Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

Document No.

F04(PRJ(SOL)-P-01)/14-3 PRE-COMMISSIONING TEST REPORT FOR


Revision No. 02 AUXILIARY TRANSFORMER
Date: 16.12.2020

PRE-COMMISSIONING TESTS FOR AUXILIARY TRANSFORMER


I. GENERAL DETAILS
DETAILS
Project: 50 MW SOLAR PLANT,HASAPUR Sub-Station: ICR-02

Feeder name: AUX TRAFO LOA/PO No.:

Make: NORTEX Type: DRY TYPE

Sr. No.: 20976396 Year of Manufacture: 2022

Rated Capacity: 7 KVA Rated Voltage: 800 V


Rated Current: HV SIDE-5.05 A
Vector Group: NA
LV SIDE-30.4 A
Cooling Type: AN Rated Frequency: 50 Hz

Type of Neutral Grounding: SOLID Type of Tap Changer: NA

Voltage Variation: NA Oil Quantity: NA

Date of Receipt at site: Date of Completion of Erection:

Date of Commissioning: Date of Loading:

II. CHECK LISTS OF ELECTRICAL TESTS CARRIED OUT FOR AUXILIARY TRANSFORMER
Sl. Performed Test Results
Name of Tests
No. (Yes/No) (Ok/Not Ok)
1 Pre-Commissioning Checks YES OK
2 Voltage Ratio Test YES OK
3 Vector Group Test & Polarity Check NO -
4 Magnetic Balance Test NO -
5 Insulation Resistance Measurement YES OK
6 Measurement of Winding Resistance YES OK
7 Protection and Alarm Tests NO -

Signature: Signature: Signature: Signature: Signature:


Name: RATIKANT
Name: Name: Kashyap Patel Name: Name:Gowtham
SAHOO
Designation: Erection Designation: Erection Designation: Quality
Designation: Testing Er. Designation: Testing Er.
Er. Er. Er.
Organization: Main Organization: Akshar
Organization: Renew Organization: Renew Organization: Renew
Bidder Leepant
Sheet No
Document No.
F04(PRJ(SOL)-P-01)/14-3 PRE-COMMISSIONING TEST REPORT FOR
Revision No. 02 AUXILIARY TRANSFORMER
Date: 16.12.2020

III. PRE-COMMISSIONING CHECKS:


Sl. Status Remarks
Description
No YES NO Deficiencies
1 Transformer is free from visible defects on physical inspection YES
2 All fittings as per out line General Arrangement Drawing YES
3 Check Main Tank has been provided with double earthing -
All nuts and bolts are tightened correctly as per specified torque (as
4 -
per manufacturers recommendation) (ERECTION REPORT ENCLOSED)
5 Check tightness of Terminal at cable YES
6 Check leveling of Transformer and its accessories YES
YES REVIWED AS
Erection Completion Certificate along with list of outstanding activities
7 PER ERECTION
reviewed(ERECTION REPORT ENCLOSED)
CHECK LIST
8 Any Paint removed / scratched in transit has been touched up YES
9 Bushings are clean and free from physical damages -
10 Check oil leakage through any Joints / Valves etc. -
11 Check oil drain valves are properly closed and locked -
12 Check oil level in Main Tank & Conservator tank -
Check oil level at conservator matches with oil temperature of -
13
transformer
14 Check OTI and WTI pockets and replenish the oil, if required -
15 Check all valves for their opening & closing Sequence -
16 Check the color of the breather silica gel (blue when dry) -
17 Check availability of oil in the breather cup -
Check all rollers are locked and tack welded with rails (wherever -
18
applicable)
Check no debris, loose T & P and oil strains on and around the -
19
Transformer
Check door seals of Marshaling Box is intact and all cable gland plates
20 YES
unused holes are sealed
21 Check that pressure relief device is correctly mounted -
22 Check that permanent and adequate lighting arrangements are ready -
23 Check that labeling and identification is permanent and satisfactory -
Check that Buchholz Relay is correctly mounted with arrow pointing
24 -
towards conservator
25 Check cables are properly fixed and ensure cable entry at the bottom YES
26 Ensure all Power and Control cable Terminals are Tightened YES
Check all cables and Ferrules are provided with Number as per Cable
27 YES
Schedule (Cross Ferruling to be checked)
28 Check that all cables are correctly glanded. YES

Signature: Signature: Signature: Signature: Signature:


Name: RATIKANT
Name: Name: Kashyap Patel Name: Name:Gowtham
SAHOO
Designation: Erection Designation: Erection Designation: Quality
Designation: Testing Er. Designation: Testing Er.
Er. Er. Er.
Organization: Main Organization: Akshar
Organization: Renew Organization: Renew Organization: Renew
Bidder Leepant
Sheet No
Document No.
F04(PRJ(SOL)-P-01)/14-3 PRE-COMMISSIONING TEST REPORT FOR
Revision No. 02 AUXILIARY TRANSFORMER
Date: 16.12.2020

Check external cabling from Junction Box to Relay / Control Panel


29 -
completed
Check that air has been released from the Radiators and their
30 -
headers / Buchholz relay / Main tank/Bushing chambers etc.
31 Check Fire Protection System is adequate & ready -
Check that all radiator bank valves on top and bottom headers are
32 -
open
33 Calibration of OTI & WTI performed as per procedure -
34 Equipment is cleaned and free from dust/dirt foreign materials etc. -
35 Equipment is free from all visible defects on physical inspection. -
36 Check tightness of each cable termination. -
37 Check all the fuse/ MCB. -

IV. INSULATION RESISTANCE MEASUREMENT:


(Using 5000 Volts Megger)

Make & Sl. No. of Testing Kit : FLUKE & 2560001


Date of Last Calibration of Kit : 16/07/2022
Ambient Temp in ºC : 300C
Date of Testing : 19/10/2022

PHASE
CORE UNIT
R – Phase Y – Phase B - Phase
PRIMARY – EARTH GΩ >1 GΩ >1 GΩ >1 GΩ
PRIMARY – SECONDARY GΩ >1 GΩ
SECONDARY- EARTH GΩ >1 GΩ

V. Ratio Test:
Make & Sl. No. of testing kit : FLUKE & 37911953WS
Date of last calibration of the kit : 18/07/2022
Ambient temp in ºC : 300C
Date of Testing : 19/10/2022
Tap Applied HV Voltage(V) LV Measured Voltage(V)
Position 1U1V 1V1W 1W1U 2U-2N
- 406.0 406.0 406.0 118.6

Signature: Signature: Signature: Signature: Signature:


Name: RATIKANT
Name: Name: Kashyap Patel Name: Name:Gowtham
SAHOO
Designation: Erection Designation: Erection Designation: Quality
Designation: Testing Er. Designation: Testing Er.
Er. Er. Er.
Organization: Main Organization: Akshar
Organization: Renew Organization: Renew Organization: Renew
Bidder Leepant
Sheet No
Document No.
F04(PRJ(SOL)-P-01)/14-3 PRE-COMMISSIONING TEST REPORT FOR
Revision No. 02 AUXILIARY TRANSFORMER
Date: 16.12.2020

VI. MEASUREMENT OF WINDING RESISTANCE:

Make &Sl. No. of testing kit : FLUKE & 37911953WS


Date of last calibration of kit : 18/07/2022
Ambient temp in ºC : 300C
Date of Testing : 19/10/2022

WINDING RESISTANCE (HV) LV SIDE


Tap Position
1U-1V 1V-1W 1W-1U 2U-2N
3.3 3.4 6.3 0.5

VII. ALL ELECTRICAL TEST RESULTS COMPARED WITH FACTORY TEST RESULTS & FOUND TO BE IN ORDER
Date of Testing : YES NO REMARKS

i. Phase marking & Continuity Sequence check.


YES NO

VIII. FINAL DOCUMENTATION REVIEW

i. Factory test results are available


YES NO

ii. Final documents of Pre- Commissioning checks reviewed and approved.

YES NO

iii. Document regarding spares equipment, O&M manuals etc. available at site.

YES NO

iv. After modification, if any, “As built Drawings” are available at site.
YES NO

Signature: Signature: Signature: Signature: Signature:


Name: RATIKANT
Name: Name: Kashyap Patel Name: Name:Gowtham
SAHOO
Designation: Erection Designation: Erection Designation: Quality
Designation: Testing Er. Designation: Testing Er.
Er. Er. Er.
Organization: Main Organization: Akshar
Organization: Renew Organization: Renew Organization: Renew
Bidder Leepant
Sheet No

You might also like