Work Permit (For Function Room)
Work Permit (For Function Room)
Terms: The company/contractor hereby agree to indemnify and keep indemnified the Hotel from any and all claims, threats, demands, suit, damages, penalties, liability,
costs and expense incurred, suffered or expended by or threatened against the Hotel as a result of any theft or loss or damage to the goods, materials, tools and
equipment howsoever occurring whilst in the Hotel premises. The company/contractor acknowledges that the items are brought and retained in the Hotel premise at their
sole risk and shall not hold the Hotel liable for any loss and damage of items howsoever occurring.
CO./CONTRACTOR SUPERVISOR EVENTS MGR IN-CHARGE LIFE & SAFETY ENGR DIRECTOR OF ENG'G SECURITY MANAGER
I agree to above terms and I have reviewed and proper I have checked & certified that all I am aware of the Job to be I have checked with the Area-in-
confirm that the safety coordination has been precautions established are done and the precautions to be charge for any security
precautions specified will be conducted adequate taken requirements
Note: Person In-Charge shall appear when securing work permit. Otherwise, re-approval by Duty Engineer is required. Person In-Charge shall be
knowledgeable of the whole set-up including technical equirements.
GUIDELINES PRIOR TAPPING TO HOTEL'S POWER SOURCE
(REQUIREMENTS FOR LOADS MORE THAN THE CAPACITY OF CONVENIENCE OUTLET)
1. Organizer is required to secure tapping permit from the Engineering Office prior to the event.
a) Client/contractor shall submit to Duty Engineer (DE) the load schedule and wirings prior to tapping to Hotel power
source. DE shall assess and evaluate the power requirement.
b) Client/contractor shall provide their own disconnecting circuit breaker (CB) from the Hotel’s Electrical Panel (tapping
point). Refer below for respective function space electrical requirement:
CB
Function Space Qty Minimum Wire Size Requirement
Requirement
Tower Wing
Isla 1 to 3 60A, 2-Pole 2 sets Royal Cord, 3-conductors, 14mm2 (#6 AWG)
Palawan 1 to 3 60A, 2-Pole 1-set Royal Cord, 3-conductors, 14mm2 (#6 AWG)
Basilan & Boracay 1 & 2 40A, 2-Pole 1-set Royal Cord, 3-conductors, 5.5mm2 (#10 AWG)
Batanes 1 & 2 40A, 2-Pole 2 sets Royal Cord, 3-conductors, 5.5mm2 (#10 AWG)
Mactan 1 & 2 40A, 2-Pole 1-set Royal Cord, 3-conductors, 5.5mm2 (#10 AWG)
Lubang 40A, 2-Pole 1-set Royal Cord, 3-conductors, 5.5mm2 (#10 AWG)
Dapitan
Bohol
NO TAPPING POINT. CONVENIENCE OUTLET ONLY
Sulu
Marquee
Garden Wing
Rosal
Sampaguita
NO TAPPING POINT. CONVENIENCE OUTLET ONLY
Kamia 1 & 2
Santan 1 & 2
Garden Ballroom 1 to 4 60A, 2-Pole 1-set Royal Cord, 3-conductors, 14mm2 (#6 AWG)