Site Inspection Report 001
Site Inspection Report 001
Description of Work:
Dear sir,
On 30-12-2023 the BC overlay work done from Ch. 142.680 to Ch. 143.404 in LHS Direction. Due to tack coat distributor
heating problem the laying got delay. The BC Overlay was started at 11:00 AM and ended at 9:00 PM. The rolling work
was stopped for one hour in the evening due to water issue. Due to night execution work, we noticed that Ch. 143.374 to
143.404 (40m) proper laying/ rolling was not done.
Photographs:
Contractor Representative: Concessionaire/ PMC Representative:
(Received) (Issued)
Name: Name:
Designation: Project Manager (PM) Designation:
Conformance/ Compliance Status Report