House Construction Cost Estiamtion Sheet For Lo

Material Quantity Unit Rate

UP TO PLINTH
1 Excavation Work - Earthwork 14447.50 cu. ft. 3.00
2 Filling in Foundation - Earthwork 11932.41 cu. ft. 3.00
3 PCC Work in Foundation(1:2:4) 1083.56 cu. ft.
Cement 191.29 Bags 350.00
Sand 470.57 cu. ft. 35.00
Aggregate 941.15 cu. ft. 45.00
3 Concrete work in foundation 1910.00 cu. ft.
Cement 429.15 Bags 350.00
Sand 791.78 cu. ft. 35.00
Aggregate 1583.56 cu. ft. 45.00
4 Steel in Foundation 3714.00 Kg 50.00
Total

Ground Floor
1 Concrete work - 1st Floor 1140.46 cu. ft.
Cement 260.00 Bags 350.00
Sand 500.00 cu. ft. 35.00
Aggregate 1000.00 cu. ft. 45.00
Steel in Column, Beam, Slab, Stair 3017.00 Kg 50.00
3 Brickwork at First Floor 1750.00 Sq. ft.
Bricks 18000.00 Nos. 5.00
Cement 55 Bags 350.00
Sand 425 cu. ft. 35.00
4 Plaster (Inner) at 1st Floor(1:4) 48.21.52 Sq. ft.
Cement 120 Bags 350.00
Sand 600 cu. ft. 35.00
5 Plaster (Outer) at 1st Floor(1:3) 1923.50 Sq. ft.
Cement 48 Bags 350.00
Sand 230 cu. ft. 35.00
6 Floor Tiles 793.49 sq. ft. 25.00
7 Skirting Tiles 1315.9 ft 20.00
8 Marble Work on Stair Steps 14.301 sq. ft. 55.00
Marble Skirting 27.208 ft 20.00
9 Bathroom Floor Tiles 200.78 sq. ft. 30.00
Wall Tiles 882.98 sq. ft. 30.00
10 Waterproofing in bath & Toilet 200.78 sq. ft. 50.00
11 Balcony Railing 28.58 ft 50.00
12 Door Wood Work 123.38 cu. ft. 500.00
Total

Total Materials Cost

Total Labour Cost

Total Construction Cost


on Sheet For Loan

Unit Amnout

cu. ft. ₹ 43,343 Rs.


cu. ft. ₹ 35,797 Rs.

Bags ₹ 66,952 Rs.


cu. ft. ₹ 16,470 Rs.
cu. ft. ₹ 42,352 Rs.

Bags ₹ 150,203 Rs.


cu. ft. ₹ 27,712 Rs.
cu. ft. ₹ 71,260 Rs.
Kg ₹ 185,700 Rs.
Total ₹ 639,788 Rs.

Bags ₹ 91,000 Rs.


cu. ft. ₹ 17,500 Rs.
cu. ft. ₹ 45,000 Rs.
Kg ₹ 150,850 Rs.
Rs.
Nos. ₹ 90,000 Rs.
Bags ₹ 19,250 Rs.
cu. ft. ₹ 14,875 Rs.
Rs.
Bags ₹ 42,000 Rs.
cu. ft. ₹ 21,000 Rs.
Rs.
Bags ₹ 16,800 Rs.
cu. ft. ₹ 8,050 Rs.
sq. ft. ₹ 19,837 Rs.
ft ₹ 26,318 Rs.
sq. ft. ₹ 787 Rs.
ft ₹ 544 Rs.
sq. ft. ₹ 6,023 Rs.
sq. ft. ₹ 26,489 Rs.
sq. ft. ₹ 10,039 Rs.
ft ₹ 1,429 Rs.
cu. ft. ₹ 61,690 Rs.
Total ₹ 669,482 Rs.

aterials Cost ₹ 1,309,270 Rs. 65%

abour Cost ₹ 704,991 Rs. 35%

struction Cost ₹ 2,014,261 Rs. 100%