Area=20000 ha

Ct=5.4
Cp=0.5
L=110000 ft
Lc=80000 ft

110000 80000 0.3


𝑡𝑙 = 𝐶𝑡 (𝐿𝐿𝑐 )0.3 = 5.4( . ) = 30.348 ℎ𝑟
5280 5280

𝑡𝑙 30.348
𝑡𝑟 = = = 5.517 ℎ𝑟
5.5 5.5

𝑡𝑟
𝑡𝑝 = 2
+ 𝑡𝑙 =33.10 hr

𝑡𝑏 = 3𝑡𝑝 =99.3 hr (the first trial)

20000
640 𝐶𝑝 𝐴 640 ∗ 0.5 ∗ 258.99
𝑄𝑝 = = = 814.55 𝑐𝑓𝑠
𝑡𝑙 30.348
830 830
𝑊50 = 𝑄𝑝 = 814.55 = 62.17 ℎ𝑟 1:3=20.72 hr 2:3=41.45 hr
( )1.1 ( )1.1
𝐴 20000/258.99

830 470
𝑊75 = 𝑄𝑝 1.1 = 814.55 = 35.22 ℎ𝑟 1:3=11.74 hr 2:3=23.48 hr
( ) ( )1.1
𝐴 20000/258.99

Time Q
0 0
9.38 407.275
18.36 610.9125 1000
30.1 814.55 800
53.58 610.9125 600
Q

71.6 407.275 400


99.3 0 200
0
0 50 100
Time
Check the 5.5hr-Snyder UH:
Area
T Q
cfc.hr
9.38 407.275 1910.12
8.98 509.0938 4571.662
11.74 712.7313 8367.465
23.48 712.7313 16734.93
18.02 509.0938 9173.869
27.7 203.6375 5640.759

Area
46398.8
under the
cfs.hr
curve

Runoff Volume= 167035695.75 ft3


167035695.75
Runoff Depth= = 0.0775 𝑓𝑡 = 0.93 𝑖𝑛
20000∗107639.104

The expansion of tb:


The area of the last triangle: 5640.759*3600= 20306732.4 ft3
For a 1in UH the area under the curve must be: 1in/12* 20000*107639.104=179398506.7 ft3
The difference: 12362810.95 ft3
27.7(20306732.4+12362810.95)
∆t= 20306732.4
=44.56 hr

The time which should be expanded: 44.56-27.7=16.86 hr


Therefore, the modified and final tb=16.86+99.3=116.6 hr

The new and expanded 5.5hr-Snyder UH: 1000

Time Q 800
0 0 600
Q

9.38 407.275
400
18.36 610.9125
30.1 814.55 200

53.58 610.9125 0
71.6 407.275 0 50 100 150

116.16 0 Time
Check the area under the curve:

T Q Area
9.38 407.275 1910.11975
8.98 509.0938 4571.66188
11.74 712.7313 8367.46488
23.48 712.7313 16734.9298
18.02 509.0938 9173.86938
44.56 203.6375 9074.087

Area
under the 49832.1326cfc.hr
curve

Runoff Volume= 179395677.45 ft3


179395677.45
Runoff Depth= 20000∗107639.104 = 0.0833 𝑓𝑡 = 0.999 𝑖𝑛