MATERIALS 7.

ADJOINING SOCKS MUST BE


OVERLAPPED AT LEAST 450mm, NOT
SOCKS: MINIMUM 200mm DIAMETER
ABUTTED.
SYNTHETIC OR BIODEGRADABLE TUBES
MANUFACTURED FROM NON-WOVEN OR
MAINTENANCE
COMPOSITE FABRIC SUITABLE FOR THE
‘FILTRATION’ OF COARSE SEDIMENTS.
1. INSPECT ALL FILTER SOCKS PRIOR TO
FILL MATERIAL: STRAW, CANE MULCH, FORECAST RAIN, DAILY DURING
COMPOSTED MATERIAL (AS4454), EXTENDED PERIODS OF RAINFALL,
COARSE SAND, OR CLEAN AGGREGATE. AFTER SIGNIFICANT RUNOFF
STAKES: MINIMUM 25 x 25mm TIMBER. PRODUCING STORMS OR OTHERWISE AT
WEEKLY INTERVALS.
INSTALLATION
2. REPAIR OR REPLACE DAMAGED FILTER
1. REFER TO APPROVED PLANS FOR SOCKS.
LOCATION AND INSTALLATION DETAILS.
IF THERE ARE QUESTIONS OR PROBLEMS 3. REMOVE COLLECTED SEDIMENT AND
WITH THE LOCATION, DIMENSIONS OR DISPOSE OF IN A SUITABLE MANNER
METHOD OF INSTALLATION CONTACT THE THAT WILL NOT CAUSE AN EROSION OR
ENGINEER OR RESPONSIBLE ON-SITE POLLUTION HAZARD.
OFFICER FOR ASSISTANCE.
REMOVAL
2. WHEN PLACED ACROSS
NON-VEGETATED OR NEWLY SEEDED 1. ALL EXCESSIVE SEDIMENT TRAPPED
SLOPES, THE FILTER SOCKS MUST BE BY THE FILTER SOCKS MUST BE
PLACED ALONG THE CONTOUR. REMOVED FROM THE DRAIN OR SLOPE IF
SUCH SEDIMENT IS LIKELY TO BE
3. IF PLACED ON OPEN OR LOOSE SOIL, WASHED AWAY BY EXPECTED FLOWS. Collected sediment
ENSURE THE FILTER SOCKS ARE
TRENCHED 50 TO 100mm INTO THE 2. DISPOSE OF COLLECTED SEDIMENT IN
GROUND. A SUITABLE MANNER THAT WILL NOT
CAUSE AN EROSION OR POLLUTION Socks recessed
4. ENSURE THE OUTER MOST ENDS OF HAZARD. 50 to 100mm
EACH FILTER SOCK OR CONTINUOUS
ROW OF FILTER SOCKS ARE TURNED UP 3. ALL SYNTHETIC (PLASTIC) MESH OR
THE SLOPE TO ALLOW WATER TO OTHER NON READILY BIODEGRADABLE
ADEQUATELY POND UP-SLOPE OF THE MATERIAL MUST BE REMOVED FROM THE
SOCKS, AND TO MINIMISE FLOW SITE ONCE THE SLOPE OR DRAIN IS
BYPASSING. STABILISED, OR THE SOCKS HAVE
DETERIORATED TO A POINT WHERE THEY
ARE NO LONGER PROVIDING THEIR
Catchments & Creeks Pty Ltd

5. ENSURE THE ANCHORING STAKES ARE


DRIVEN INTO THE END OF EACH SOCK INTENDED DRAINAGE OR SEDIMENT Figure 1 - Placement of filter socks
AND ALONG THE LENGTH OF EACH SOCK CONTROL FUNCTION.
AT A SPACING NOT EXCEEDING 1.2m OR
SIX TIMES THE SOCK DIAMETER Drawn: Date:
(WHICHEVER IS THE LESSER).