M/S New India Contractors and Developers Pvt. Ltd.

Improvement/Construction of Existing Class-5 Road to NH Intermediate ane Specification with Hard Shoulder from Existing Km 76+340 to Km
Name of Project :- 134+940 (Design Chainage from Km 76+300 t Km 133+000) [Total Length 56.700 Km] of NH 505 (Sumdo-Kaza-Gramphoo Road) on EPC mode in
the state of Himachal Pradesh (Package-I)
CLIENT :- Border Roads Organisation
Consultant :- Border Roads Organisation
C- Other Works
SPS.No. 2 Period:- Sept & Oct-2023
b) Retaining Wall
Measurment
DATE OF Sub- SPS
S.NO RFI NO DESCRIPTION OF WORK Chainage Length in Remarks.
INSPECTION Side Nos. Total No.
Km.
Qty.

1 NICDPL/BRO/Pkg-1/STR/00089 19.07.2023 Retaining Wall Top Level Complete 90+800 90+860 RHS 1 0.060
2 NICDPL/BRO/Pkg-1/STR/000103 20.07.2023 Retaining Wall Top Level Complete 90+870 90+900 RHS 1 0.030 0.090 1
3 NICDPL/BRO/Pkg-1/HWY/000264 31-08-2023 Retaining Wall Top Level Complete 82+650 82+675 RHS 1 0.025
4 NICDPL/BRO/Pkg-1/HWY/000265 31-08-2023 Retaining Wall Top Level Complete 88+700 88+740 RHS 1 0.040
0.155 1
5 NICDPL/BRO/Pkg-1/HWY/000280 23.09.2023 Retaining Wall Top Level Complete 100+260 100+290 RHS 1 0.030
6 NICDPL/BRO/Pkg-1/HWY/000281(A) 25.09.2023 Retaining Wall Top Level Complete 101+360 101+450 RHS 1 0.090 0.120 2
7 NICDPL/BRO/Pkg-1/HWY/000495 30.10.2023 Retaining Wall Top Level Complete 100+010 100+075 RHS 1 0.065
8 NICDPL/BRO/Pkg-1/HWY/000509 31.10.2023 Retaining Wall Top Level Complete 90+580 90+620 RHS 1 0.040
9 NICDPL/BRO/Pkg-1/HWY/000510 31.10.2023 Retaining Wall Top Level Complete 90+630 90+655 RHS 1 0.025 0.130 2

Total Scope (Km) 3.035


Total for Cumulative QTY (Km) 0.405
Total for Previous QTY (Km) 0.155
Total for this Month (Km) 0.250