تطبيقات على خطوط الكنتور
تطبيقات على خطوط الكنتور
AENG 268
3- Topographic Survey/Contouring
Field Work: Leveling Topographic Survey Data Capture
Field work Report I: Part III: Topographic Leveling
Construction of contours
9.8 10.2 10.6 11.2
Construction of contours
Scale 1:100
AENG 268
THE AMERICAN UNIVERSITY IN CAIRO Surveying for Architects
Department of Construction and Architectural Engineering Spring Semester 2013
1- X-sections
2- Terrain Slope
Site Analysis
AENG 268
THE AMERICAN UNIVERSITY IN CAIRO Surveying for Architects
Department of Construction and Architectural Engineering Spring Semester 2013
Contouring Applications
X-Sections
Scale 1:50
11
10
10 20 30
Scale 1:100
AENG 268
THE AMERICAN UNIVERSITY IN CAIRO Surveying for Architects
Department of Construction and Architectural Engineering Spring Semester 2013
Contouring Applications
Terrain Slopes
Y Contour
Slope = tan ѳ = Y Interval
X ѳ
X
Y = 0.5 m Real Distance between 2
contours (dist. On map
X = ?? * Scale)
Measured distance = 2cm
Map Scale 1:100
1cm on map : 100 cm on earth
1cm : 1m
Scale 1:100
2cm : ??
Scale 1:50
X = 2m
0.5
Slope = tan ѳ = * 100 = 25% 11
o 2
Ѳ = 14 10
10 20 30
AENG 268
THE AMERICAN UNIVERSITY IN CAIRO Surveying for Architects
Department of Construction and Architectural Engineering Spring Semester 2013
Contouring Applications
Terrain Slopes
2
Slope = tan ѳ = * 100 = 100%
o 2
Ѳ = 45
An Example:
Landuse Suitability Scale 1:100
0-4% V. Gentle slope Agriculture, Industrial
4-8 % Gentle Slope Residential
8-12% Med Slope Tourism, Residential, Services
12-25% Steep Slope Entertainment, Green spaces
25 – 40% Very Steep Slope No development
** The categories are not fixed and depends on terrain relief and the objective of the study
AENG 268
THE AMERICAN UNIVERSITY IN CAIRO Surveying for Architects
Department of Construction and Architectural Engineering Spring Semester 2013
AENG 268
THE AMERICAN UNIVERSITY IN CAIRO Surveying for Architects
Department of Construction and Architectural Engineering Spring Semester 2013
Contouring Applications
Cut & Fill Applications
The basic calculation is the difference between the desired elevation and the
original elevations
AENG 268
THE AMERICAN UNIVERSITY IN CAIRO Surveying for Architects
Department of Construction and Architectural Engineering Spring Semester 2013
Construction of contours
9.8 10.2 10.6 11.2
Construction of contours
9.8 10.2 10.6 11.2
Fill Area
Cut Area
Contouring Applications
Cut & Fill Applications
Using the elevation data and the grid system, a three dimensional model of the terrain (
TIN, DEM) & the cut-and-fill volumes can be constructed
Volume equals the average of the cell height times the area of the cell
2
- Cell Area C (50 )(50 ) C 2,500 m
3
VolumeC (2500) * 101.5 C 253,750 m
98+100+102+105
- Av. Height = = 101.5 m
4
m m
m
98
AENG 268
THE AMERICAN UNIVERSITY IN CAIRO Surveying for Architects
Department of Construction and Architectural Engineering Spring Semester 2013
Contouring Applications
Cut & Fill Applications
Development at this site requires that this area be at an elevation of 101
Cut/Fill Volumes = Proposed Volume – Original Volume
2 2
- Cell Area C (50 )(50 ) C 2,500 m - Cell Area C (50 )(50 ) C 2,500 m
98+100+102+105 101+101+101+101
- Av. Height = = 101.5 m - Av. Height = = 101
4
3
VolumeC (2500) * 101.5 C 253,750 m - VolumeC (2500) * 101 C 252,500 m
m m
m
98
AENG 268
THE AMERICAN UNIVERSITY IN CAIRO Surveying for Architects
Department of Construction and Architectural Engineering Spring Semester 2013
Contouring Applications
Cut & Fill Applications
Cut/Fill Height = Proposed Height – original Height ( + Fill / - CUT )
2
- Cell Area = (50 )(50 ) = 2,500 m
-1 - 4 + 1 + 3
- Av. Height = = - 0.25 m
4
-1 -4
+1
+3
AENG 268
THE AMERICAN UNIVERSITY IN CAIRO Surveying for Architects
Department of Construction and Architectural Engineering Spring Semester 2013
Contouring Applications
Site Analysis
1-Topographic Map ( Elevation Map)
4- Aspect map
1-Topographic Map
AENG 268
THE AMERICAN UNIVERSITY IN CAIRO Surveying for Architects
Department of Construction and Architectural Engineering Spring Semester 2013
1-Topographic Map
AENG 268
THE AMERICAN UNIVERSITY IN CAIRO Surveying for Architects
Department of Construction and Architectural Engineering Spring Semester 2013
1-Topographic Map
AENG 268
THE AMERICAN UNIVERSITY IN CAIRO Surveying for Architects
Department of Construction and Architectural Engineering Spring Semester 2013
1-Topographic Map
AENG 268
THE AMERICAN UNIVERSITY IN CAIRO Surveying for Architects
Department of Construction and Architectural Engineering Spring Semester 2013
Contouring Applications
Site Analysis
1-Topographic Map
4- Aspect map
Contouring Applications
Site Analysis
1-Topographic Map
4- Aspect map
Contouring Applications
Site Analysis
1-Topographic Map
4- Aspect map
4- Aspect map
AENG 268
THE AMERICAN UNIVERSITY IN CAIRO Surveying for Architects
Department of Construction and Architectural Engineering Spring Semester 2013
4- Aspect map
AENG 268
THE AMERICAN UNIVERSITY IN CAIRO Surveying for Architects
Department of Construction and Architectural Engineering Spring Semester 2013
Contouring Applications
Site Analysis
1-Topographic Map
4- Aspect map
Contouring Applications
Site Analysis
1-Topographic Map
4- Aspect map
Contouring Applications
Site Analysis
1-Topographic Map
4- Aspect map
AENG 268
AENG 268