Monthly Progress Report - July
Monthly Progress Report - July
OBJECTIVE
Summary for the Month of July regarding activities performed and jobs observed.
ACTIVITIES PERFORMED
1. Added daily shift-notes on SAP (using shn1 transaction).
2. Involved in revision of lubrication and greasing plan for Ammonia Plant Machinery.
3. Involved in filling checklist for G-301-B overhauling.
4. Involved in following activities during shutdown of DAP Plant (01-Aug-2023)
a. Replacement of bearing for Granulator DB-121.
b. Replacement of conveyor belt on discharge side of Dryer (DF-141)
c. Buckets and bolts inspection for bucket elevator DM-221.
d. Inspection for conveyors DM-223 and DM-222.
JOBS OBSERVED
1. Witnessed weekly oil lubrication and greasing activities for Ammonia Plant machinery.
2. Witnessed ratcheting activity for loop-A Synthesis Gas compressor (K-306-A) during
shutdown.
3. Observed jobs on aqueous ammonia pump G-301-B for mitigating high vibrations.
a. Reinforcement on the pump skid
b. Alignment done using rim and face alignment method.
c. Grouting filling on top of the pump skid.
d. Pump overhauling activity
Zunair Noor 01
4. Observed different inspection activities including DPT, hardness test and Positive
Material Identification during inspection lot processing.
Name:-_________________
Signature: _______________
Zunair Noor 02