PROGRESS REPORT

PROYEK : AHU PRE COOLING GUEST ROOM


PEKERJAAN : INSTALL DEHUM GUEST ROOM ST. REGIS, KUNINGAN
PO NUMBER : POCIP/H/00039/04/23
TANGGAL PENGAJUAN : 19/06/2023

PROGRESS PROGRESS THIS PROGRESS


Total Harga Weight PREVIOUS MOUNTH COMULATIVE
NO URAIAN PEKERJAAN SAT VOL Remarks
( Rp ) %

% Weight % Weight % Weight

PEKERJAAN PERALATAN UTAMA


Pengadaan dan Pemasangan Sistem Air Handling Unit c/w Material Bantu.

sesuai spesifikasi teknis yg berlaku .

A.1 Air Handling Pre Cooling Unit - ( AHU DX ) S-4 Unit 1 227,879,000
13.72 - 75 % 10.29 75 % 10.29
Merk : ITU

Model : Indoor CS 032 SH DS 2" 8A12 + Outdoor VRF LG (Multi V 5 Pro)

Capacity : 100.000 Btu/h

Air Flow : 3.500 Cfm

Spec AHU CS : Blower Backward Curve

: Include panel Control Unit

: Cooling Coil

: Fix Pulley dilengkapi dengan Fan Belt (Fix Grooved Pulley)

: Viledon washable Filter 2"

: Casing Isolasi panel menggunakan PU double Skin (PU Insulated Panel) Casing 2"

: Spring Vibration Isolator

: Manual Airvent

A.2 Dehumidifier for Control Humidity Unit 1 421,779,000


25.39 - 30 % 7.62 30 % 7.62
Brand : LUTA (LT-DR3000K) Ex. China

Kapasitas : 3000 CMH

A.3 Pekerjaan Instalasi Ducting & Grille / Diffuser

Ducting Pre Insulated duct dengan bahan PIR panel D.52 kg/m3 x T.20mm , c/w Alumunium

Embose , Bayonet , Flange's U PVC , Covering angle , Sealent , Spliter Damper , Tape Alm

Hanger, support (Complete Jacketing Ducting Area Luar)

1 Supply dan Return Duct Pre Insulated Duct ( MERK TD DUCT ) m2 54 35,424,000
2.13 - 80 % 1.71 80 % 1.71
A.4 PEKERJAAN LISTRIK FOR DEHUM

Panel Control Dehum, Comp Schneider Panel Maker & Control PLC Unit 1 45,828,000
2.76 - 80 % 2.21 80 % 2.21
Parameter dalam HMI : Suhu, RH, Status On/Off, Alarm, Setpoint

KABEL POWER DEHUM NYY (4C x 10 mm2 ) + NYA 6mm2 m 40 10,800,000


0.65 - - - -
KABEL POWER AHU NYY (4C x 6 mm2 ) + NYA 4mm2 m 25 4,275,000
0.26 - - - -
KABEL Control LYICY 8 x 0,75mm2 m 24 1,608,000
0.10 - - - -
KABEL TRAY 200x100mm m 24 14,352,000
0.86 - 80 % 0.69 80 % 0.69
Kabel Toefur dari SDP ke Panel Control Dehum

Handheld Visala Instrumen ( Alat Ukur) Unit 1 12,541,000


0.76 - 100 % 0.76 100 % 0.76
B.1 Air Handling Pre Cooling Unit - ( AHU DX ) S-26 Unit 1 227,879,000
13.72 - 80 % 10.98 80 % 10.98
Merk : ITU

Model : Indoor CS 032 SH DS 2" 8A12 + Outdoor VRF LG (Multi V 5 Pro)

Capacity : 100.000 Btu/h

Air Flow : 3.500 Cfm

Spec AHU CS : Blower Backward Curve

: Include panel Control Unit

: Cooling Coil

: Fix Pulley dilengkapi dengan Fan Belt (Fix Grooved Pulley)

: Viledon washable Filter 2"

: Casing Isolasi panel menggunakan PU double Skin (PU Insulated Panel) Casing 2"

: Spring Vibration Isolator

: Manual Airvent

B.2 Dehumidifier for Control Humidity Unit 1 421,779,000


25.39 - 30 % 7.62 30 % 7.62
Brand : LUTA (LT-DR3000K) Ex. China

Kapasitas : 3000 CMH

B.3 Pekerjaan Instalasi Ducting & Grille / Diffuser

Ducting Pre Insulated duct dengan bahan PIR panel D.52 kg/m3 x T.20mm , c/w Alumunium

Page 1 of 2
PROGRESS REPORT
PROYEK : AHU PRE COOLING GUEST ROOM
PEKERJAAN : INSTALL DEHUM GUEST ROOM ST. REGIS, KUNINGAN
PO NUMBER : POCIP/H/00039/04/23
TANGGAL PENGAJUAN : 19/06/2023

PROGRESS PROGRESS THIS PROGRESS


Total Harga Weight PREVIOUS MOUNTH COMULATIVE
NO URAIAN PEKERJAAN SAT VOL Remarks
( Rp ) %

% Weight % Weight % Weight

Embose , Bayonet , Flange's U PVC , Covering angle , Sealent , Spliter Damper , Tape Alm

Hanger, support (Complete Jacketing Ducting Area Luar)

1 Supply dan Return Duct Pre Insulated Duct ( MERK TD DUCT ) m2 54 35,424,000
2.13 - 80 % 1.71 80 % 1.71
B.4 PEKERJAAN LISTRIK FOR DEHUM

Panel Control AHU & Dehum, Comp Schneider Panel Maker & Control PLC Unit 1 45,828,000
2.76 - 80 % 2.21 80 % 2.21
Parameter dalam HMI : Suhu, RH, Status On/Off, Alarm, Setpoint

KABEL POWER DEHUM NYY (4C x 10 mm2 ) + NYA 6mm2 m 40 10,800,000


0.65 - - - -
KABEL POWER AHU NYY (4C x 6 mm2 ) + NYA 4mm2 m 25 4,275,000
0.26 - - - -
KABEL Control LYICY 8 x 0,75mm2 m 24 1,608,000
0.10 - - - -
KABEL TRAY 200x100mm m 24 14,352,000
0.86 - 80 % 0.69 80 % 0.69
Kabel Toefur dari SDP ke Panel Control Dehum

C PEKERJAAN LAIN-LAIN & PRELIMINERIES

Peralatan Bantu & Material Bantu & Comsumable Lot 1 10,010,000


0.60 - 50 % 0.30 50 % 0.30
Erection / Handling Unit Dehum ke Lokasi Penempatan Lot 1 11,001,000
0.66 - 50 % 0.33 50 % 0.33
Safety & Preparation Lot 1 4,120,000
0.25 - 50 % 0.12 50 % 0.12
Testing & Commisioning Lot 1 3,530,000
0.21 - - - -
Transportasi & Akomodasi Lot 1 20,000,000
1.20 - 50 % 0.60 50 % 0.60
PEKERJAAN DUDUKAN UNIT AHU = 2 Unit, CDU = 2 Unit & Dehum 2 Unit Lot 1 75,908,000
4.57 - 100 % 4.57 100 % 4.57

TOTAL HARGA PEK. DEHUM 1,661,000,000 100.00 52.39 % 52.39

JAKARTA, 18 JUNI 2023


PREPARED BY : APPROVE BY :
PT. DWI MITRA TEKNINDO PT. PERMADANI KHATULISTIWA NUSANTARA

ICHFAN PRIYANTO
PROJECT INCHARGE

Page 2 of 2