Professional Documents
Culture Documents
Sacimem Steam Trap Survey
Sacimem Steam Trap Survey
Mahajanga, Madagascar
Dear Petro
Further to the steam system survey carried out on 12th April 2023 to 15th April 2023, I am pleased to
enclose the survey findings and steam trap inventory record.
We at Spirax Sarco East Africa trust that you will find this report resourceful and it assists you in the
equitable use of steam energy at the brewhouse. Should you be in need of further services or clarifications,
please do not hesitate to contact me.
Yours Faithfully
Wycliffe Apindi
M: +254113476132
E: Wycliffe.Apindi@ke.spiraxsarco.com
W: www.spiraxsarco.com/global/en-KE
Contents
Abstract………………………………………………………………………….1
Executive Summary………………………………………………………..4
Plant Information…………………………………………………………17
Detailed Replacement………………………………………………….23
A total of 17 steam traps were surveyed out of which; 10 steam traps (58.82%) were considered to be in
good condition and working efficiently. 1 steam trap (5.88%) was out of service, meaning that they it was
not in operation during the survey works, and 6 steam traps (35.29%) failed open meaning it is leaking live
steam during its operation, resulting to a loss of 184.13 tons per year which translates to a financial loss
of USD. 14,003.74 yearly. Please refer to page 4 for more on these.
It was also noted that certain good steam practices had not been adhered to resulting to plant problems,
such e.g. stall, incorrect installations and wet steam, these among others have been touched on in the
observation and recommendations section, kindly refer to page 8.
1
Boiler House
Boiler No. 2 1
Boiler Ref XF11/47439 4108-07790
Make Babcock-Wanson Babcock-Wanson
Type Fire tube Fire tube
Year of Manufacture 1992 1983
Design Pressure (bar) 50 30
Working Pressure (bar) 8 7
Output F & A (kg/hr) 2800/80 2250/80
Status – Live / Standby
Live Live
/ Maint
Level Controls
Temperature °C 30 30
Capacity (litre) 5000 5000
2
Condition – Good /
Average Average
Average / Poor
Insulated (Y/N) y y
Temperature controlled
No No
(Y/N)
3
Executive Summary
Annual Losses
Steam Loss 184.13 tonnes/year
Cost of Steam Loss 14,003.74 $
CO2 Emissions 36,810.45 kg/year
4
Executive Summary
5
Executive Summary
Bad Actor/Frequent Failures (Please refer to the Failure Frequency Report for further details)
Location Tag Number Failed Total Steam Loss Total Annual Cost ($) Application
(tonnes/year)
105 1 68.49 5,208.69 Drying cylinders
102 1 30.27 2,302.21 Separators
113 1 29.12 2,214.58 Separators
114 1 21.74 1,653.50 Heated rotating cylinder
106 1 18.54 1,409.90 Separators
110 1 15.97 1,214.86 Terminal ends
Application Total % Total Failed % Failed Application Total % Total Failed % Failed
6
Executive Summary
ANTSIRABE
110
VAKINANKARATRA
Madagascar
7
Observations & Recommendations
1. Incorrectly done drain pocket
At the steam supply header, it was noted that, their respective condensate return line was
incorrectly installed in terms of sizing and installation (see photo)
The effect of poor/incorrect condensate return line sizing, is that it results to accumulation of
condensate in the steam main. Here it can be picked up by high velocity steam, leading to erosion
and water-hammer in the pipework. To mitigate such occurrence, the below sizing parameters and
installation method should be adopted:
8
In addition, Air vents should also be installed at the terminal end of the steam line as illustrated
below to remove air present during start up. For this a ¼ “AV13 is recommended.
Still on the supply header, it is recommended that the isolation valve shown below, should be
removed and in its place, a steam trap installed, to ensure only condensate is drained while steam
is trapped
9
2. Poor safety valves installation
Provide venting pipe for the safety valves (highlighted in red) at the supply headers. It poses a
safety hazard presently as it is.
It’s recommended that the outlet pipework must be of longer length and directed to a safe point
for discharge where there is no risk of injury to persons or damage to property in the event of the
valve operating. In addition, it is essential at all times to ensure that the downstream pipework is
well drained so that downstream flooding (which can also encourage corrosion and leakage) cannot
occur, as shown below.
10
3. Mechanical pump maintenance
For the condensate return pump at the boiler house highlighted below, the following are
recommended to ensure its efficient operation
4. Insulation of ancillaries
It was noted at the steam supply header, the steam valves were not insulated hence heat loss
through convection to the environment was being experienced
11
Research has shown that an isolation valve having a size of DN100 and operating at an average
pressure of 10 bars lose about 16GJ of heat energy annually. Insulation jackets are hence
recommended to mitigate these losses i.e. DN80 isolation valve (8pcs), DN80 separator (2pcs),
DN80 strainer (2pc) and DN80 crown valves (2pcs)
Since boilers are CAPEX investment of high initial capital it is thus always important to always
ensure this important process is carried out to ensure there is no buildup of suspended solids in the
boiler shell, hence to enhance the blowdown process and limit human error, we recommend the
use of a timer controlled automatic blowdown process.
12
The timer should be capable of opening the valve at a specific time, and holding it open for a set
number of seconds. The use of automatic bottom blowdown ensures that this important action is
carried out regularly and releases the boiler attendant for other duties.
To achieve this we recommend the use of a spirax Sarco ABV2i bottom blowdown valve complete
with a blowdown timer and actuated solenoid valve.
13
7. Metering of steam generated
It was noted that there is no means of metering steam generated from both boilers.
Measuring steam is important as it will helps in providing vital information on usage and associated
costs that can improve efficiency in the following areas:
I. Plant Efficiency
Is idle machinery switched off?
Is plant loaded to optimum efficiency?
Identify cleaning and / or maintenance needs.
Identify major steam users.
Highlight peak steam usage periods.
Indicate whether working practices are satisfactory.
II. Energy Efficiency
Monitor results of energy saving schemes.
Compare efficiency of various pieces of plant.
14
8. Faulty mechanical pump
It was noted that, the mechanical pump conveying condensate to the feed tank from the rotary
dryer 1 was faulty.
This was confirmed by the low return of condensate to the feed tank. Moreover on further
investigation, it was discovered that, the respective pump was not efficiently operating hence there
was condensate accumulation at the receiver which eventually was being drained off through U-
bend overflow pipe to the drainage hence not being recovered.
15
it is recommended that the pump should be serviced to ensure its efficient operation, the following
are recommended:
Check the motive supply line to ensure steam is being supplied at the right pressure
Check the motive inlet and exhaust valves and replace as necessary
Check the mechanism component for any disjoint of the component
Check for any foreign item at the inlet and outlet non return valve which hinder their
operation obstruction.
16
Site Information
Currency $
Steam Source Primary Fuel Unit Cost of FuelCO2 Boiler Feed water Estimated Steam Generation
Pressure bar (g) Fuel Pressure Temp Boiler Cost
($) Efficiency ($)
Mass kg Default Light Oil 1.1400 /L 201.5 9.0 bar (g) 40°C 90 % 76.05
kg/1000kg
Average Hours of
Operation per Item
72 Hours Per
Week
X 52 Weeks Per
Year
17
Notes
Please review the cost of steam and operating hours to ensure this is suitable for your site.
If you feel any of the above figures are inappropriate, please do not hesitate to contact us and we will revise them accordingly.
18
Steam Loss & CO2 Emissions Summary
19
Steam Loss & CO2 Emissions Details
20
Steam Trap Replacement Report
105 Rotary Dryer DN40 (1 1/2") Flanged Drying Failed Open Replace 3.0 bar(g)
Eye 1 FT43-10 PN16 cylinders Large
Rotating Spirax Sarco Horizontal Suitable
Cylinder Float Right to Left Yes
106 Boiler House DN15 (1/2") Screwed Separators Failed Open Replace 8.0 bar(g)
High Supply Lines FT14-10 BSP Suitable Large
Spirax Sarco Horizontal Right to Left
Float Yes
110 Rotary Dryer DN25 (1") Flanged Terminal ends Failed Open Replace 6.2 bar(g)
Low 1 FT14-10 PN16 Non-Preferred Large
Steam Spirax Sarco Horizontal Right to Left
Supply line Float Yes
21
113 Conditioning DN25 (1") Flanged Separators Failed Open Replace 4.0 bar(g)
Low Cylinder FT14-10 PN16 Suitable Large
Steam Spirax Sarco Horizontal Right to Left
supply Float Yes
mains
114 Conditioning DN25 (1") Flanged Heated Failed Open Replace 3.0 bar(g)
Low Cylinder FT14-10 PN16 rotating Large
Drying Spirax Sarco Horizontal cylinder
cylinder Float Suitable Yes
Left to Right
22
Detailed Replacement Report
23
Detailed Replacement Report
Orientation Horizontal No
24
Detailed Replacement Report
25
Detailed Replacement Report
Orientation Horizontal No
26
Detailed Replacement Report
27
Detailed Replacement Report
Orientation Horizontal No
28
Detailed Replacement Report
29
Detailed Replacement Report
Orientation Horizontal No
30
Detailed Replacement Report
31
Detailed Replacement Report
Orientation Horizontal No
32
Detailed Replacement Report
33
Detailed Replacement Report
Orientation Horizontal No
34
Steam Trap Inventory Report
102 Boiler House DN25 (1") Screwed Separators Failed Open Replace 6.2 bar
Eye Supply Lines FT14-10 BSP Suitable (g)
Spirax Sarco Horizontal Right to Left Yes
Float
103 Boiler House DN25 (1") Screwed Separators OK None 6.2 bar
Eye Supply Lines FT14-10 BSP Suitable (g)
Spirax Sarco Horizontal Right to Left Yes
Float
104 Boiler House DN15 (1/2") Screwed Steam motive Not in Use None 8.0 bar
Low Mechanical FT14-14 BSP supply (g)
pump Spirax Sarco Horizontal Suitable Yes
Float Right to Left
35
105 Rotary Dryer DN40 (1 1/2") Flanged Drying Failed Open Replace 3.0 bar
Eye 1 FT43-10 PN16 cylinders (g)
Rotating Spirax Sarco Horizontal Suitable Yes
Cylinder Float Right to Left
106 Boiler House DN15 (1/2") Screwed Separators Failed Open Replace 8.0 bar
High Supply Lines FT14-10 BSP Suitable (g)
Spirax Sarco Horizontal Right to Left Yes
Float
107 Boiler House DN15 (1/2") Screwed Separators OK None 8.0 bar
High Supply Lines FT14-10 BSP Suitable (g)
Spirax Sarco Horizontal Right to Left Yes
Float
108 Rotary Dryer DN25 (1") Flanged Separators OK None 3.0 bar
Low 1 FT14-10 PN16 Suitable (g)
Steam Supply Spirax Sarco Horizontal Right to Left Yes
line Float
109 Rotary Dryer DN15 (1/2") Flanged Steam motive OK None 3.0 bar
Low 1 FT14-4.5 PN16 supply (g)
Mechanical Spirax Sarco Horizontal Suitable Yes
pump Float Right to Left
110 Rotary Dryer DN25 (1") Flanged Terminal ends Failed Open Replace 6.2 bar
Low 1 FT14-10 PN16 Non-Preferred (g)
Steam Supply Spirax Sarco Horizontal Right to Left Yes
line Float
36
Vessels Spirax Sarco
Float
112 Conditioning DN15 (1/2") Flanged Cooker OK None 1.0 bar
Low Cylinder FT14-10 PN16 Suitable (g)
Mixing Spirax Sarco Horizontal Right to Left Yes
Vessels Float
113 Conditioning DN25 (1") Flanged Separators Failed Open Replace 4.0 bar
Low Cylinder FT14-10 PN16 Suitable (g)
Steam supply Spirax Sarco Horizontal Right to Left Yes
mains Float
114 Conditioning DN25 (1") Flanged Heated Failed Open Replace 3.0 bar
Low Cylinder FT14-10 PN16 rotating (g)
Drying Spirax Sarco Horizontal cylinder Yes
cylinder Float Suitable
Left to Right
115 Conditioning DN15 (1/2") Flanged Heated OK None 3.0 bar
Low Cylinder TD32FLC PN16 rotating (g)
Drying Spirax Sarco Horizontal cylinder Yes
cylinder Thermodynamic Not Suitable
Left to Right
116 Conditioning DN15 (1/2") Flanged Terminal ends OK None 4.0 bar
Low Cylinder FT14-10 PN16 Non-Preferred (g)
Steam supply Spirax Sarco Horizontal Right to Left Yes
mains Float
117 Rotary Dryer DN25 (1") Flanged Heated OK None 3.0 bar
Low 1 FT14-10 PN16 rotating (g)
Rotating Spirax Sarco Horizontal cylinder Yes
Cylinder Float Suitable
Right to Left
37