them and those chillers and ducting are still maintained in their original forms till now.
• Integration of project activities: SAP integrates different project activities such as planning, scheduling, resource
allocation, budgeting, and tracking into one system.
• Resource management: It can track resource availability, utilization, and allocation, ensuring that resources are
optimally used to complete the project.
• Financial management: SAP provides tools for budgeting, costing, and financial management.
• Reporting and analysis: It allows project managers to monitor progress, identify issues, and take corrective actions
as needed.
4
2 SCOPE OF WORK
The building is comprising of ten storeys having two Basements & Ground + six storeys. The Main Building having one
hundred and four Suites, Laundry, Prayer Hall for one hundred and seventy five persons, I.T Rooms, Accommodation for
two hundred and fifty drivers, Security Rooms, Gymnasium, Gaming Area and two Mini conference rooms for thirty
persons.
• Relocation of Tunnel
Planning sets the stage for construction, yet construction phase evolves it further.
Due to the presence of a mosque and its minaret, there is a consideration to relocate
the underpass. The site engineers have suggested shifting the location of the
underground tunnel to address the issue of minaret as it is a part of international
heritage. The tunnel has a width of 30 feet and starts at 60 feet as shown in the
detailed plans. Tunnel cost 64 million for its construction.
• Walls of Tunnel
To ensure stability and support, the walls of the underpass are designed to be pile retention and load bearing. The slope
for the underpass was maintained between 1/8 and 1/9, and the layout was drawn accordingly. In a proactive approach
to save time, separate retaining walls were not provided.
In summary, the construction of the underpass is a strategic solution to prevent road blockages, but careful considerations
are being taken to ensure it meets safety standards and respects the surrounding environment.
The storage tank provides a large quantity of water that can supply multiple fire sprinkler systems at once, ensuring that
there is enough water to combat a large fire. These tanks are often required by building codes and regulations, and their
capacity is based on the size and type of the building or facility they are intended to protect.
5
2.1.4 Over Head Water Tank
Water supply system is divided for each tower and two separate tanks are provided to meet the requirements of each.
There was a 35000 gallons per water tank was provided. There was an additional water tank for the purpose of fire
extinguisher system as specified above.
Retention piles were constructed to prevent the surrounding buildings from collapsing due to the excavation up to twenty-
eight feet. The pressure exerted on the soil could have caused significant damage to the 3-storey high buildings that are
present in the surroundings of the project. The process of casting five hundred and twenty-one piles and placing anchors
would have taken about a year, and consultation with a geotechnical engineer was done to know the possibilities of
reducing this time. The pile depth was calculated to be forty to forty-two feet with anchors and sixty feet without anchors.
The diameter of the piles remained the same while the depth was increased where a six-inch gap was maintained between
two piles.
6
2.2 MAIN BUILDING COVERED AREA
Following is the distribution of covered area within the building.
7
2.4 SUITE DETAILS
Each Suit having the area of one thousand and five hundred sq meter. There are six identical floors each having sixteen
suits. Ground floor has other services along with eight suites and seventh floor has sports room and gymnasium. Detail
for suits among each storey is provided as follow.
Floor plans are given as follow that represents the placement of suits and other rooms within two towers.
8
Elevator Type Number Size
Passenger Lifts 4 Nos. 7x6 feet
Luggage Lifts 2 Nos. 9x 9 feet
Service Lifts 2 Nos. 9x7 feet
Total No. of Lifts 08 Nos.
2.7 COURTYARD
Slope should be maintained in the courtyard, but one may feel it during walking on the ground surface.
Solution was that the courtyard is divided into two parts where slopes run down towards the opposite
direction on both sides. In case if there will be water during washing and cleaning. Otherwise, roof is
covered and there will be no rainwater to accumulate in courtyard.
9
2.10 TAPERED SLABS
A tapered slab, also known as a waffle slab, is a type of reinforced concrete slab used in building construction. It is a two-
way concrete system with a grid-like pattern of ribs and voids that create a waffle-like appearance. The voids in the slab
help to reduce the weight of the structure while maintaining its strength. Tapered slabs are commonly used in high-rise
buildings, commercial buildings, and industrial facilities due to their high strength and load-carrying capacity. They are
also preferred for their excellent thermal and acoustic insulation properties.
Elevator walls can serve as shear walls in a building. These walls are
located around the elevator shaft and are designed to resist lateral forces.
The elevator walls are typically constructed of reinforced concrete or
other materials that provide high strength and stiffness. The elevator
walls serve the purpose of a shear wall by transferring lateral forces from
the upper floors of the building to the foundation.
Since the Shear walls/Lift Cores are the Major Components of a structure
to withstand the lateral stresses due to seismic activity. From the
inspection, Voids in the concrete wall were observed. Due to which Wall
Vertical and Transverse Steel was exposed to environment. These voids
may lead to the reduction of the structural strength and stability. Honey
combing was observed.
2.12 FACILITIES
Fire Fighting, Fire Alarm System, Telephone, Networking, H.T/L. T Panel, and CCTV Camera costs the total of 144 million.
Air conditioning system costs 81 million alone. State of the art facilities include:
10
2.12.4 Internet System
Routers are installed in each room to provide a strong and secure Wi-Fi connection. The internet system provides high-
speed internet connectivity to the occupants of the building, enabling them to stay connected with the world.
11
3 OBSERVATIONS AND MATERIALS
The pressure test is typically carried out after the ductwork has been installed and before it is
commissioned. During the test, the ductwork is sealed at all joints and connections, and a
specialized blower is used to pressurize the system. The pressure is typically maintained for a
specified duration, during which any leaks in the system will cause a drop in pressure. Pressure
is checked through pumps now a days. Traditional method is still in use where ducts are filled
with water up to a certain level. If there is a drop, then it means that there is leakage
somewhere in the system.
12
Shuttering, also known as formwork, is a temporary structure used to support the concrete or other materials that are
poured into it to form a desired shape or structure. It is typically made of wood, steel, or other materials and is used to
mold and support concrete or other materials until they harden and gain sufficient strength.
13
Cement Mixer Roller for Compaction Tubewell
14
3.7 OBSERVATIONS AND RECOMMENDATIONS
After general inspection, following observations were made.
During the Building Inspection it was observed, Steel bars were dumped on the Natural Ground instead
Mixing and Placement of Concrete were not of placed on any Wooden Pad. Steel bars should not be
properly done as the voids in beams slab face. And dumped on the Natural ground to avoid the rusting of
the Exposed steel was noticed. Mix Design and the rebars.
Placement of Fresh Concrete should be checked by
proper compaction to eliminate voids in concrete.
From the visual inspection, Irregularities in Slab No safety equipment was provided to workers working
Thickness was observed due to improper formwork. on the site. Worker’s safety equipment should be
Irregularities in Slab Thickness should be removed provided to confirm the worker's safety.
by ensuring the alignment of the formwork.
15