To be submitted for approval

RFI
Dear all,
Hope this mail finds you well,

In reference to the above-mentioned project, please follow the below link for electrical RFI for your kind
action.

Please take into consideration attachments 1 & 2

RFI
Dear all,
Hope this mail finds you well,

In reference to the above-mentioned project, please find the attached electrical RFI for your kind action.

Please take into consideration attachments 1 & 2

Please find attached for ‫برجاء الحصول على المرفق‬

As discussed in yesterday’s progress meeting about the ‫بناء على االجتماع باالمس بخصوص‬

Please follow the below link for ‫برجاء اتباع الرابط‬

Dear all,
Hope this mail finds you well,
I’m Inviting you to a meeting for Dammam Factory Project
Meeting Time : Tomorrow 4 October 2022 - 12 AM KSA Time – 11 AM Egypt time
Meeting Subject : Engineering Work Phase 01 Submittals Discussion
Meeting Link:-
Dammam Factory Meeting