Professional Documents
Culture Documents
Electricity Service Guide (WERA)
Electricity Service Guide (WERA)
Contact point:
Contact us if you have any enquiries or comments about this publication at: SR@wera.gov.sa
Document language
This document was prepared in Arabic and translated into English from the Arabic original. In case
of discrepancy, the Arabic version is definitive.
Copyright © Water and Electricity Regulatory Authority, 2023. All rights reserved.
This revision of the Guide contains nine chapters and several appendices. These provide details of
every stage of electricity service provision for all Consumer categories, from service request to
termination, and all service related aspects in between, such as Tariffs and consumption calculations.
Goal:
The purpose of this Guide is to regulate interactions between the Consumer and the electricity
Service Provider, as well as the procedures related to providing the service to all beneficiaries in a
way that achieves an accurate balance between the interests of both the Consumer and the Service
Provider.
Scope:
This Guide details the regulatory process of electricity service provision in its various stages, and the
interactions between the electricity Service Provider and the beneficiary or others affected.
▪ General Rules
▪ Connection Regulations for Plots
▪ Electrification of Villages, and Rural Areas.
▪ Residential Facilities without Legal Deeds or Property Documents Authorized
by the Country
▪ Service Applicant Load Calculations
▪ Determining the Number of Service Applicant Meters
▪ Sub-meters
▪ Requirements for a New Electricity Service Connection
▪ Connection Regulations According to Load
▪ Electricity Service Connection for Minor Loads
▪ Temporary Electricity Service Connection
Introduction:
This chapter addresses the regulations and procedures for the connection of an electricity service to
private plots; the electrification of villages, rural and residential areas; and the permanent or
temporary connection of electricity services to facilities. This chapter also deals with the method of
calculating loads, the number of meters, and the service connection requirements, in addition to the
connection regulations based on loads.
The radial and ring planning systems are shown in diagram (1) of Appendix (8) 1
11-3 Electricity service connection regulations for loads exceeding (25 MVA):
11-3-1 Electricity services for loads exceeding (25MVA) and not exceeding (120MVA) must be
connected to the transmission high voltage network.
11-3-2 Electricity services for loads exceeding (120 MVA) must be connected to the transmission
high or extra high voltage networks.
11-3-3 As an exception to paragraph (11-3-1) above, the Service Provider may deliver the
electricity service to the Service Applicant at a medium distribution voltage from one of its
substations according to the following controls:
11-3-3-1 This procedure should not delay the provision of the service to Consumers whose loads are
less than (25 MVA) in the same area.
11-3-3-2 The Service Applicant must share the costs of the substation from which they will be fed
based on actual costs at the time of construction – including the recorded value of the
substation land – in a ratio equivalent to the ratio of the simultaneous Demand Load to
the safe capacity of the substation.
11-3-4 The Service Applicant must bear the connection costs to the transmission high voltage as
shown in Table (3) of Appendix (3).
11-3-5 The Service Applicant must bear the connection costs to the nearest suitable point in the
network (specified by the Service Provider) starting with the feeder breaker. If the Service
Applicant objects to the location of the network connection point specified by the Service
Provider, WERA must decide on the matter. The cables and connection lines must be owned
by the Service Provider.
For example: small billboards, telephone booths, self -service machines, ATMs.2
22-2 Cases and situations in which electricity services disconnection due to non-payment is
prohibited:
The Service Provider may not disconnect the electricity service from a Consumer due to non-
payment, during the following times and in the following cases:
A. During school examinations in the residential consumption category
B. After 12 o’clock noon
C. Outside the official working hours of the Service Provider
D. During the holy month of Ramadan in the residential consumption category
22-4-2 The electricity service can be reconnected to the facility that had been disconnected,
once its consumption arrears have been linked to the consumption of the new facility to
which the same Consumer has moved.
Article (23): Disconnecting the Electricity Service for Reasons other than Non-Payment
Subject to the provisions of Chapter (9) and Article (24) of this chapter, the Service Provider may
disconnect the electricity service from a Consumer for reasons unrelated to payment in the following
cases:
23-1 Electricity service disconnection based on a request from an official concerned authority:
The Service Provider may disconnect the electricity service from a Consumer based on an executive
decision or a request from the administrative governor, in accordance with the following procedures:
A. A letter is received from the official party concerned, asking the Service Provider to disconnect the
electricity service from the Consumer. The letter should explain the reason(s) for disconnecting the
service, and provide the Consumer's name, and account or subscription number.
23-5-2 In all cases, the violation report must be submitted to the Authority for a decision, and if
upheld, the Service Provider issues and collects the corresponding fine on behalf of the Authority.
24-2 Should a Consumer in these categories fail to pay their bill, the Service Provider should send a
letter demanding payment be made within (30) days from the date the letter was received.
Proof that the letter was received must be obtained from a representative of the Consumer
concerned.
24-3 If the bill has not been paid by the date specified in the demand letter, the matter must be
referred to the Authority for further action.
Article (25): Cancelling the Electricity Service:
The Service Provider, when requested by the owner, and after verifying that there are no Consumers,
may cancel the service and remove the meter permanently or temporarily. Except for the stipulations
in Article (26) of this chapter, the Service Applicant may neither reserve the meter and keep it until
property modifications are complete, nor transfer it from one property to another. The procedures
are as follows:
25-1 Permanent removal:
If the owner submits a request to remove the meter because the property is to be demolished, the
Service Provider will permanently remove the meter according to the following procedures:
25-1-1 Ensure that no other Consumer is using the same meter.
25-1-2 Submit a demolition permit.
25-1-3 Settle all outstanding payments and cancel the subscription
25-1-4 If the owner submits a request for a new connection for the same site, he must be treated
as a new Service Applicant and must pay the connection fee.
25-1-5 If the demolition results in the removal of a distribution substation, the case should be
dealt with in accordance with Plan (2), detailed in Appendix (8).
25-2 Temporary removal:
If the owner submits a request to remove the meter and then return it for the purpose of renovation
or reconstruction, the following procedures must be followed:
25-2-1 Ensure that no other Consumer is using the same meter.
25-2-2 Submit a demolition and reconstruction, or renovation permit.
30-2-2 Private institutions, institutes and schools licensed by government entities concerned with
issuing education and training licenses
Article (31): Agricultural Tariff
The agricultural Tariff applies to Agricultural Facilities and projects, including, but not limited to the
following:
A. Agricultural crop production farms.
B. Cattle and dairy production farms.
C. Poultry farms, their processing and similar projects.
Introduction:
This chapter addresses the Service Provider’s responsibility to ensure the accuracy of consumption
readings and related matters, such as meter inspections and auditing consumption readings. It also
deals with consumption calculations for special cases such as calculating the consumption of
temporary meters for building works or events. This chapter also covers problems related to
consumption calculations and billing, in addition to faults resulting from illegal connections or meter
tampering. It concludes with a mechanism for handling complaints related to incorrect consumption
bills.
Article (33): Responsibility of the Service Provider to Calculate Consumption Accurately:
33-1 Consumption auditing:
Consumption is calculated from actual monthly consumption readings (kWh). The Service
Provider must check consumption bills before issuing them. If an unusual increase or decrease
in consumption bills is noticed, the Service Provider must inspect the meters linked to the
suspect bills at their own expense.
33-2 Periodic meter inspection and calibration:
The Service Provider must inspect and calibrate the meters at their own expense according to
the specific schedules for the different types of installed meters, as set out in Appendix (10).
33-3 Handling the inspection result:
33-3-1 If the result of the meter inspection shows the accuracy is within the tolerance limit given
in Appendix (10), then the meter is considered valid for use, and the result should be kept
for future reference.
33-3-2 If the result of the meter inspection shows the accuracy exceeds the tolerance limit, it
must be addressed in accordance with Article (40) of this chapter.
33-4 Meter inspection at the request of the Consumer:
If the Consumer requests their meter be checked, it should be carried out by the Service Provider
using the following steps:
A. If the meter is fully functioning, the Consumer must pay any outstanding bill for consumption, and if
the service was disconnected, they must also pay the reconnection fees.
B. If the meter is not fully functioning and it is not possible to recalibrate it, the Service Provider must
bear the costs of replacing the meter, in accordance with Article (40) of this manual.
C. They must notify the Consumer of their right to appeal to the Authority.
▪ General Rules
▪ Clearance Distance
▪ Cases Requiring Relocation
▪ Relocation Impracticality
▪ Relocation upon Request
▪ Documents Required to Study Relocation Requests
▪ Execution Period for Distribution Network Relocation
▪ Relocation Request Records
Introduction:
This chapter deals with the regulations and procedures for relocating electricity network
components. It covers the cases that require relocating and specifies the responsibilities of both the
Service Provider and the Relocation Applicant in terms of costs and requirements. This chapter also
discusses the responsibility of the Service Provider to document relocation requests.
Article (44): General Rules:
44-1 If the Service Provider’s network, or part of it, poses a threat to public safety, the Service Provider
must relocate the network to a safe site or remove all sources of danger.
44-2 If a disagreement ensues about the relocation request from its original location, or the details
of its implementation, the Service Provider must notify the relocation applicant of their right to
refer the matter to the Authority for adjudication.
44-3 The Service Provider is responsible for rectifying problems related to clearance distances, and
to ensure that they comply with the applicable technical standards and specifications in force
at the time.
Article (45): Clearance Distance:
The Service Provider must abide by the clearance distance requirements for the transmission and
distribution networks specified in Appendix (11).
Article (46): Cases Requiring Relocation:
The Service Provider must relocate the network components to another location that complies with
safety requirements and clearance distances at his own expense if there is an alternative route
approved by the competent authority and the relocation is technically possible in the following
cases:
46-1 Safety reasons:
The Service Provider must relocate the components of the electricity network or address the causes
of danger as soon as possible if it becomes clear that they pose a threat to the lives of individuals or
property. The Service Provider is responsible for unjustified delays in dealing with the situation.
46-2 Interference with private property:
The Service Provider must relocate all components of the network at his own expense from a private
property approved by a legal deed, in which the date of ownership precedes the date of constructing
the network. In the case of transfer of ownership from older to younger generations or vice versa,
the earliest date is considered the date of ownership, unless one of the owners had previously given
unconditional written confirmation that the network may pass through their property.
48-2 If it is proven that the relocation has deprived any person of an ability to benefit equal to or
greater than the benefit provided before the relocation took place, then the Service Provider,
at their own expense, must compensate those deprived of the ability to benefit, or to return
the relocated network to its original site.
51-2 The Service Provider is required to send a periodic (semi-annual) report to the Authority on all
relocation requests received, with an explanation of the outcome of each request. The Service
Provider must include details of all previous unfulfilled requests in the report. The report must
include the following details:
A. The applicant’s name
B. A summary that includes the subject of the request, its date and location, and its expected costs
C. The application status (fulfilled, under consideration, included in the budget for a specific year,
rejected, subject to court review)
Residential 18 30
Commercial 20 30
Agricultural 16 20
Charities & Cooperative Societies 16 20
Governmental 32
Private Hospitals & Schools 18
Saline Water Conversion Corporation Pumping Stations 6.5
Cloud Computing 18
Consumption Tier and Connection Voltage
Network
Categories (Halalah/kWh)
Connected to Connected to
Distribution Network Transmission Network
Industrial 18 18
Sectors in which the ratio of electricity
costs to operational costs, excluding 18 12
raw material costs, is (20%) or more.
Intensive Electricity
Sectors in which the ratio of electricity
Tariff * costs to operating costs, excluding raw
24 18
material costs, ranges from
(10%) to (19.9%).
* The intensive electricity tariff is applied to customers from any eligible sector from the industrial, commercial, and
agricultural categories that fulfil all the requirements.
Table (2)
Connection Fees for Loads Connected on Medium Distribution Voltages
Work Required Connection Tariff
(Per Order) (Saudi Riyals)
Initial Study Work 25,000
Planning, Engineering and Engineering Supervision Work 75,000
Splitting loads on the low distribution voltage network 1,000
for each meter, including
to measure consumption accessories and installation
Table (3)
Connection Fees Payable to the Distribution Network Service Provider
by the Service Applicant
Area Connection Tariff
Work required
(m2) (Saudi Riyals)
Up to 50,000 25,000
Connection to the Service Provider’s More than 50,000 to 100,000 50,000
distribution network on behalf of the
More than 100,000 to 500,000 100,000
Service Applicant
More than 500,000 150,000
25 5 626 108
50 8 650 111
30
55 10 675 115
300
75 13 700 120
76 14 725 124
100 18 50 750 128
125 22 751 129
126 23 775 133
150 26 800 137
70
175 30 850 146 400
200 34 900 154
201 35 950 162
225 38 100 1000 166
250 43 1001 167
251 44 1050 179
275 47 1100 188
500
300 51 1150 197
150
325 56 1200 205
350 60 1250 214
375 64 1251 215
376 65 1300 222
600
400 69 1400 239
425 73 1500 256
200
450 77 1501 257
475 82 1600 274
500 86 1700 290
501 87 1800 307 800
525 90 2000 342
550 94 2100 358
250
575 98 2200 363
600 102
625 107
Service Fees
Table (3): Tariff for Meter Reading, Maintenance, and Bill Preparation
Meter Breaker Capacity (Ampere)
Monthly Tariff (Riyals)
Greater than or equal to Less than
20 100 10
100 200 15
200 300 21
300 400 22
Equal to 400 25
Greater than 400 30
subscribers
Electricity service disconnection for pre-scheduled works ● Direct calling through the call
centre
● Written notice
centre
● Written notice
Illustration Diagrams
Main Main
Substation Substation
Distribution
substation
Main
Substatio
n
Distribution
substation
Start
The substation
No was originally Yes
installed to serve
the Consumer
The substation
Relocation or
No removal is No serves other Yes
Consumers as
technically well
possible
Yes
Relocation or
No removal is
technically
possible
Yes
The location is
expropriated for the The Service Provider
The removal or The Consumer bears The Consumer bears
benefit of the bears the costs of
relocation request is the costs of removal the costs of removal
Service Provider removal or
rejected or relocation or relocation
according to the Law relocation
of Expropriation
Finish
Tampering
detected
A completed
violation report is
available in the
No approved format
Yes
The present
Consumer
tampered with
the meter No
Yes
Table (2): Classification of Consumers by Type of Use According to the Authority’s Board of Directors
Resolution No. (1/22/31), dated 01/06/1431H
Tariff Consumption
Unit Type
Category
Commercial unit Commercial service meter
Furnished apartment Billboard
Hotel Mobile tower
Embassy and consulate Laundry
Commercial
Establishment Radiology centres and medical laboratories
Company Gym
Event hall Temporary meter for building works
Bank Publishing house
Factory Industrial automatic bakery
Industrial
Industrial press Water desalination or treatment plant
Nationality
Passport number Iqama Number
Name Letter Number/Record Letter date Letter source
For more information, please visit the service provider's website or call the toll-free enquiry number.
Eleventh: This agreement has been issued in two original copies in English, and each party shall be
given a copy to act according to it.
Consumer details
First name Father’s name Grandfather’s name Family name National ID number
Nationality
Passport number Iqama Number
Authorized representative details
First name Father’s name Grandfather’s name Family name National ID number