Concrete Foundations
Concrete Foundations
Project
LINDE ENGINEERING
Shell Project No: HP-3000-QAT Contractor Project No : 5887
Project Document Number: T- 4.234.086 Project Rev.: B Page 1 of 10
SUPPLIER/VENDOR DOCUMENTATION
Purchase Order Number: 2MH127
No Comments. ACCEPTED.
X Code 1 Work May Proceed.
Unit(s): ASU
PCWBS: Z
QATAR SHELL GTL PROJECT (PEARL)
C2 AIR SEPARATION UNITS CONSTRUCTION
Document Title:
Q A T A R Date : 06.07.2009
CONTENTS
1. PURPOSE_______________________________________________________________________5
2. SCOPE_________________________________________________________________________5
3. REFERENCES__________________________________________________________________5
4. DEFINITIONS___________________________________________________________________5
5. RESPONSIBILITY_______________________________________________________________6
5.1. Site Manager______________________________________________________________________6
5.2. Surveyor__________________________________________________________________________6
5.3. QA/QC Inspector__________________________________________________________________6
6. METHOD OF EXECUTION_______________________________________________________6
6.1. General___________________________________________________________________________6
6.2. Monitoring intervals of foundations_________________________________________________7
6.3. Settlement behavior_______________________________________________________________7
6.4. Monitoring of settlement___________________________________________________________7
6.5. Monitoring of tilting________________________________________________________________8
6.6. Slopes____________________________________________________________________________8
6.7. Tank foundation___________________________________________________________________8
7. HSSE___________________________________________________________________________8
8. QUALITY ASSURANCE___________________________________________________________8
9. ATTACHMENTS________________________________________________________________9
Q A T A R Date : 06.07.2009
1. PURPOSE
This document describes the methods proposed to be used for the Monitoring of concrete
foundations that will be carried out as part of ASU Construction Works of Qatar Shell GTL Plant
(Pearl) in Ras Laffan Industrial City of Qatar including similar works in TSF Area.
2. SCOPE
This method statement identifies the monitoring activities of concrete foundations during and after
construction.
3. REFERENCES
T.4.234.542 Project Quality Plan
34.11.00.10 GEN Site Investigations
34.11.00.11 GEN Site Preparation and Earth works (Amendments T.13.376.352E)
34.11.00.12 GEN Geo Technical and Foundation Engineering
(Amendments T.13.376.360E)
BS 5930 Site Investigation
BS 6031 Earthworks
BS 8110 The Structural use of Concrete
4. DEFINITIONS
Q A T A R Date : 06.07.2009
5. RESPONSIBILITY
5.1. SITE MANAGER
The site manager will provide inputs to the project monitoring plan to ensure that Strategies
& philosophy are properly addressed.
5.2. SURVEYOR
Provide the markings and verify all details and record.
Maintain all the records and make non-conformity if observed. Inform the Contractor about
non-conformities.
6. METHOD OF EXECUTION
6.1. GENERAL
In order to monitor the concrete foundation, the followings are to be checked and recorded:
For horizontally loaded foundations, the horizontal movements should also be monitored.
Q A T A R Date : 06.07.2009
The monitoring marks etc. at the structure or foundation shall be installed by the contractor.
During his construction period, the contractor shall be responsible for carrying out the
monitoring.
Concrete foundations are to be marked to check the settlement and tilting.
Major Foundations for monitoring Lox tank, Lin tank, Cold box.
Mark 500 mm / or anchor bolt top elevation as datum from the top of floor elevation at
four location of the foundation during concreting.
The difference in elevation is the settlement of the foundation. If different elevations are
readed, the settlement is improper.
Check the coordinates of middle and corner points in the structure in vertical plane
during concrete and recording.
Verify as stated in the monitoring intervals the middle and the corner points. If found
any difference the same is the tilting. The same is to be recorded.
6.6. SLOPES
The stability of a slope should be monitored over a minimum period of six months after
completion of that slope. As a minimum a monthly visual inspection for cracks and
deformations shall be carried out. For major works monitoring should also comprise
measurements of pore pressure, settlements and horizontal displacements.
Q A T A R Date : 06.07.2009
7. HSSE
All works shall be in compliance with the State of Qatar laws and regulations, Ras Laffan Industrial
City and international standards/codes, and Company and Contractor requirements and
instructions.
All personnel will go through Gama, Linde and Company Safety Induction courses as well as other
trainings as identified by their supervisor. Please see Document Number GTL-GM-001-A-5635 for
details.
All personnel will have PPE required for their specific tasks in addition to the minimum PPE
(coveralls, safety goggles, safety shoes, high-visibility vests, gloves) at site at all times as required.
In the event of a release, fire or explosion, employees will secure their area and evacuate to the
nearest muster point. Once all employees are evacuated the supervisor will conduct a headcount to
verify all employees are out of harms way. The supervision will report this to Contractor. Emergency
Contact numbers for Company, Contractor and Gama will be posted onsite.
All vehicles and equipment used for the subject work will be inspected and certified as required.
Drivers and operators will be competent and will have attended all required trainings set forth in
project procedures and specifications.
8. QUALITY ASSURANCE
A Quality Assurance System shall be operated conforming to related standards. Controls and
checks shall be established and documented through relevant GAM-PRO-QAC-GTL-027 (QCP),
GAM-QCR-QAC-GTL-110 (QCR).
9. ATTACHMENTS
JSA