Professional Documents
Culture Documents
Effectsof Inadequate RPMon Costand Qualityinthe Garment Industry
Effectsof Inadequate RPMon Costand Qualityinthe Garment Industry
net/publication/332439909
CITATIONS READS
0 299
1 author:
Walker Sterlin
Instituto Tecnológico de Santo Domingo
1 PUBLICATION 0 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Effects of machine speed RPM in the Garment and Fashion insdutry View project
All content following this page was uploaded by Walker Sterlin on 16 April 2019.
1. Why the operator's cycle time resulting from the study does not match the
mathematical value corresponding to the preset RPM of the machine?
2. How much impact the variance accounts for in productivity?
3. What would be an effective "productivity at the source" solution to prevent this first
effect.
In order to correctly answer the first question, first the distribution of the time study must
be analyzed and understood. A good study will include different times of the day, say at
least morning and afternoon, different levels of operators (slow, medium, and fast) for the
same operation, and about 10 parts each time. Therefore the study generates at least 60
data, enough to define a distribution, which not necessarily is a normal distribution and
hence statistical mean or average may not be representative.
Average cycle time from the study is 18.92 seconds. But is it really a fact, when you have
time as much as 27.68 seconds, more than 46% higher, or as low as 12 seconds or 36.5%
lower? Using 18.92 seconds as cycle time which would be the tendency of most factories,
would be a gigantic mistake and any plan made on this number, incentives, customer
delivery dates, and even product cost and gross margin, would be at very high risk.
This study presents the following distribution, in which it can be observed that in spite of
being a normal distribution (p-value =0.0516), because of the dispersion between time
samples the mean is no significant for the production process.
Time studies in any industry have three important characteristics that must be looked at:
skewness, kurtosis and coefficient of variation, and specially in the fashion industry using
sewing RPM, as all three of them will have an effect on RPM. In our particular case study
it is observed
• a slightly skewed distribution to the right (0.52) meaning that there exists a bit more
frequent repetitions of times lower than the mathematical mean. The higher the
skewness value, the more disqualified would be the average time, the mean, to be
used as cycle time of the operation.
• a negative kurtosis (using a software which in turn uses the G2 formula with a
correction factor of -3 for excess kurtosis, so that a normal distribution would have a
kurtosis of zero) meaning that the distribution is platykurtic (flat and dispersed). The
more platykurtic is the time study, the higher the uncertainty of meeting production
goals would be using the average time as cycle time
• a coefficient of variation relatively high, 19%. This is basically a summary of the
amount of variation present in the distribution. In this case study it tells us on the
volatility of productivity. Productivity can "evaporate" at a rate of 19%. This is a high
risk for cost.
Understanding the distribution (in plain language the behavior) of the time study is thus a
first and important step in any process balancing in any type of industry and even service.
But in sewing what is its relation with RPM? Logically speaking one cannot operate any
machine faster than the maximum machine speed itself, which is given by the motor
driving the speed. Therefore it is evident that there exists a regression formula which
correlates both factors: RPM and cycle time. The given formula is:
Machine RPM = (SPI X loop length X 60)/cycle time
where the loop length is the length of the part to be sewn, and SPI is stitches per inch.
This equation expressed in term of cycle time is:
Cycle time = (SPI X loop length X 60)/Machine RPM
At the time of the study, the machine had a preset speed. Hence it can be calculated
mathematically what the expected cycle time should be; and vice versa given the cycle
time from the time study it can be calculated what is the corresponding machine speed.
In either case, the difference between the theoretical expected value and the actual
observed value is the first effect of setting RPM in the garment and fashion industry in
general.
In this case study the preset speed is 3550 RPM. The SPI as per customer requirement
was set at 12 stitches per inch and the loop length for this sewing section of the garment
was 78.74 inches. Given those conditions and the 18.924 seconds average cycle time if
used, the expected RPM by mathematics should of been 2996 RPM and not 3550, leading
to the conclusion of the negative impact on productivity of -16%
1. As the preset speed was 3550, let us vary as much as a wide range possible, the
RPM. We will use the range from 2000 to 6000 with and increment of 100. This will
give a large enough of RPM spectrum.
2. For each RPM increment, we calculate from the equation above the expected CT,
which we called Standard cycle time below.
3. From the descriptive statistics we have a CV of 19%, therefore let us vary over a
range of -19% to 19% the CV, to create different scenarios.
The following learning curve is the result or the plot of above table distribution with a zoom
on step 3.
Using this learning curve for training, shows either by how much should we set RPM for
the trainee according to his efficiency performance while in training, or what efficiency
should we ask him per out setting of RPM. So the recommended use is to start at a certain
RPM as low as possible on the first day of training and keep increasing RPM every time
he consistently reach the expected cycle time within the range provided. This way he
being trained on faster and faster machine and is expected to math the theoretical value
once release to production. This is standardization of speed and cycle at the source, what
we previously denominated "productivity at the source" solution.
We found therefore that it is necessary for the garment industry to also realized some
design of experiments, DOE, to capture the impact of setting the machine RPM at a speed
greater or lower than the operator acquired skill from the RPM-cycle time learning curve
above. A DOE of this type should at the least consider RPM as one of the factor, operator
efficiency as a second factor, SPI stiches per inch as a third factor, making it a 2x3
experiment, and if desired the type of fabrics material being sewn as a fourth factor for a
2x4 DOE. And as the interest is on the effect of RPM on quality and productivity the
response to look for in the DOE is dimension variation, that is either stretching or shrinking
of the fabrics. The industry may also want to study the probability of other quality defects
and include in the measure responses potential quality related issues such as missing
stitches, potential result from pushing in the fabrics at a low speed by a fast operator, or
again defects such as holes from holding back on fabrics at a high speed by a slow
operator.
Those are the different effects of RPM that should not be neglected when seeking a
productivity improvement in the fashion manufacturing industry.
24 treatments are randomly ran and the results in dimension variation is shown on the
following table, yellow column. The effect of an appropriate setting of speed relative to
operator's skill measure in time (cycle time) is already visible in the results, as predicted
above. There are negative numbers meaning shrinkage of the piece of the garment,
positive numbers meaning stretching of the piece, and zeros meaning the sewn piece has
the same dimension before and after sewing.
To determine whether the difference in settings of the pair (RPM/Operator
Capacity) means, is due to random chance or are statistically significantly different, an
ANOVA F-test is performed as we recommend to do on any DOE. Any design of
experiment implies that one is looking for a model that correlates the individual factors
and their combinations to the response recorded. The coefficient of determination R
squared is 60% and a sensitive analysis of the residuals allow to conclude that correlation
between dimension variation and the factors is good enough. Confirming mathematically
the hypothesis of the effect of an inadequate RPM over product dimensions
specifications. In fact the ANOVA also shows that operators efficiency and machine
speed are quite significant in the model. This can be observed both in the P-values of the
parameters and the Pareto Chart of significance.
The F-ratio is equal to the Mean Square of the model divided by the Mean Square error
within the model. The Model F-ratio of 3.473 implies the model is significant.The p-value
('Probability of exceeding the observed F-ratio assuming no significant differences among
the means') of 0.0186 indicates that there is only a 1.86% probability that a Model F-ratio
this large could occur due to noise (random chance) only. In other words, the setting of
the factors differs significantly in terms of impact on dimensions or specifications.
An analysis of Main effects and Interactions of the results shows that both independent
variables RPM and Operator efficiency have opposite effects on dimension. An increase
in machine speed will increase stretching while an increase in operator efficiency will
reduce stretching. SPI behaves the same as RPM, but with a lighter slope. As for
interactions there are two relevant ones: SPI interacts with both RPM and Operator
efficiency
The main purpose of this research paper is to not only establish the probable impact of
machine speed, RPM, on quality and cost but also to provide a potential solution or
compensation to the effect. Just like the tailored learning curve for RPM-Cycle time
derived in part one from the time study, it is fundamental in the design of experiment to
be able to extract a guide capable of helping the factory who adopts the principles of RPM
effects to optimized the setting of machine speed for the prevention of a later customer
satisfaction issue, resulting from dimensions and specifications process related defects.
By using a surface and/or contour plot, it is possible to accomplish this objective. Contour
plot is a technique consisting of a graphic representation of the relationships among three
numeric variables in two dimensions, each variable in the desired range of operation. The
two variables are for the X and Y axes, and the third variable Z is for contour levels. The
contour levels are plotted as curves and color coded for range of responses. The surface
plot is a 3D representation of the contour.
In the particular case study which above results for the DOE, the contour plot is
highlighted next and reveals the different options of settings of the machine speed in RPM
according to operator efficiency in units per hour for a range of possible responses
of variation of the original specifications. As the optimal response would be no stretching,
and no shrinking, that is zero elongation, which we have circled in the legend of ranges,
what should be the RPM setting for ideally a regular average operator, not fast, not slow?
We have marked the answer with the two intersecting lines on the plot. A middle
efficiency operator (188 pieces per hour in that particular operation) for the blue range of
0 to 0.01 in of stretch would need an RPM close to 4775. This set guarantees the
sustainability of quality specifications over time.
However it is also revealed that RPM and the Operator efficiency has some kind of
interaction with SPI, stitch per inches. Therefore setting the RPM of the machine to an
average operator or even to a fast or slow operator, requires to go and verify that the
setting will not affect in turns the SPI specifications usually given by the customer. For
this it is necessary that from a contour plot of Operator efficiency versus SPI or RPM
versus SPI, it is verified why is the corresponding Stitches necessary to continue yielding
a zero or near zero dimension variation.
This contour plot of our case study is shown next and revealed that SPI can indeed be 12
as originally required by the customer specifications. In case it does not fall within the SPI
recommended by customers then it is necessary to discuss options with the customer on
the basis of the DOE and share the results so that a consensus can be obtained. However
it must be cleared that any consensus reached, it is what it is, a consensus and not the
optimum response to minimize RPM effect over dimensions specifications in quality.
Such a measurement would require a real-time recording system of when the failure
started, when the repair technician arrived, and when the failure was repaired (finish time)
and the machine was given back to the operator for full production. We suggest the use
of a simple database as the one we developed in our case study to research on the
matter.
The headline of the database shows the relevant informations to be recollected; the most
important being the three times of the day for each minor stoppage, the reason of the
stoppage, whether or not the stoppage is originated from a reason related to machine
speed versus operator efficiency as this is the main purpose of the study, and on a
secondary level of importance the line or area number if we want to go into detailed lines
in the future. We could as well record the technician name or employee number for further
details in the future, and the machine code for even more details. So far we kept it simple
and record the absolute necessary for the main purpose of demonstrating the effect of
RPM on MTBF and hence on productivity and cost.
It is important to define and standardize the names of all the potential reasons for
stoppages prior to recording, so that data can be filtered if needed. From the data
recollected there are three columns which calculate:
• the total downtime from the calling of the technician to handing back of the machine,
• the time it took the technician to arrive or show up at the point of repair
• and the real actual time of repair which is the difference of the above two times.
The results shown a negative MTBF which at the a first glance may seems to be a non-
sense on the basis of the apparent impossibility of having a negative time between two
events. However it is not a non-sense when your calculations are contemplating a large
number of machines and an entire production facility, in the case here 354 machines,
because it is perfectly logic that it may occur that a machine breaks down before the
technician completes its repair on another machine. In fact the higher the number of
machines in the plant, the higher the probability of negative MTBF, when of course there
are some serious maintenance issues or inadequate speed adjustment for our particular
case study.
Therefore the correct interpretation is that 48 minutes before a machine gets repaired,
another breaks down and operator must stop. It is obvious that this will affect the plant
productivity even though at this stage we do not yet know by how much. Meanwhile the
total time from the calling of the mechanics to the resume time of production is in the
average 55 minutes (MTTR) while the real repair time is 36 minutes. This means on the
average the technician or mechanics take 19 minutes to arrive at the POS, point of
stoppage. expressing the situation in one sentence would be: 48 minutes on the average,
before a technician completes his repair work, another machine in the facility will break
down and another technician will take 19 minutes to arrive and 36 minutes to repair
The numbers are alarming in this particular true case study. Other cases may show a
healthier MTBF but the principles and the calculations applied here remain the same.
There are calculations that are derived from this data and that are fundamental in the
future strategy of the maintenance department. With a total of 21 technicians and a gross
day of 576 minutes, the available maintenance time in men-minutes is 21 by 576 or
12,096 minutes-men. From there we can calculate the following:
• Given that it takes 55 minutes of restoration of the function, the maintenance team
as a whole has the capacity to attend to 12096/55 = 220 stops per day to be at
maximum capacity.
• However, since the technicians must also provide preventive maintenance to the
machines, have time for personal needs, and inject holiday factors where the 21 are
not present simultaneously, the balancing calculations should only contemplate 50%
of the maximum capacity. This 50% would represent 110 stops per day.
• The data show 4340 stops in 48 days, an average of 90 stops per day or 41% of the
maximum capacity, but more important 90/110 = 82% of the recommended load for
repair. That is to say that sooner than later even 21 technicians will not be enough to
attend the machinery.
• The solution is not only in the reduction of the 19 minutes of response time, or in the
application of autonomous maintenance checklist of the reasons for stoppages at the
beginning of the shift, but above all in an induction program to new operators where
speed machine increment is considered progressively with acquired operator s skills.
Taking into account that the working day is 576 minutes, it can be predicted that on
average the plant will experience 82 stops during the day (576 / (55-48)). Since each stop
takes an average of 55 minutes of repair or average duration to restart its operation, a
total of 4510 minutes (82 by 55) of "not working" or stops during the day can be calculated.
Assuming that the plant has 354 sewing machines, the total available time is 203,904
minutes (354 by 576 minutes per day). The minimum daily impact on productivity is (4510
/ 203,904) is 2.2%
The following table summarize the lost revenues daily impact according to different
scenarios of production volume and gross margins per unit.
In general Non adjusted RPM to operators efficiency will also generates Mean time
between failures considerable increase and hence have a serious impact on revenues
not earned daily. From the number in the case study it can go from only 3.3 dollars a day
for an extremely low production and product gross margin, up to 1650 dollars a day for a
high volume production and expensive gross margin per product. In this particular plant
the production volume is 9000 a day, and on average the gross margin on a product is
1.5 dollars. At the end of the measurement period they had a lost revenues (297 times
48) of US$ 14,256 and in one year the lost revenue would be (297 by 252 days for the
year) US$ 74,844
Conclusion
There is a great effect of machine speed expressed in revolutions per minute, RPM, on
productivity, quality, and maintenance, hence on operating cost and lost revenues. Most
of the time upper management knows or at least has a feeling for the issue but because
they have not put it into equation, it has been difficult for them to take concrete and
sustainable decisions. In addition the lack of identification of the most effective solution,
that is a different method of training new operators learning curve also contemplate
separate curves for machine speed and quality, has prevented upper management in
Latin America sewing industry to boost revenues, lower cost and be more competitive on
the global contract manufacturing market.