Professional Documents
Culture Documents
0006 - 033 Simultaneous Operations (Simops)
0006 - 033 Simultaneous Operations (Simops)
CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 DEFINITIONS
4.0 REFERENCES
5.0 RESPONSIBILITIES
6.0 REQUIREMENTS
7.0 DECISION TREE
* 8.0 APPROVAL
1.0 PURPOSE
The purpose of this General Instruction (GI) is to provide requirements for developing and implementing
Simultaneous Operations (SIMOPS) plans. SIMOPS plans are used to protect all personnel and company assets.
The risks associated with SIMOPS shall be managed with effective planning through the following steps:
• Changing schedules, if possible, to eliminate the need for SIMOPS.
• Limiting the number of simultaneous activities.
• Identifying preventive measures to be implemented prior to starting SIMOPS activities.
• Implementing effective communication rules among SIMOPS organizations.
Safe SIMOPS requires that all activities are identified, assessed, properly planned, communicated, authorized
and executed according to the SIMOPS plan. SIMOPS should only be undertaken if the associated risks are
appropriately mitigated and reduced to tolerable levels.
Note: This GI provides the minimum requirements for SIMOPS activities. For a detailed explanation inclusive
of examples, refer to SMG 06-007, Simultaneous Operations.
2.0 SCOPE
This GI applies to all Saudi Aramco (SA) facilities; onshore, offshore, project sites and project support facilities
covered under land use permits, where simultaneous activities may occur. Examples of where SIMOPS may take
place include; construction within an existing facility, during commissioning activities, upgrades, start up,
expansion projects, major plant shut downs, turnarounds, drilling, workover, pipeline work, laydown yards,
workshops, seismic work, subsea and well intervention work, etc.
Note: Section 7.0 contains a decision tree to assist with determining the need for SIMOPS.
3.0 DEFINITIONS
3.2 Lower Flammable Limit (LFL): The lower vapor concentration boundary for a specific compound, or
material of interest, at which the vapor-air mixture will propagate a flame (i.e., explode) if ignited. When
testing for combustible gas using gas monitoring instruments, the amount of combustible gas present is
specified in terms of % LFL: 0% LFL being a combustible gas-free atmosphere and 100% LFL being an
atmosphere in which the gas is at its lower flammable limit.
3.3 Qualitative Risk Assessment: A method of hazard analysis using descriptive scales or ranking schemes
(e.g., high/medium/low) to define the magnitude of potential consequences and the probability that those
consequences may occur. Qualitative analysis is generally used for an initial screening to identify risks that
require more detailed analyses. It can also be used where the level of risk does not justify, or where
numerical data is insufficient, for a quantitative analysis.
3.4 Readiness Review: This review involves key representatives from relevant parties to ensure that all
SIMOPS hazards have been identified and appropriately mitigated prior to beginning work.
3.5 Rupture Exposure Radius (RER): For toxic effects, the rupture exposure radius refers to the horizontal
distance from a leak source to specified levels of hydrogen sulfide (H2S) concentration, in parts per
million (ppm). Concentration thresholds to be considered are 30 ppm and 100 ppm for a well. For a
flammable gas hazard, with no toxic gases in its composition, the RER refers to the horizontal distance
from a leak source to half the Lower Flammable Limit (LFL).
3.6 Simultaneous Operations (SIMOPS): The activities of two or more work groups working near each
other where the actions of one work group may affect the safety of the adjacent work group personnel,
company assets or an adjacent operating facility.
3.7 SIMOPS Coordinator: The single point of contact for all SIMOPS activities to be conducted. This
position is not needed for all SIMOPS projects but is required for major project work with a high number
of SIMOPS activities or high-risk activities such as, but not limited to: total plant shutdown or up-grade,
onshore well work, offshore well work, hook up and commissioning of major projects with other nearby
activities such as laying pipelines or flowlines and drilling/workover with two or more rigs on the same
drill site/well pad. See section 5.6 for more details.
3.8 SIMOPS Matrix: This document encompasses all activities to be executed by various organizations,
work groups and contractors. It provides recommendations for the elimination and mitigation of workplace
hazards and control measures required to undertake simultaneous activities.
3.9 SIMOPS Plan: This plan clarifies the roles and responsibilities of parties involved in the work. It
establishes which operations take priority over others, and who has the overall decision-making authority.
It also establishes emergency response protocols, the work permit process, daily communication
requirements, highlights the hazards along with the appropriate elimination, mitigations and control
measures to be used.
3.10 SIMOPS Team: Personnel assigned by management to assess possible SIMOPS activities, develop the
risk assessment for these activities, and the SIMOPS plan.
4.0 REFERENCES
GI 2.100, Work Permit System
GI 6.012, Isolation, Lockout and Use of Hold Tags
SAES-B-062, Onshore Wellsite Safety
SMG 02-002, Qualitative Risk Assessment
SMG 06-007, Simultaneous Operations (SIMOPS)
SMG 08-001, Emergency Preparedness
5.0 RESPONSIBILITIES
5.5.2 Communicates, through the SIMOPS Coordinator, all actual and potential hazards and proposed
mitigation measures to the proponent and/or PMT.
5.5.3 Provides clear and effective communication and instruction to employees and sub-contractors,
including readiness review meetings and safety talks concerning:
• The SIMOPS plan
• Emergency response plans and procedures
5.5.4 Maintains direct control over the work and ensures contractors and subcontractors compliance
with the SIMOPS plan and this GI requirements.
6.0 REQUIREMENTS
6.1 Once a SIMOPS conflict or potential conflict has been identified, a meeting with all stakeholders shall be
held to discuss possible schedule changes to eliminate the need for SIMOPS.
6.2 If SIMOPS activities cannot be avoided, a team shall be assembled to assess the risks and develop the
SIMOPS plans.
6.3 The SIMOPS team shall consist of experienced personnel covering the various fields of work expected to
be used during the SIMOPS activities.
6.4 SIMOPS training shall be conducted for all people participating (or expected to participate) in the planning
of the SIMOPS. This training is available through Loss Prevention.
6.5 The team shall conduct a risk assessment, develop a SIMOPS plan, SIMOPS matrix and determine the
SIMOPS activity boundaries.
6.6 SIMOPS coordinator shall be assigned to coordinate all SIMOPS-related activities, if determined to be
necessary.
6.7 Prior to beginning SIMOPS activities, the leadership of all organizations participating in the SIMOPs
activities, shall attend a training session that explains the developed plan and associated matrix.
Individuals to be trained should include permit issuers, receivers, supervisors and those that have the
ability to control the work.
6.8 All agreed upon mitigation measures shall be in place prior to starting work.
* CHANGE ** ADDITION NEW INSTRUCTION COMPLETE REVISION
6.9 An integrated site-specific Emergency Response Plan (ERP) shall be developed for all parties involved in
SIMOPS activities. All personnel shall be trained on their respective responsibilities, as outlined in the
integrated ERP.
6.10 The integrated ERP must be discussed with all parties involved in SIMOPS prior to starting work. This
shall occur at least once per quarter while the work is ongoing, and immediately following any changes to
the ERP.
6.11 Conduct all work according to the SIMOPS plan and matrix.
6.12 Any deviation from the agreed upon SIMOPS plan shall follow the MOC process and be fully
communicated to all affected parties.
6.13 Daily pre-work coordination meetings shall be held to ensure the day’s work is allowed, as per the
approved plan and matrix.
6.14 Once SIMOPS work is complete, the asset management must confirm that all work has been completed
satisfactorily and accept handover of the asset from the work groups. This process must be formally
documented.
6.15 Any SIMOPS-related incidents must be reported, recorded and investigated, as stipulated in the
appropriate Saudi Aramco General Instructions.
6.16 All SIMOPS-related documents shall be held by the asset owner for a period of not less than three years
for auditing purposes.
SIMOPS Determination of
Planned Work
YES
NO
* 8.0 APPROVAL