PROJECT FILE

JANGKRIK COMPLEX PROJECT - EKS Modification – Nilam 220802DJPCME714_EXCO00_13.zi


Project p

PLANT LOCATION TRANSMITTAL IN DATE


OnShore 12/28/2018

CONTRACTOR PAGE
VCD 1 of 2

COMMENTS SHEET

Document Title
Pipeline Drying and Draining Procedure
Company Document Number and Revision
220802DJPCME714 - EX-CO - 00
Contractor Document Number and Revision

Transmittal IN Number
IN-2208-02-MK1-ENI-V0040
Transmittal OUT Number
OUT-220802-ENI-MK1-00023
Transmittal OUT Date
16/01/2019
Approval Status Code
B - APPROVED WITH COMMENTS
Company Document Approver
Approval(s) - Arief Tri Setiawan

Note: "COMPANY's approval of this document has to be deemed just as an authorization to proceed with the project execution.
CONTRACTOR is aware that COMPANY's approval is not relieving CONTRACTOR from any of its responsibilities in the performances required by
the CONTRACT"

(*)
A APPROVED
B APPROVED WITH COMMENTS
C NOT APPROVED
D DEEMED APPROVED

Comments:

CONTRACTOR’S
DISCIPLINE COMMENTS
REPLY (IF ANY)
Commissioning JH: pls provide Drying Calculation (how long drying to be taken) Well Noted and
incorporated
Closed by: Hardianto Judo Closed Date: 01/03/2019 07:29 AM

Piping & Layout 1. Please stated reference of drying acceptance criteria. Well Noted and
incorporated
2. Please provide test sheet for this activity i.e. PT-003A.

Closed by: Yanuar Idris Closed Date: 01/15/2019 04:36 AM

Quality Assurance Well Noted and


Statement " After
drying achieved COMPANY
incorporated
satisfaction" shall be revised become "After drying
achieved acceptance level/criteria".

Please attach REPORT / CERTIFICATION form in this


procedure
PROJECT FILE
JANGKRIK COMPLEX PROJECT - EKS Modification – Nilam 220802DJPCME714_EXCO00_13.zi
Project p

PLANT LOCATION TRANSMITTAL IN DATE


OnShore 12/28/2018

CONTRACTOR PAGE
VCD 2 of 2

Closed by: Bastomi Tomi Closed Date: 01/09/2019 05:02 AM

Quality Control sect 5.2 add size and rating of quick open valve to used Well Noted and
incorpsorated
sect 5.5 mis-typo para 6.2 for tools and equipment list

provide sample report for drain and drying

Closed by: Hertanto Bambang Closed Date: 01/03/2019 03:12 AM

Focal Point (Focal Please to address discipline engineer's comments in the next
Point)
revision.

Closed by: Al Anshari Dicky Closed Date: 01/15/2019 10:10 AM