Professional Documents
Culture Documents
Practical Work No.5
Practical Work No.5
Practical Work No.5
The list of tasks in the project is usually determined by the persons responsible for monitoring the
project implementation. The level of detail of the project tasks must be agreed with the project owner
(project manager) and the general director of the company. Decompositions, as already written, should be
based on the principle of sufficiency, otherwise such an operation as, for example, "manual excavation of
soil" (i.e. when the pit needs to be dug), you can split into elementary operations such as: "search for a
shovel," "smoke break," etc.
It is recommended to write a prefix before the name of the created views, tables, filters, groups, so
as not to get confused in the views and easily distinguish created from built-in ones.
3. In the created view, display the required columns, leave the necessary ones and hide the key
"Del" are unnecessary.
In our case, there should be the following columns:
– Task mode;
– SWD;
– Task name;
– Unit of measure (Text1);
– Duration;
– Labor costs;
– Type;
– Fixed scope of work;
– Task calendar;
– Deadline.
After extracting the necessary columns, we fix their order, saving a new table. To do this, in the
"View" menu, in the "Data" area, click "Tables - Save fields as a new table" and enter the name of the
table "PR_ Entering_Task_Data", Figure 5.3.
So, the view saves the settings for text formats, Gantt lines, timeline details, and the binding of a
specific table, and the table stores a selection of columns and their names. If you accidentally switch to
another table in the saved view and save the file, the view you created will already be associated with the
new table.
Note:
1
All tasks of this stage with automatic planning, type "Fixed duration," with an unfixed scope of
work and with a standard project calendar, that is, in the calendar column, the calendar is not selected.
2
You can also set the deadline for the “Project Start Decision” task in the task properties, in the
“Advanced” tab in the “Restriction” area. The deadline is the target date indicating the directive time for
the end of the task. You can also set a deadline for summary tasks.
To assign a standard calendar to all the tasks of the TEJ project stage at once, you need to select
all the tasks of the stage, right-click, select "Information" in the menu, go to the "Advanced" tab and
select a standard calendar.
To create tasks in the project with the default type "Fixed duration," you need to select "Default
task type - Fixed duration" in the menu "File - Parameters - Schedule."
To select a task type (fixed duration, fixed work, fixed work scope), you must change the task
scheduling type from manual to automatic.
To create a summary task from the "TEJ project" task, you need to select this task and click on the
"Summary task" icon on the "Task" tab in the "Insert" section.
We rename the old task "TEJ of the Project" to "A decision was made to start the stage "TEJ of the
Project, "and transfer the resulting total in the "TEJ of the Project" to a manual type of planning to control
the timing of the attached tasks and set its duration for 20 days, Figure 5.4.
The next action with the tasks of this stage is to define their relationships. We highlight all tasks of
this stage and associate them with links of the type "End - Beginning," Figure 5.5.
As can be seen in Figure 5.5, there was a delay in the timing of the directive duration of the TEJ
phase of the project and a disruption in the directive date of the decision to start the project. If you move
the mouse cursor to the red line at the project stage, an information window will appear in which it will be
written what is the duration of the nested tasks.
To eliminate the failure of deadlines, you can, or:
1. To increase the duration of the stage to 22 days, or;
2. Reduce the duration of nested tasks by a total of two days, or;
3. Assign an automatic planning type to the summary task so as not to track the target date, or;
4. Review link types and set advances, i.e. review work execution procedures. For example, in
this case, you can make the “Legal Analysis” and “Marketing Analysis” tasks parallel. It is also necessary
to create a link between the tasks "Legal Analysis" and "Business Plan Making." As we do, Figure 5.6.
Now, if you move the mouse cursor to a segment of the project stage, an inscription will appear
about the nesting of tasks (16 days), which indicates that the nested tasks have a reserve of 4 days for
execution delays, so as not to disrupt the directive period of the stage.
In the event of a failure of the directive date for planning on the start of the project, it is necessary
either to revise the key date itself, or to reduce the duration of the tasks of the stage.
The next step with the tasks of the “Land Allocation” stage is to determine their relationships. We
highlight all the tasks of this stage, transfer them to automatic planning and associate them with links like
"End - Start."
After that, we remove the connection between the task "It was decided to start the stage of the " TEJ of
the project "and "Development of land management documentation," and instead of it we create a new
one between tasks "Decision on the start of the project" and "Development of land management
documentation," Figure 5.7. Stage "Land allocation" is transferred first to automatic planning, and then
to manual planning.
Figure 5.7 - Tasks of the "Land allocation" stage
Engineering Tasks
The “Design” stage shall consist of sub-stages (summary tasks) and works given in Table 5.3.
Before creating tasks, we immediately put the total task "Design" into manual planning mode.
We change the type of task as follows, select the necessary tasks using the "Ctrl" key, right-click
and select in the "Information" menu. In the "Information about several tasks" window, go to the
"Advanced" tab and select the type of task.
Once you have defined the task parameters, you must associate them. We associate all the tasks of
the design stage with the “End – Start” links.
We also establish the link "End - beginning" between the tasks "End stage
"Land allocation" and "Development of draft design," Figure 5.8.
If, when detailing a stage into tasks, the total duration of the nested tasks exceeded the specified
directive duration of the stage, you simply need to revise the duration of the stage by increasing it by
the required number of days.
As you can see from Figure 5.10, the delivery tasks did not move to the installation of the window.
This is because tasks have a default constraint type of “As Early As Possible”. As previously described,
tasks with this type tend to be performed as early as possible, in our case, this is at the beginning of the
project. In order for these tasks to move to the installation, it is necessary for all tasks of the "Deliveries"
stage to select the restriction "As soon as possible," Figure 5.11, and for the summary task - the limitation
"Ending no later than."
In order for these tasks to move to above-groundwork, all tasks of the stage need
"Settlements with suppliers" select the restriction "As soon as possible," Figure 5.12, and for the summary
task - the restriction "End no later than."
The task "Implementation of the cottage" is renamed to "Agreement with the client." We associate
all the tasks of this stage with each other with the links "End - beginning." Task
"Agreement of the contract with the client" begins after the task "Construction is completed," Figure 5.13,
and the old connection that went to the task "Agreement of the contract with the client" (renamed
"Implementation of the cottage") is removed.
The last stroke is to remove the link between the “Customer Agreement” task and the “Project
Complete” task. To the "Project Complete" task, we stretch the connection from the "Project Complete"
checkpoint.
The result of work decomposition is shown in Figure 5.14.
QUESTIONS
1. What do I use custom fields for? How do I create a custom field?
2. How is a custom view created? How is a custom table created?
3. How to display information about exceeding the target dates
performing tasks? How can you eliminate excess?