DAFTAR HARGA SATUAN UPAH,DAN BAHAN / MATERIAL

Zona BAWAH (SS,LS,PNRG,JBYN,LKK,SPKT,RPG,JKG, JBYN TENGAH)


A. HARGA SATUAN UPAH

NO URAIAN KODE SAT HRG. SAT KETERANGAN

1 Tukang L 01 JAM 27.428,57 192.000,00 / Hari


2 Kepala tukang L 02 JAM 31.428,57 220.000,00 / Hari
3 Operator L 03 JAM 47.142,86 330.000,00 / Hari
4 Pemb. Operator L 04 JAM 27.428,57 192.000,00 / Hari
5 Mandor L 05 JAM 35.285,71 247.000,00 / Hari
6 Pekerja L 06 JAM 23.571,43 165.000,00 / Hari

B. HARGA SATUAN BAHAN / MATERIAL dan ALAT

NO URAIAN KODE SAT HRG. SAT KETERANGAN

SURVEY
BAHAN / MATERIAL TOKO 1 TOKO 2
1 Koral cor ( palu ) M 01 M3 750.000,00 600.000,00 650.000,00
2 Pasir cor ( lokal ) M 02 M3 242.000,00 500.000,00 425.000,00
3 Pasir pasang (Lokal) M 03 M3 242.000,00 125.000,00 125.000,00
4 Agregat klas B M 04 M3 600.000,00 500.000,00 550.000,00
5 Batu Gunung M 05 M3 500.000,00 400.000,00 400.000,00
6 Sirtu M 06 M3 132.000,00
7 Tanah Timbunan Pilihan M 07 M3 50.000,00
8 Portland cemen M 08 Kg 1.600,00
9 Portland cemen M 09 Zak 80.000,00 70.000,00 70.000,00
10 Kayu begisting M 10 M3 3.300.000,00
11 Kayu Ulin 10/10 - 4m M 11 M3 7.150.000,00
12 Kayu Ulin 5/10 - 4m M 12 M3 7.150.000,00
13 Multipleks 9 mm M 13 Lbr 181.500,00 110.000,00 100.000,00
14 Paku M 14 Kg 22.000,00 20.000,00 20.000,00
15 Besi polos U24 M 15 Kg 22.000,00
16 Kawat Bendrat M 16 Kg 22.000,00 25.000,00 25.000,00
17 Plastik Cor M 17 M2 2.200,00
18 Gorong-gorong Diameter 20 x 100 Cm M 18 Bh 400.000,00 350.000,00 250.000,00
19 Gorong-gorong Diameter 30 x 100 Cm M 19 Bh 400.000,00 350.000,00 300.000,00
20 Gorong-gorong Diameter 40 x 100 Cm M 20 Bh 400.000,00 350.000,00 300.000,00
21 Gorong-gorong Diameter 60 x 50 Cm M 21 Bh 400.000,00 350.000,00 300.000,00
22 Gorong-gorong Diameter 80 x 50 Cm M 22 Bh 400.000,00 350.000,00 300.000,00
23 Balok Kayu Meranti M 23 Bh 3.300.000,00
24 Pipa PVC 3/4 " M 24 Kg 13.200,00 35.000,00 35.000,00
ALAT / PERALATAN
1 Dump Truck 3,5 ton E 01 Jam 223.230,75
2 Concrete mixer E 03 Jam 50.200,00

1. URUKAN / M3 181.987,00 6. PARIT / TURAP


2. SEMENISASI (L = 3 M) / M3 1.912.193,00 Pemasangan Batu Gunung / M3 1.413.165,00
SEMENISASI (L = 4 M) / M3 1.789.663,00 Plesteran / M2 103.312,00
3. PENGERASAN Acian / M2 62.070,00
BATU (TELFORD) / M3 822.007,00 7. K3 1.000.000,00
AGREGAT / M3 731.931,00 8. PAPAN PROYEK 500.000,00
4.PENYIAPAN BADAN JALAN / M2 10.008,00 9. READY MIX K250 ( L = 3 m ) 2.588.783,00
5. PEKERJAAN GALIAN TANAH / M2 42.538,00 READY MIX K250 ( L = 4 m ) 2.563.337,00
10. ASPAL SAND SHEET / M2 336.775,00
LAPIS PEREKAT / LT 21.404,00