Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

Karachi Bus Rapid Transit Red Line Project (RRP PAK 47279)

RISK ASSESSMENT AND RISK MANAGEMENT PLAN

Risk Description Rating Mitigation Measures Responsibility


Political and/or Organizational
1. Changing government L No major political change in Sindh took place after Government
priorities after July 2018 the election. The BRT project also responds to of Sindh; ADB;
general elections delay unmet demands in terms of public transport and PDA
project implementation improvement of the urban environment. consultants
2. Political rivalry builds M A strong communications team has been Government
on flawed comparisons recruited as part of the PMCCB consulting team of Sindh;
between existing BRT to support the provincial government in designing PMCCB
projects in Pakistan and and implementing a project communication consultants
the proposed project, strategy, and engaging with the media and
derailing the project various civil society stakeholders.
3. Vested interests (e.g., S Existing operators. Dedicated consultant SMTA;
existing public transport support is built into the project design to facilitate TransKarachi
operators, shopkeepers, the bus industry transition through negotiations, Company;
and others along the BRT and to build the existing operators’ capacity to be ODBM
corridor) try to undermine part of the BRT system. The industry transition consultants
the project during process will also include the Green and Orange
implementation lines, to be implemented prior to the Red Line, to
ensure a common approach and minimize
conflicts that could affect project implementation.
Consultations with existing bus operators’
federations were held by ODBM consultants to
inform these operators about the project. Skilled
negotiators have been recruited to further discuss
and develop a business model to include these
operators as much as possible in the BRT
operations. The initial BRT fleet will be financed
under the project and leased to private operators
to reduce the need to mobilize capital and allow
existing operators to participate in the bidding
process. The project design also includes a fleet
scrapping program and compensation
mechanism for non-participating operators.
Shopkeepers’ and traders’ associations. The
Government of Sindh, supported by the PMCCB
consultants’ communications team, engaged with
traders’ associations and other organizations
impacted by the BRT corridor, to present the
project design, consider their concerns, and
promote buy-in and ownership, so that these
groups do not oppose the project or ask to
change the project design and alignment.
4. The delayed S The SMTA was established in September 2016 Government
operationalization of the and has been operating since then. TransKarachi of Sindh;
SMTA and TransKarachi was incorporated as a Section 42 public company SMTA;
fails to provide the in October 2018. The Government of Sindh has TransKarachi;
necessary critical mass approved an annual allocation for the SMTA’s ADB; PMCCB
to implement the project, operations. ADB will finance TransKarachi’s consultants
and capacity building operational expenditures for 3 years.
Organizational charts and job descriptions for key
staff for both organizations have been developed
by PMCCB consultants, who will also provide
support for staff recruitment and capacity building.
2

Risk Description Rating Mitigation Measures Responsibility


5. Limited capacity and a M An assessment of additional capacities required SMTA;
lack of coordination and by the executing and implementing agencies, TransKarachi;
clarity regarding the including international and national consultants PMCCB
roles and responsibilities and incremental staff (PMU and PIU), was consultants
of the executing and undertaken. Staff required by the SMTA are being
implementing agencies hired by the Government of Sindh with support
from PMCCB consultants. Consultants required
by TransKarachi have been hired under the PDA
and have been fully mobilized. The Government
of Sindh approved advance funding for the PMU
and PIU, and staff are currently being hired. The
SMTA’s board of directors will act as the project
oversight body to guide, oversee, and coordinate
among all government agencies involved during
project implementation. The PMU, supported by
PMCCB consultants, will provide dedicated
coordination support only, while TransKarachi’s
PIU will be the sole implementing agency. Roles
and responsibilities of the executing and
implementing agencies are clearly outlined in the
PAM.
Governance
6. Pakistan’s score for M Federal and provincial governments have Government of
control of corruption, initiated reforms to strengthen governance. In Pakistan;
government addition, several federal-level anticorruption Government of
effectiveness, and watchdogs (e.g., the NAB and ombudsman) Sindh; ADB
regulatory quality comprise provincial divisions. The project will also
remains low institute a mechanism to redress project-based
grievances, corruption control, and the periodic
review of regulatory compliance.
7. Because of the potential M Several partners, including the DFID, EU, GIZ, Government of
for corruption and political and World Bank, are providing support for legal Pakistan;
interference (notably and judicial anticorruption reforms. The project Government of
regarding the appointment will be insulated from corruption risks in Sindh; ADB
of the ombudsman and accordance with ADB’s Anticorruption Policy
chairperson of the NAB), (1998, as amended to date) through compliance
oversight institutions are requirements built into the draft loan and project
not perceived as impartial agreements, and close monitoring of their
implementation.
8. Lack of transparency M Project design and implementation arrangements TransKarachi;
and disclosure of project include several measures to bring more ADB; PMCCB
activities, especially accountability and transparency to procurement. consultants
procurement A proper system of procurement planning,
tracking of various procurement actions, and
complaints monitoring will be implemented. This
includes support from a team of experienced
procurement and financial consultants already
hired under the PDA. TransKarachi will maintain
a website to show the updated procurement
status. The number of contracts to be procured
will be limited, using ICB procedures in most
cases, and supervised by international
consultants to minimize risks. In addition, direct
payment procedures will be used.
3

Risk Description Rating Mitigation Measures Responsibility


9. TransKarachi lacks S ADB’s prior review will be required for TransKarachi;
staff with experience in procurement of all contracts. ADB will provide ADB; PMCCB
procurement in general formal training in ADB procurement and consultants
and in ADB’s consulting services procedures and practices.
Procurement Guidelines PDA consultants will provide timely and on-the-
(2015, as amended from job training on this aspect. Progress reports of
time to time) in particular, PDA consultants will be required to record all
to efficiently carry out trainings conducted. PMCCB consultants will also
procurement activities. be required to develop a procurement manual
Deficient contract and a contract management manual to be
management may create followed by procurement staff in TransKarachi.
implementation delays The ADB project team will monitor compliance.
Technical
10. Longer M Bidding documents are expected to be prepared TransKarachi;
preconstruction time and with the support of PMCCB and EPCM ADB; EPCM
delayed start of civil consultants. They should be ready to be consultants;
works because of the advertised by December 2018, allowing advance PMCCB
delayed preparation of procurement to be undertaken for civil works consultants
bidding documents, and contracts, which will be ready for award shortly
the time required for after loan effectiveness.
procurement PMCCB consultants conducted a procurement
capacity assessment of the implementing agency
and are building the PIU’s capacity to undertake
advance procurement actions and handle
contract management. EPCM consultants will
provide support and oversight. The procurement
plan has been designed to reduce the number of
packages without compromising competition, and
to reduce contract management requirements.
11. Delays because of the M EPCM consultants have been hired under the Government
complexity of the design PDA, and initial surveys for both design and of Sindh;
and implementation in the relocation of utilities have been completed. Traffic Karachi
city center and management and alternate routes have been Cantonment
cantonment area identified, and procurement packaging and Board; EPCM
phasing have been synchronized accordingly. consultants
12. Public transport S PDA consultants estimated demand using TransKarachi;
users do not use BRT at detailed surveys and a sophisticated model, ODBM
projected levels factoring in the use of an innovative operations consultants
plan and communication strategy that will likely
boost ridership.
13. Few or inadequate M To encourage appropriate bidders to take part in TransKarachi;
bidders for BRT the bidding process, PMCCB consultants PMCCB
operating contracts, conducted a market analysis and a road show. consultants
resulting in substandard The perception of risk and reward by potential
operation bidders was paid a particular attention.
Public Financial Management
14. Incomplete and S TransKarachi willl adopt the FMM developed by TransKarachi;
inaccurate financial ADB as a technical backstop. PMCCB ADB; PMCCB
reporting consultants will also deploy an accounting consultants
software for cost control based on ADB’s FMM.
Regular supervision missions and training by
ADB will further enhance the company’s staff
capacity to build and establish an effective
financial management system.
4

Risk Description Rating Mitigation Measures Responsibility


15. The implementing M The FMM includes a comprehensive section TransKarachi;
agency is unfamiliar with providing step-by-step guidance on expenditure ADB
ADB’s policies and management, defining the service standards and
procedures, and there is requisite supporting documentation for payment
a risk that expenditures processing. TransKarachi will adopt the FMM.
incurred will not be in
accordance with the
applicable legal
framework
Social and Environmental
16. Unemployment of M The project design includes dedicated cost and TransKarachi;
existing private bus consultancy support to facilitate the bus industry’s ODBM
drivers and other transition through capacity building to operate the consultants
workers BRT system. This includes training existing
drivers and bus industry workers, who will be
given employment preference to operate the BRT
system. The BRT system is expected to generate
about 2,130 jobs directly.
17. High traffic M EPCM consultants under the PDA are currently TransKarachi;
congestion, leading to developing (a) a detailed and comprehensive EPCM
delays in vehicular traffic management plan that will promote the use consultants
movement (including of alternative routes to minimize traffic congestion
ambulances), and an and reduce traffic and pedestrian movement
increased risk of along the proposed project corridor construction
accidents during the sites, and (b) a comprehensive set of mitigation
construction phase measures to manage traffic-related issues during
construction, to be implemented and monitored.
18. High noise levels M Noise barriers shall be placed at different TransKarachi;
(i.e., exceeding strategic locations at work sites along the project EPCM
acceptable local and corridor to shield nearby sensitive receptors from consultants
international noise limits) any high noise levels generated during
generated from construction. In addition, the EIA prepared for the
construction activities project outlines a comprehensive set of mitigation
near sensitive receptors measures to be implemented to minimize the
(e.g., educational impacts, if any, of high noise levels.
institutions, health care
facilities, and
residences) leads to
disturbances and
significant adverse
impacts
19. Utility interruptions M Effective pre-planning is being conducted with all TransKarachi;
and outages because of concerned utility departments to minimize any EPCM
damage caused to possible impact(s) on different utilities along each consultants
equipment (e.g., section of the project corridor. Alternative
electricity and telephone arrangements will be made wherever outages are
poles, underground gas, unavoidable. The duration of any utility outages
and water and sewerage will be minimized as much as possible. All
lines) by excavation and associated possible mitigation measures, such as
construction works at keeping communities informed of planned
sites along the project outages, will be conducted to enable advance
corridor could disturb preparation and planning.
sensitive facilities.
5

Risk Description Rating Mitigation Measures Responsibility

20. Delayed land M Close coordination has been established by the Government
acquisition for depots, PIU with the Rangers and PTCL, and work will be of Sindh;
and the relocation of phased to start along sections that do not require TransKarachi;
utilities by relevant land acquisition. Relocation of utilities is funded EPCM
agencies, may delay civil by the Government of Sindh as part of its consultants
works contribution to the project financing. Funds will be
transferred to the utilities in advance, along with
location maps of the utilities to be removed. This
will be closely coordinated by TransKarachi,
which will establish a coordination mechanism
with all major utilities to ensure timely removal.
21. Delayed land M Close coordination has been established by the Government
acquisition from airport PIU with the Pakistan Civil Aviation Authority to of Sindh;
may delay civil works finalize an agreement with TransKarachi for the Pakistan Civil
lease of a portion of Jinnah International airport Aviation
land required for a 10-meter widening of a 450- Authority;
meter section of the BRT corridor. Required funds TransKarachi;
will represent a marginal percentage of EPCM
operational expenses. consultants
22. The security situation S The Government of Sindh has committed to Government
deteriorates and impairs provide security to the project site through its of Sindh;
project implementation Home Affairs Department and local law contractors;
and future BRT enforcement agencies. Bidders will be instructed EPCM
operations to include provisions for security of their staff. The consultants
project design includes measures such as metal
detectors installed in all BRT stations, and the
presence of security agents in all BRT vehicles.
Overall S
H = high, L = low, M = moderate, S = substantial.
ADB = Asian Development Bank; BRT = bus rapid transit; DFID = Department for International Development of the
United Kingdom; EIA = environmental impact assessment; EPCM = engineering, procurement, and construction
management; EU = European Union; FMM = financial management manual; GIZ =Deutsche Gesellschaft für
Internationale Zusammenarbeit; ICB = international competitive bidding; NAB = National Accountability Bureau; ODBM
= operations, design, and business model; PAM = project administration manual; PDA = project design advance; PIU
= project implementation unit; PMCCB = project management, coordination, and capacity building; PMU = project
management unit; PTCL = Pakistan Telecommunication Company Limited; SMTA = Sindh Mass Transit Authority.
Source: ADB.

You might also like