Sub Total Dismantling Works Carried to Summary

Vistex Hospital boq


Quotation Proposed
Item Location MAKE
Unit Quantity Rate Rs. Amount Rs. Rate Rs. Amount Rs. Difference

1.00 Dismantling works


1.00 Dismantling works -
1.00 Total Dismantling works -

2.00 Civil works Rs.


2.10 R.C.C. Slab, 150MM Thick First &Second Floor Concerete
Cu. M ,PPC/PSC cement,Cement- ULTRATECH/NUVOC
9600 O ,Chips used – Koderma,
9600Sand – Gaya
2.20 R.C.C. Slab, 75 MM Thick First &Second Floor Chajja Works ) Concerete
Sq. Mtr ,PPC/PSC cement,Cement- ULTRATECH/NUVOC
3800 O ,Chips used – Koderma,
3800Sand – Gaya
3.20 R.C.C. Lintel First &Second Floor RFT 340 340
2.30 230mm Thick. Exposed Brick Work First &Second Floor Sq.Ft. 335 335
2.40 230mm Thick. Brick Work First &Second Floor Sq.Ft. 210 210
2.50 150mm Thick. Brick Work First &Second Floor Sq.Ft. 165 165
2.60 100mm Thick. Brick Work First &Second Floor Sq.Ft. 150 150
2.70 150mm Thick. R.C.C. Wall Lift Cu. M 10800 10800
2.80 230mm Thick. R.C.C. Wall Lift Cu. M 10600 10600
2.90 R.C.C. Counter, 75mm Thick Bathroom Cu. M 12500 12500
2.10 Wall Plaster Internal Internal Walls Sq.Ft. 36 31
2.11 Wall Plaster External External Walls Sq.Ft. 55 55
2.12 Water Proofing Sq.Ft. 60 60
2.13 Beam Cu. M 10400 10400
2.14 Column Cu. M 10800 10800
2.15 R.C.C. Staircase Cu. M 16500 12000
2.16 Ramp 120mm Thick Cu. M 10400 10400
2.17 Reinforcement M.T 80000 71358
Sub Total Civil Works Carried to Summary

3.00 Floor Finish


3.10 Anti-Skit Vitrified Tiles 01/Stone 01 Toilet Area Nitco/ Kajaria/
Sq.Ft.Hindware /As Sample/As Approved
145 145
3.20 Anti-Skit Vitrified Tiles 02/ Stone 02 Corridor/Waiting Area Nitco/ Kajaria/
Sq.Ft.Hindware /As Sample/As Approved
135 135
3.30 Anti-Skit Vitrified Tiles 03/ Stone 03 Hospital Nitco/ Kajaria/
Sq.Ft.Hindware /As Sample/As Approved
120 120
3.40 Granite Stone Staircase Nitco/ Kajaria/
Sq.Ft.Hindware /As Sample/As Approved
240 240
3.50 Counter Top Stone Bathroom Counter Nitco/ Kajaria/
Sq.Ft.Hindware /As Sample/As Approved
300 300
3.60 Stone Ledge Wall Top Cladding Bathroom Legde Top/Counter Side Nitco/ Kajaria/
R.Ft.Hindware /As Sample/As Approved
360 360
3.70 Stone LIning On Parapet Parapet Nitco/ Kajaria/
R.Ft.Hindware /As Sample/As Approved
300 300
Sub Total Flooring Works Carried to Summary

4.00 Wall Finish


4.10 P.O.P. Punning Over Internal Wall Internal Walls J.K / SakrniSq.Ft.
/As Sample 28844.99 21 21
4.20 P.O.P. Punning Over External Wall External Walls J.K / SakrniSq.Ft.
/As Sample 18 18
4.30 Tile Dado (1050mm ht) Corridor/Waiting Area/Rooms Nitco/ Kajaria/
Sq.Ft.Hindware /As Sample/As Approved
150 150
4.40 Tile Dado (2100mm ht) Bathrooms Nitco/ Kajaria/
Sq.Ft.Hindware /As Sample/As Approved
135 135
4.50 Stone Ledge wall (1050mm ht) Bathroom Nitco/ Kajaria/
Sq.Ft.Hindware /As Sample/As Approved
300 300
4.60 Paint over Internal walls Internal Walls Asian/ Burger / Spectrum
Sq.Ft. /As Sample/As app.
20 20
4.70 Paint over External walls External Walls Asian/ Burger / Spectrum
Sq.Ft. /As Sample/As app.
20 20
Sub Total Wall Finish Carried to Summary

5.00 CEILING WORKS


5.10 Gypsum False Ceiling Bathroom Saint Gobin/ Boral/As
Sq.Ft.Sample /As App 105 105
5.20 P.O.P. Punning Over Ceiling First &Second Floor Sq.Ft. 25 25
5.30 Trap Door First &Second Floor Sq.Ft. 450 450
Sub Total Ceiling Works Carried to Summary

6.00 Door and Windows


6.10 DOOR FRAME -WOODEN / ALUMINIUM FRAME As R.Ft.
Sample 465 465
6.20 WINDOW ALUMINIUM FRAME As Sample
R.Ft. 375 375
6.30 GLASS DOOR WINDOW ALUMINIUM FRAME andShutters As Sample
RFt 480 480
6.40 6-8 MM TOUGHENED GLASS As Sample
Sq.Ft. 145 145
6.50 FLUSH DOOR PANEL Amuliya/
Nos. Green/ Durian/ As sample 10800 10800
6.60 ROLLER BLINDS / ROMAN BLINDS Mac/ Vista/ Assample
Sq.Ft. 140 140
Sub Total Doors and Windows Carried to Summary

7.00 Plumbing
7.10 CP FITTINGS & ALLIED
7.1.1 Washbasin First and Second Floor Nos.
Jaguar/Aquaviva/ Perryware/As Sample 3000 3000
7.1.2 Water closet (indian ) First and Second Floor Jaguar/Aquaviva/ Perryware/As
Nos. Sample 4000 4000
7.1.3 Water closet First and Second Floor Jaguar/Aquaviva/ Perryware/As
Nos. Sample 6500 6500
7.1.4 URINAL First and Second Floor Nos.
Jaguar/Aquaviva/ Perryware/As Sample 16500 16500
7.1.5 Sanitary ware ,CP FITTINGS & ALLIED Washrooms Nos 1200 1200
7.1.6 Health faucet First and Second Floor Jaguar/Aquaviva/
Nos. Perryware/As Sample 800 800
7.1.7 Bibcork First and Second Floor Jaguar/Aquaviva/
Nos. Perryware/As Sample 1600 1600
7.1.8 Angle valve First and Second Floor Jaguar/Aquaviva/
Nos. Perryware/As Sample 300 300
7.1.9 Conceal Cistern/ Flush Valve First and Second Floor Jaguar/Aquaviva/
Nos. Perryware/As Sample 5500 5500
7.1.10 Soap holder First and Second Floor Jaguar/Aquaviva/
Nos. Perryware/As Sample 600 600
7.1.11 Towel ring First and Second Floor Jaguar/Aquaviva/
Nos. Perryware/As Sample 600 600
7.1.12 Braided hose First and Second Floor Jaguar/Aquaviva/
Nos. Perryware/As Sample 450 450
7.1.13 Floor drain with Cockroch Trap First and Second Floor Jaguar/Aquaviva/
Nos. Perryware/As Sample 850 850
7.1.14 Basin mixer First and Second Floor Jaguar/Aquaviva/
Nos. Perryware/As Sample 3900 3900
7.1.15 Bating area spout First and Second Floor Jaguar/Aquaviva/
Nos. Perryware/As Sample 1200 1200
7.1.16 Diverter First and Second Floor Jaguar/Aquaviva/
Nos. Perryware/As Sample 4500 4500
7.1.17 Waste and Soil Line Works First and Second Floor , W.C , Bathing Area ( Wash
Prince Basin
Nos. , Urinal Counted inW.C and
/Appolo Bathing Area )
22500 11250
7.1.18 Hot and Cold WATER SUPPLY INSTALLATION First and Second Floor , W.C , Bathing Area ( Wash
Prince Basin
Nos. , Urinal Counted inW.C and
/Appolo Bathing Area )
14800 7400
7.1.19 Rate Basis for Item 7.1.17 and 7.1.18
7.17 Waste and Soil Line Works Washrooms /Pantry / Terrace /LandscapePrakash/
Area Supreme/Prince
R.Ft 1350 1350
7.18 Waste and Soil Line Works Washrooms /Pantry / Terrace /LandscapePrakash/
Area Supreme/Prince
R.Ft 1080 1080
7.19 Waste and Soil Line Works Washrooms /Pantry / Terrace /LandscapePrakash/
Area Supreme/Prince
R.Ft 750 750
7.20 Waste and Soil Line Works Washrooms /Pantry / Terrace /LandscapePrakash/
Area Supreme/Prince
R.Ft 675 675
7.21 WATER SUPPLY INSTALLATION Washrooms /Pantry / Terrace /Landscape Area 0
7.22 WATER SUPPLY INSTALLATION Washrooms /Pantry / Terrace /Landscape Area Nos 6500 6500
7.23 WATER SUPPLY INSTALLATION Washrooms /Pantry / Terrace /Landscape Area Nos 5800 5800
7.24 WATER SUPPLY INSTALLATION Washrooms /Pantry / Terrace /Landscape Area Nos 5200 5200
7.25 WATER SUPPLY INSTALLATION Washrooms /Pantry / Terrace /Landscape Area Nos 4500 4500
7.26 WATER SUPPLY INSTALLATION Washrooms /Pantry / Terrace / LandscapeSupreme
Area /Prince 0
7.27 WATER SUPPLY INSTALLATION Washrooms /Pantry / Terrace /LandscapeSupreme
Area /Prince
Rm 275 275
7.28 WATER SUPPLY INSTALLATION Washrooms /Pantry / Terrace /LandscapeSupreme
Area /Prince
Rm 325 325
7.29 WATER SUPPLY INSTALLATION Washrooms /Pantry / Terrace /LandscapeSupreme
Area /Prince
Rm 405 405
7.30 WATER SUPPLY INSTALLATION Washrooms /Pantry / Terrace / Supreme /Prince
Rm 675 675
7.31 WATER SUPPLY INSTALLATION Washrooms /Pantry / Terrace /LandscapeSupreme
Area /Prince
Rm 796 796
7.32 WATER SUPPLY INSTALLATION Washrooms /Pantry / Terrace /LandscapeSupreme
Area /Prince
Rm 980 980
Sub Total Modular Furniture Carried to Summary -

9.00 ELECTRICAL
9.10 Light Points Finloex, Havells,
Sq.Ft. Crabtree ,Achror, Panasonic/
70 Crompton/As App/As Sample 55
9.20 Wiring Switch Socket/ A.C /Kitchen Equipment's/ Audio Video and other Equipment's Finloex, Havells,
Sq.Ft. Crabtree ,Achror, Panasonic/
75 Crompton/As App/As Sample 70
9.90 Exhaust Finloex, Havells,
Nos. Crabtree ,Achror, Panasonic/
3500Crompton/As App/As Sample 3500
9.10 Geyser Finloex, Havells,
Nos. Crabtree ,Achror, Panasonic/
6000Crompton/As App/As Sample 6000
9.11 Ceiling Fan Finloex, Havells,
Nos. Crabtree ,Achror, Panasonic/
2400Crompton/As App/As Sample 2400
9.12 Ceiling Light Finloex, Havells,
Nos. Crabtree ,Achror, Panasonic/
650Crompton/As App/As Sample 650
9.13 Mirror Lights Finloex, Havells,
Nos. Crabtree ,Achror, Panasonic/
1000Crompton/As App/As Sample 1000
Note: CCTV and Specific Door Lock Entry to be designed and discussed.
Sub Total Electrical Works Carried to Summary -

11.00 Fire Fighting


11.10 Fire Sprinklers Nos. 85 85
11.20 Smoke Detector Edwards, Sq.
Conventional/
Ft Agni 65 55
Sub Total Fire Fighting Works Carried to Summary

12.00 MISCELLENOUS
12.10 Railing 900mm High Staircase R.Ft. 1350 1350
12.20 Railing Along Dado Corridor/Waiting Area R.Ft. 650 650
12.3. Tensile Roof Sq.Ft. 750 750
Sub Total Miscellaneous Works Carried to Summary
G. Total -

Including taxes @ extra -

Annexure - B
Terms and conditions:
All fees and sanctions required for the job though not limiting to M.C.D, Fire, Police and any other government body is to be arranged is to be paid separately and extra from the work contract rates mentioned
above.
30% as advance of total order value ,65% with running works and 5% on completion of work.
Freight & forwarding including in the above price.
Warrantee: 12 months warrantee/ standard equipment warranty , against manufacturing and installation defects (does not cover any consequential damage or losses. Does not cover normal wear and tear )
All the items would be as per the approved specifications and drawings only.
Any other item which shall come up during execution shall be charged separately as per mutually agreed rates.
Water and electricity has to be provided free of cost at site. In case of non availability from client’s side the same would be arranged by us and would be charged additionally @ 2% of the total work value.
All labor and installation charges included in the above mentioned price
The above mentioned qty is for rough estimate only the work would be done on as per actual measurements and final billing would be done after due measurements on site.
Period of final measurements 15 days from the date of submission of final bills.
Clause of force majurare should be applicable. I.e. We shall not be liable delay due to natural calamity, disaster ,strikes, riot or any other conditions which are beyond our control.
Delay due to approvals from statuary bodies like M.C.D, Fire Etc would be credited to time allotted for completion of project.
Escalation @ 5% would be applicable , (Any rate change by brands from the date of submission would be reflected in billing )
Material left over as wastage after completion of project would be property of m/s globespan design studio