Method Statement

Shoring system
Prepared for

Project

P4 – Makkah Entertainment Complex

Method Statement No. MBL-CC-MES-0000XX, Rev.00

METHOD STATEMENT FOR SHORING WORKS


BERLINER-WALL SYSTEM

Document Reference #: MBL Method Statement 1 of 16


Revision: 00
Issued Date: 18 July 2023
P4 – Makkah Entertainment Complex

METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM

REVISION HISTORY

Prepared by Reviewed by
REV. Date Description
Construction Manager QA/QC Manager

00 11-Nov-23 For Approval

01 18-Jan-2024 For Approval

Document Ref. No. 4MAKA08-MAKA-08-MBL-CC-MES-00006 2 of 16


Revision: 01
Issued Date: 18 Jan 2024
P4 – Makkah Entertainment Complex

METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM

Contents
1. SCOPE OF WORK........................................................................................................................................................................4
2. ACRONYMS & ABBREVIATIONS..................................................................................................................................................4
3. REFERENCES...............................................................................................................................................................................4
4. RESPONSIBILITIES.......................................................................................................................................................................4
4.1 Project Manager..........................................................................................................................................................4
4.2 Construction Manager.................................................................................................................................................5
4.3 QA/QC Manager..........................................................................................................................................................5
4.4 QA/QC Engineer.......................................................................................................................................................... 5
4.5 Site Engineer............................................................................................................................................................... 5
4.6 Site Foreman............................................................................................................................................................... 6
4.7 Site Land Surveyor.......................................................................................................................................................6
4.8 HSE Manager...............................................................................................................................................................6
4.9 HSE Officer...................................................................................................................................................................7
5. MANPOWER, EQUIPMENT AND MATERIALS..............................................................................................................................8
5.1 Manpower..................................................................................................................................................................8
5.2 Equipment...................................................................................................................................................................8
5.3 Material.......................................................................................................................................................................8
6. METHODOLOGY......................................................................................................................................................................... 8
6.1 General........................................................................................................................................................................8
6.2 Shoring System and Adjacent Structures Monitoring Method......................................................................................
7. QHSE PROCEDURE................................................................................................................................................................... 10
7.1 QUALITY.................................................................................................................................................................... 10
7.2 SAFETY.......................................................................................................................................................................10
7.3 Environmental Policy Implementation......................................................................................................................12
7.4 Housekeeping and Cleanup.......................................................................................................................................12
7.5 Site and HSSE Personnel Contact...............................................................................................................................12
8. ATTACHMENTS........................................................................................................................................................................ 13

Document Ref. No. 4MAKA08-MAKA-08-MBL-CC-MES-00006 3 of 16


Revision: 01
Issued Date: 18 Jan 2024
P4 – Makkah Entertainment Complex

METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM

1. SCOPE OF WORK
This method statement covers execute the solider piles wall required for the project utilizing Piling Method along the
ground shoring guide line already sitting by surveyor.
All works will be based on Project Specification and approved latest revision Construction drawings.

2. ACRONYMS & ABBREVIATIONS


 SEVEN – Saudi Entertainment Venture; Client.
 MBL – Modern Building Leaders; Main Contractor.
 DAR – (LDC) Supervision Consultant.
 SAPL – (PMC) Saudi Arabian Parsons Limited
 HSE – Health safety & Environment.
 RA – Risk Assessment.
 PPE – Personal protective Equipment.
 QHSE – Quality, Health, Safety & Environment.

3. REFERENCES
 Employer’s Requirements.
 Project Quality Plan.
 Project Health & Safety Plan.
 Project Specifications.
 Manufacturer`s Recommendations.

Document Ref. No. 4MAKA08-MAKA-08-MBL-CC-MES-00006 4 of 16


Revision: 01
Issued Date: 18 Jan 2024
P4 – Makkah Entertainment Complex

METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM

4. RESPONSIBILITIES
4.1 Project Manager
 Ensures that the content of this method statement is understood and implemented at all times.
 Coordinate with the Construction Manager to ensure that the necessary resources to implement the
approved Method Statement have been allocated to the task.
 Determine all the requirements needed in order to comply with quality and safety standards and regulations
as required.
 The Project Manager is responsible to appoint site supervisory personnel to organize, coordinate, and
oversee the execution of the work detailed in this method statement.

4.2 Construction Manager


 Is responsible for the organization and coordination of the work detailed in this method statement.
 Is Responsible to provide all resources (Manpower, Materials, Equipment etc.) to the site required to execute
the job.

4.3 QA/QC Manager


 Responsible of the implementation of this procedure.
 Responsible for the arrangement of inspection, preparation of all documents and compiling them for the
inclusion in the final documentation packaged.

4.4 QA/QC Engineer


 Responsible to assist/advise the construction team to ensure all works comply with specified requirements.
 Monitor implementation of the controls as required.
 Ensure that all pre-concreting inspection i.e. formworks and reinforcement are done and approved by DAR as
per approved ITP.
 Ensure that all materials are delivered, stored and handled in proper manners to avoid damages.
 All activities are carried out as per approved ITP and inspection checklists.
 Hold inspections to verify work is implemented properly prior to client inspection.

4.5 Site Engineer


 The Site Engineer shall be responsible for the overall civil construction work:
 Shall be directly involved in the planning and execution of all activities.
 Monitor and coordinate all inter-related construction activities to ensure compliance with quality, schedule,
and sequence requirements.

Document Ref. No. 4MAKA08-MAKA-08-MBL-CC-MES-00006 5 of 16


Revision: 01
Issued Date: 18 Jan 2024
P4 – Makkah Entertainment Complex

METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM

 Coordinate inspection requests to QC Engineer.


 Control productivity and quality of work.
 Ensure proper handling and storage of material.
 Arrange the resources required (Manpower, Material, equipment etc.).

4.6 Site Foreman


 Ensure works carried out correctly and in a safe manner as per approved drawings.
 Acts as direct link between site engineer and workers.
 Arrange the labors, masons and skilled worker.
 Arrange all construction material to be available on time at site.
 Direct control of engaged resources and ensure meeting to set targets of production, quality, and safe works.

4.7 Site Land Surveyor


 Responsible for survey data will be acquired, archived correctly, and ensure that data processed and
interpreted correctly.
 Provide the required levels as per approved drawings.
 Coverage and density of acquired survey data will be as per specifications.
 Comprehensive instructions and proper supervision will be provided to the survey assistants.
 Ensure that calibration certificates are available with each instrument all the time for inspection.

4.8 HSE Manager


 HSE Manager is responsible to establish and implement an effective HSE management system in accordance
with SEVEN HSE requirements.
 Ensures the HSE management system requirements are implemented and maintained.
 Coordinates with the Site HSE team and the Construction Management team to ensure effective
implementation of the HSE Procedures.
 Assist risk assessment team to formulate Method Statement and JSA for specific construction activities.
 He may lead the entire team, maintaining HSE awareness and to create safe culture and working
environment through innovative ideas.
 Planning and coordinating the HSE Trainings for the project.

Document Ref. No. 4MAKA08-MAKA-08-MBL-CC-MES-00006 6 of 16


Revision: 01
Issued Date: 18 Jan 2024
P4 – Makkah Entertainment Complex

METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM

 Issue necessary directives to Safety Officer / Supervisor and render advice to the Project Manager, as
required.
 Prepare and submit HSE reports to, Client's / SEVEN Safety Executives whenever required.
 Carryout HSE inspections at construction sites with reference to all HSE issues
 Liaise with SEVEN HSE Department.
 Take part in incident investigation and reporting of all Incidents.
 Take part / attend in Client's HSE meetings.
 Monitor and assess HSE measures on visits to sites.

4.9 HSE Officer


 He will ensure that all the activities related to the specified task followed safely and all workers are wearing
PPE.
 Identify hazards and take measure control those hazards and follow risk assessment.
 He is responsible for monitoring and assessing hazardous and unsafe condition / situations.
 Developing measures to assure personnel safety.
 Correct unsafe acts or conditions through the regular line of authority.
 May exercise authority to prevent or stop unsafe acts when immediate action is required.
 Participate in planning meetings to identify any health and safety concerns inherent in the operations daily
work-plan.
 Inspects the site to ensure it is a hazard-free environment.
 Conduct toolbox meetings.
 Verify that all tools and equipment are adequate and safe for use.
 Promote safe practices at the job site.
 Enforce safety guidelines.
 Trains and carries out drills and exercises on how to manage emergencies.
 Watches out for the safety of all workers and works to protect them from entering hazardous situations.
 Respond to employees’ safety concerns.
 Advise and instruct on various safety-related topics (noise levels, use of machinery etc.).

Document Ref. No. 4MAKA08-MAKA-08-MBL-CC-MES-00006 7 of 16


Revision: 01
Issued Date: 18 Jan 2024
P4 – Makkah Entertainment Complex

METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM

 Conduct risk assessment and enforce preventative measures.


 Initiate and organize OHS training of employees and executives.
 Inspect premises and the work of personnel to identify issues or non-conformity (e.g., not using protective
equipment)
 Stop any unsafe acts or processes that seem dangerous or unhealthy.
 Prepare reports on occurrences and provide statistical information to HSE Manager.
 Carry out PTW Monitoring and review.

5. MANPOWER, EQUIPMENT AND MATERIALS


5.1 Manpower
1. Site Engineer.
2. QC Engineer.
3. Site Foreman.
4. Labor.

And other position will be arranged according to work schedule

5.2 Equipment
a. Drilling machine ( soilmec R622 )
b. welding machine
c. drilling tools (flight auger , core bucket , auger , core barrel ..)
d. Excavator

5.3 - Material
1. steel H-beam ( HEA-320 , HEA-240 )
2. Timber lagging ( 10x10 cm , 2m length )

6. METHODOLOGY
6.1 General

The installation of Berliner wall shoring construction procedure is as follows:


 Pile centre points shall be fixed on the temporary guide line.
 The piling rig moves to the position of the pile to be installed,

Document Ref. No. 4MAKA08-MAKA-08-MBL-CC-MES-00006 8 of 16


Revision: 01
Issued Date: 18 Jan 2024
P4 – Makkah Entertainment Complex

METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM

 A temporary casing is used if required (inner diameter 60cm) is pitched and centralized over
the center of the beam at pile point.
 An auger or bucket are used to excavate the pile shaft to the designed elevation.
 In loose soil we can use the vibro hammer for installation of H-Beam .
 In case we faced a rock formation the drilling will continue in rock to reach 50 cm down the
final excavation level of culvert slab as per SGS comment.
 Record & photos and excavated materials (Fill, Soil and Rock) with depth shall be reported.
 Before installing the H-Beams, H-beam should to be inspected by consultant with type and
length according to the design for each segment
 After that, we bring the king – post beam and putting the H-Beam in the hole of pile, then
filling concrete mix around the H-Beam in order to ensure the full stability of the H-Beam.
 We will repeat the above sequence that is continued for each alternative pile for the same
day.
 In the next day, we will repeat the above sequence that is continued for each alternative
pile for previous day.
 After we finish installation of king post beams for a proper part of shoring line (25 meter) ,
we can start excavation and fixing the timber lagging between beams,
 excavation of the site (by one to two meter) and install the timber lagging between the two
H-Beam for Along perimeter of shoring line.
 Repeat the previous sequence in excavation of the site and install timber lagging between
the two H-Beam for Along available shoring
 Complete the previous steps till we reach the final excavation level
 Repeat all the previous steps to cover the all the shoring line.
 The main contractor will make monitoring and inspection of the soldier piles wall and
adjacent structures during the excavation works.
 The king post shoring system is now complete
 The works sequence shall be carried out under our experienced team supervision.

Document Ref. No. 4MAKA08-MAKA-08-MBL-CC-MES-00006 9 of 16


Revision: 01
Issued Date: 18 Jan 2024
P4 – Makkah Entertainment Complex

METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM

6.2 Shoring System and Adjacent Structures Monitoring Method

 Upon excavation, the shoring system and the adjacent structures should be monitored.
 Survey Marks spaced at max. 20m distance center to center will be added on the face of the
exposed Culvert or nearby structures and on the top of H-Beams in order to monitor the vertical and
horizontal displacement using calibrated survey instruments (Spirit level or/and Total Station)
referring to the project pre-defined control points.
 The survey marks monitoring will be done regularly and report including the monitoring values and
graphical illustration shall be submitted to the Engineer.

7. QHSE PROCEDURE
7.1 QUALITY

 All works will be undertaken in compliance with the quality requirements of the contract, and the Project
Quality Plan.
 WIR shall be submitted after finishing the repair works of each specific area.

7.2 SAFETY
 Safety for men and material have higher priority and all safety measures should be taken before doing any of
these activities mentioned above.
 MSDS must be available at work location and material storage area.
 Rubber glove and chemical protective PPE as per MSDS should use for this job.
 All personnel to join safety induction prior to commencement of site.
 Conduct toolbox talk on routine basis.
 Hazards with regards to the activity and around to be communicated to personnel working at site.
 RA is communicated to all the employees before commencing the work and acknowledged. Records will be
made available for verification
 Safety officers to ensure safe condition of the workplaces.
 Foreman / supervisor must ensure to rectify all observations indicated by the safety officer/s, personnel
working at site and or observed by anybody.

Document Ref. No. 4MAKA08-MAKA-08-MBL-CC-MES-00006 10 of 16


Revision: 01
Issued Date: 18 Jan 2024
P4 – Makkah Entertainment Complex

METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM

 Foreman / supervisor always ensure safe working condition, hazard identification and control measure
implementation.
 Ensure to have all required Works permits before to start activity.
 Follow SEVEN procedure and permits requirements.
 All hand tools and power tools will inspect before to use and will be color-coded.
 Work permits, daily inspection is carried by the competent excavation supervisor and recorded.
 Safety officers will be available in the work area until the work is completed.
 PPE will be provided and have to wear at all times on site.
 Method statements for all activities to be in place and discussed with workers.
 Suitable access roads for equipment shall be provided by MBL.
 Follow site speed limit, instructions, and warning signs.
 All engine powered mobile plant and equipment shall be equipped with an audible reversing alarm device
will have 360° vision available.
 All equipment shall hold suitable fire extinguisher.
 The responsible supervisor will periodically check the condition of the barriers, and where necessary
refurbishment will be conducted.
 Safety officer and job supervisor will ensure that PPE (Safety Shoe, Hard Hat, Hand Gloves, Reflective Vests,
Safety Goggles and Mask) are worn by site personnel at all times during the activity.
 It will ensure proper access, egress and housekeeping during excavation, carpentry works, reinforcement and
concreting works to be maintained.
 It will ensure the personnel engage on the activity will have relevant experience, further refresher trainings
will be conducted on site at routine basis.
 Emergency response team for any emergency at site will be available further emergency contact numbers
will be displayed at various locations and also SEVEN given emergency number will be maintained and display
at site.

7.3 Environmental Policy Implementation


It is important that everyone involved in the project is aware of the environmental policy and environmental plan and
bound by their requirements. Approved documents should make clear the extent and standard of environmental
performance and assessment that is required as well as requirements for monitoring and reporting. These
requirements need to be cascaded down throughout the entire Project management.
Environmental plans require policing, and this done at a number of different levels:
Document Ref. No. 4MAKA08-MAKA-08-MBL-CC-MES-00006 11 of 16
Revision: 01
Issued Date: 18 Jan 2024
P4 – Makkah Entertainment Complex

METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM

 Environmental Manager will take responsibility for environmental matters.


 Environmental Manager to manage environmental matters day-to-day basis.
 MBL site HSE Management.

7.4 Housekeeping and Cleanup


 Housekeeping will be carried out at the end of each working day to remove surplus/waste construction and
unsuitable soil materials from the job site.
 Final site cleanup will be done on completion to leave the site free of debris and surplus materials.

7.5 Site and HSSE Personnel Contact

NAME POSITION / ROLE CONTACT

Construction manager

Construction manager

Construction manager

Sr. HSSE Engineer

HSSE Supervisor

8. ATTACHMENTS

 Data sheets & manufacturer method statements of proposed materials.


 ITP & Checklist.
 Risk Assessment.

Document Ref. No. 4MAKA08-MAKA-08-MBL-CC-MES-00006 12 of 16


Revision: 01
Issued Date: 18 Jan 2024
P4 – Makkah Entertainment Complex

METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM

Document Ref. No. 4MAKA08-MAKA-08-MBL-CC-MES-00006 13 of 16


Revision: 01
Issued Date: 18 Jan 2024
P4 – Makkah Entertainment Complex

METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM

Document Ref. No. 4MAKA08-MAKA-08-MBL-CC-MES-00006 14 of 16


Revision: 01
Issued Date: 18 Jan 2024
P4 – Makkah Entertainment Complex

METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM

Document Ref. No. 4MAKA08-MAKA-08-MBL-CC-MES-00006 15 of 16


Revision: 01
Issued Date: 18 Jan 2024
P4 – Makkah Entertainment Complex

METHOD STATEMENT
SHORING WORKS BERLINER-WALL
SYSTEM

Document Ref. No. 4MAKA08-MAKA-08-MBL-CC-MES-00006 16 of 16


Revision: 01
Issued Date: 18 Jan 2024