MATERIALS CONCENTRATION OF FLOW ALONG THE REMOVAL (IF REQUIRED)

BERM, OR THE UNDESIRABLE


COMPOSTS MUST COMPLY WITH THE DISCHARGE OF WATER AROUND THE 1. WHEN DISTURBED AREAS UP-SLOPE
REQUIREMENTS OF AS4454. ENDS OF THE BERM. OF THE BERM ARE SUFFICIENTLY
STABILISED TO RESTRAIN EROSION, THE
(i) WELL-DECOMPOSED 100% ORGANIC 4. ENSURE THE BERM HAS BEEN PLACED BERM MAYBE REMOVED.
MATTER PRODUCED BY CONTROLLED ALONG THE CONTOUR SUCH THAT
AEROBIC (BIOLOGICAL) DECOMPOSITION. WATER WILL POND EVENLY ALONG THE 2. REMOVE ANY COLLECTED SEDIMENT
LENGTH OF THE BERM. AND DISPOSE OF IN A SUITABLE MANNER
(ii) MAXIMUM OF 1% OF INERT MATERIAL. THAT WILL NOT CAUSE AN EROSION OR
5. ENSURE BOTH ENDS OF THE BERM POLLUTION HAZARD.
(iii) MAXIMUM SOLUBLE SALT ARE ADEQUATELY TURNED UP THE
CONCENTRATION OF 5dS/m, AND pH SLOPE TO PREVENT FLOW BYPASSING 3. REHABILITATE/REVEGETATE THE
RANGE OF 5.0 TO 8.5. PRIOR TO WATER PASSING OVER THE DISTURBED GROUND AS NECESSARY TO
BERM. MINIMISE THE EROSION HAZARD.
(iv) MOISTURE CONTENT OF 30 TO 50%
PRIOR TO APPLICATION. 6. ENSURE 100% CONTACT WITH THE
SOIL SURFACE.
INSTALLATION
7. WHERE SPECIFIED, TAKE
1. REFER TO APPROVED PLANS FOR APPROPRIATE STEPS TO VEGETATE THE
LOCATION AND EXTENT. IF THERE ARE BERM.
QUESTIONS OR PROBLEMS WITH THE
LOCATION, EXTENT, MATERIAL TYPE, OR MAINTENANCE
METHOD OF INSTALLATION CONTACT THE
ENGINEER OR RESPONSIBLE ON-SITE 1. DURING THE CONSTRUCTION PERIOD,
OFFICER FOR ASSISTANCE. INSPECT THE BERM AT LEAST WEEKLY
AND AFTER ANY SIGNIFICANT RAIN. MAKE Sediment-laden 100 mm (min)
sheet flow Max
2. WHEN SELECTING THE LOCATION OF A NECESSARY REPAIRS IMMEDIATELY. 300 mm (min)
COMPOST FILTER BERM, TO THE 1 grade
1
MAXIMUM DEGREE PRACTICABLE, 2. REPAIR OR REPLACE ANY DAMAGED
ENSURE THE BERM IS LOCATED: SECTIONS.
Recommended maximum berm spacing
(i) TOTALLY WITHIN THE PROPERTY Land slope Max spacing
3. WHEN MAKING REPAIRS, ALWAYS Compost filter berm
< 2% 35 m
BOUNDARIES; RESTORE THE SYSTEM TO ITS ORIGINAL 5% 25 m
(ii) ALONG A LINE OF CONSTANT CONFIGURATION UNLESS AN AMENDED 10% 20 m
ELEVATION (PREFERRED, BUT NOT LAYOUT IS REQUIRED OR SPECIFIED. 20% 12.5 m
25% 10 m
ALWAYS PRACTICAL);
4. REMOVE ACCUMULATED SEDIMENT IF
(iii) AT LEAST 1m, IDEALLY 3m, FROM THE THE SEDIMENT DEPOSIT EXCEEDS A Figure 1 - Typical profile of a compost filter berm
TOE OF A FILL EMBANKMENT; DEPTH OF 100mm OR 1/3 THE HEIGHT OF
Catchments & Creeks Pty Ltd

THE BERM.
(iv) AWAY FROM AREAS OF
CONCENTRATED FLOW. 5. DISPOSE OF SEDIMENT IN A SUITABLE
MANNER THAT WILL NOT CAUSE AN Drawn: Date:
3. ENSURE THE BERM IS INSTALLED IN A EROSION OR POLLUTION HAZARD.
MANNER THAT AVOIDS THE GMW Apr-10 Compost Filter Berm CFB-01