2 PERKINS 320.00 .00 4020.93 Non-Operatio 07/18/2023 Damaged rocker Dismantle/inspection 19:32 NO 12/31/2023
nal arm, cylinder head; of cylinder head
intake and exhaust assembly and
valves and valve moving integral parts
seat inserts. for damages.
C TICAO GRID, San 24.00 2574.00 0 8235.20 5060.00 Normal Line Fault & Line Maintenance
Jacinto, Masbate Operation Line Fault: 1916H-1945H @ F2 &
0400H-0536H @ F1; Line Maintenance:
1945H-0825H @ F2 (Brgy. Gumunab to
Talisay)
2 CUMMINS 600.00 .00 33445.00 Non-Operatio 04/17/2023 Heavy smoke For further -- -- NO 09/30/2023
nal comes out at troubleshooting of
Breather side and unit
exhaust muffler.
Bearing Seizure
3 CUMMINS 600.00 .00 33082.00 Non-Operatio 07/17/2023 Unit Under PMS On-going Major -- -- NO 08/15/2023
nal Overhauling
4 WEICHAI 600.00 .00 737.57 Non-Operatio 08/10/2023 Broken alternator UNIT UNDER 10:26 -- NO 08/13/2023
nal belt WARRANTY, FOR
CHECKING AND
REPAIR BY
SUPPLIER
56 SAN PASCUAL DPP, 23.91 441.00 6 2830.00 2000.00 Normal Line Fault
Terraplin, San Pascual, Operation Line Fault: 0402H-0411H
Masbate
1 PERKINS 560.00 .00 0.00 Deactivated 05/19/2021 Irreparable engine Deactivated as per -- -- NO --
crankshaft damage approved Memo No.
and obsolescence SPU-21-5245 dated
of spare parts. 04 November 2021.
Deactivation date:
25 September 2021
58 GILOTONGAN DPP, 16.00 116.00 3 620.00 200.00 Plant 05/25/2023 Plant shutdown at -Prepared 12:00 04:00 YES
Gilotongan, Cawayan, Shutdown 1200H-1600H & Emergency PR No.
Masbate 0000H-0400H due GTD23-015 & 016.
to non-operational -Fuel Injection
units (Damaged Pumps were sent to
cylinder head of WMTSD for repair
Unit 1, Defective and recalibration.
Fuel Injection
Pumps of Unit 2&3.
NATIONAL POWER CORPORATION
Small Power Utilities Group
Daily Plant Status Report - 10 Aug (12nn) - 11 Aug (12nn)
2 FG-WILSON 135.00 .00 14658.46 Deactivated 01/05/2023 Insufficient fuel Deactivated as per -- -- NO 08/31/2023
pressure at high approved Memo No.
pressure lines. SPU-23-0788 dated
Possible cause: 14 February 2023
defective fuel &
barrel assembly
3 FG-WILSON 135.00 .00 13370.34 Non-Operatio 05/05/2023 Insufficient fuel Pull-out of Fuel -- -- NO 08/31/2023
nal pressure at high Injection Pump for
pressure lines. repair/replacement.
Possible cause:
defective fuel &
barrel assembly
2 FG-WILSON 135.00 .00 9910.00 Deactivated 10/15/2022 Defective Fuel Approved for -- -- NO 11/30/2023
Injection Pump temporary
deactivation per
Memo No.
SPU-23-2546
1 FG-WILSON 80.00 .00 19701.50 Non-Operatio 05/28/2023 Cylinder head water Immediately stopped -- -- NO 08/31/2023
nal leakage operation and
implemented inspecti
on/troubleshooting
4 CUMMINS 500.00 .00 824.83 Non-Operatio 08/10/2023 Abnormal sound at On going checking / 20:26 ---- NO 08/13/2023
nal engine during troubleshooting
staring
NATIONAL POWER CORPORATION
Small Power Utilities Group
Daily Plant Status Report - 10 Aug (12nn) - 11 Aug (12nn)