Ms For Shoring Works
Ms For Shoring Works
Shoring system
Prepared for
Project
METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM
REVISION HISTORY
Prepared by Reviewed by
REV. Date Description
Construction Manager QA/QC Manager
METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM
Contents
1. SCOPE OF WORK........................................................................................................................................................................4
2. ACRONYMS & ABBREVIATIONS..................................................................................................................................................4
3. REFERENCES...............................................................................................................................................................................4
4. RESPONSIBILITIES.......................................................................................................................................................................4
4.1 Project Manager..........................................................................................................................................................4
4.2 Construction Manager.................................................................................................................................................5
4.3 QA/QC Manager..........................................................................................................................................................5
4.4 QA/QC Engineer.......................................................................................................................................................... 5
4.5 Site Engineer............................................................................................................................................................... 5
4.6 Site Foreman............................................................................................................................................................... 6
4.7 Site Land Surveyor.......................................................................................................................................................6
4.8 HSE Manager...............................................................................................................................................................6
4.9 HSE Officer...................................................................................................................................................................7
5. MANPOWER, EQUIPMENT AND MATERIALS..............................................................................................................................8
5.1 Manpower..................................................................................................................................................................8
5.2 Equipment...................................................................................................................................................................8
5.3 Material.......................................................................................................................................................................8
6. METHODOLOGY......................................................................................................................................................................... 8
6.1 General........................................................................................................................................................................8
6.2 Shoring System and Adjacent Structures Monitoring Method......................................................................................
7. QHSE PROCEDURE................................................................................................................................................................... 10
7.1 QUALITY.................................................................................................................................................................... 10
7.2 SAFETY.......................................................................................................................................................................10
7.3 Environmental Policy Implementation......................................................................................................................12
7.4 Housekeeping and Cleanup.......................................................................................................................................12
7.5 Site and HSSE Personnel Contact...............................................................................................................................12
8. ATTACHMENTS........................................................................................................................................................................ 13
METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM
1. SCOPE OF WORK
This method statement covers execute the solider piles wall required for the project utilizing Piling Method along the
ground shoring guide line already sitting by surveyor.
All works will be based on Project Specification and approved latest revision Construction drawings.
3. REFERENCES
Employer’s Requirements.
Project Quality Plan.
Project Health & Safety Plan.
Project Specifications.
Manufacturer`s Recommendations.
METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM
4. RESPONSIBILITIES
4.1 Project Manager
Ensures that the content of this method statement is understood and implemented at all times.
Coordinate with the Construction Manager to ensure that the necessary resources to implement the
approved Method Statement have been allocated to the task.
Determine all the requirements needed in order to comply with quality and safety standards and regulations
as required.
The Project Manager is responsible to appoint site supervisory personnel to organize, coordinate, and
oversee the execution of the work detailed in this method statement.
METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM
METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM
Issue necessary directives to Safety Officer / Supervisor and render advice to the Project Manager, as
required.
Prepare and submit HSE reports to, Client's / SEVEN Safety Executives whenever required.
Carryout HSE inspections at construction sites with reference to all HSE issues
Liaise with SEVEN HSE Department.
Take part in incident investigation and reporting of all Incidents.
Take part / attend in Client's HSE meetings.
Monitor and assess HSE measures on visits to sites.
METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM
5.2 Equipment
a. Drilling machine ( soilmec R622 )
b. welding machine
c. drilling tools (flight auger , core bucket , auger , core barrel ..)
d. Excavator
5.3 - Material
1. steel H-beam ( HEA-320 , HEA-240 )
2. Timber lagging ( 10x10 cm , 2m length )
6. METHODOLOGY
6.1 General
METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM
A temporary casing is used if required (inner diameter 60cm) is pitched and centralized over
the center of the beam at pile point.
An auger or bucket are used to excavate the pile shaft to the designed elevation.
In loose soil we can use the vibro hammer for installation of H-Beam .
In case we faced a rock formation the drilling will continue in rock to reach 50 cm down the
final excavation level of culvert slab as per SGS comment.
Record & photos and excavated materials (Fill, Soil and Rock) with depth shall be reported.
Before installing the H-Beams, H-beam should to be inspected by consultant with type and
length according to the design for each segment
After that, we bring the king – post beam and putting the H-Beam in the hole of pile, then
filling concrete mix around the H-Beam in order to ensure the full stability of the H-Beam.
We will repeat the above sequence that is continued for each alternative pile for the same
day.
In the next day, we will repeat the above sequence that is continued for each alternative
pile for previous day.
After we finish installation of king post beams for a proper part of shoring line (25 meter) ,
we can start excavation and fixing the timber lagging between beams,
excavation of the site (by one to two meter) and install the timber lagging between the two
H-Beam for Along perimeter of shoring line.
Repeat the previous sequence in excavation of the site and install timber lagging between
the two H-Beam for Along available shoring
Complete the previous steps till we reach the final excavation level
Repeat all the previous steps to cover the all the shoring line.
The main contractor will make monitoring and inspection of the soldier piles wall and
adjacent structures during the excavation works.
The king post shoring system is now complete
The works sequence shall be carried out under our experienced team supervision.
METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM
Upon excavation, the shoring system and the adjacent structures should be monitored.
Survey Marks spaced at max. 20m distance center to center will be added on the face of the
exposed Culvert or nearby structures and on the top of H-Beams in order to monitor the vertical and
horizontal displacement using calibrated survey instruments (Spirit level or/and Total Station)
referring to the project pre-defined control points.
The survey marks monitoring will be done regularly and report including the monitoring values and
graphical illustration shall be submitted to the Engineer.
7. QHSE PROCEDURE
7.1 QUALITY
All works will be undertaken in compliance with the quality requirements of the contract, and the Project
Quality Plan.
WIR shall be submitted after finishing the repair works of each specific area.
7.2 SAFETY
Safety for men and material have higher priority and all safety measures should be taken before doing any of
these activities mentioned above.
MSDS must be available at work location and material storage area.
Rubber glove and chemical protective PPE as per MSDS should use for this job.
All personnel to join safety induction prior to commencement of site.
Conduct toolbox talk on routine basis.
Hazards with regards to the activity and around to be communicated to personnel working at site.
RA is communicated to all the employees before commencing the work and acknowledged. Records will be
made available for verification
Safety officers to ensure safe condition of the workplaces.
Foreman / supervisor must ensure to rectify all observations indicated by the safety officer/s, personnel
working at site and or observed by anybody.
METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM
Foreman / supervisor always ensure safe working condition, hazard identification and control measure
implementation.
Ensure to have all required Works permits before to start activity.
Follow SEVEN procedure and permits requirements.
All hand tools and power tools will inspect before to use and will be color-coded.
Work permits, daily inspection is carried by the competent excavation supervisor and recorded.
Safety officers will be available in the work area until the work is completed.
PPE will be provided and have to wear at all times on site.
Method statements for all activities to be in place and discussed with workers.
Suitable access roads for equipment shall be provided by MBL.
Follow site speed limit, instructions, and warning signs.
All engine powered mobile plant and equipment shall be equipped with an audible reversing alarm device
will have 360° vision available.
All equipment shall hold suitable fire extinguisher.
The responsible supervisor will periodically check the condition of the barriers, and where necessary
refurbishment will be conducted.
Safety officer and job supervisor will ensure that PPE (Safety Shoe, Hard Hat, Hand Gloves, Reflective Vests,
Safety Goggles and Mask) are worn by site personnel at all times during the activity.
It will ensure proper access, egress and housekeeping during excavation, carpentry works, reinforcement and
concreting works to be maintained.
It will ensure the personnel engage on the activity will have relevant experience, further refresher trainings
will be conducted on site at routine basis.
Emergency response team for any emergency at site will be available further emergency contact numbers
will be displayed at various locations and also SEVEN given emergency number will be maintained and display
at site.
METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM
Construction manager
Construction manager
Construction manager
HSSE Supervisor
8. ATTACHMENTS
METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM
METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM
METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM
METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM