Professional Documents
Culture Documents
Cidp 2327 Draft For Validation
Cidp 2327 Draft For Validation
SIAYA COUNTY
County Integrated Development Plan 2023-2027
TO BE DISIGNED
Theme
Economic Transformation for Shared Growth
SIAYA COUNTY
2023-2027
VISION
MISSION
Achieve sustainable development and excellence using world class methods of service
delivery and technology with emphasis on public participation.
The unveiling of the third CIDP (2023-2027) marks an important milestone in the
development journey of Siaya county towards transforming the quality of services offered,
improving the living standards of the people and guaranteeing a shared prosperity. This CIDP
provides a bridge for transitioning from the first and second generation CIDPs, that laid the
foundation for sustained economic development, to creating a platform for implementing my
transformative agenda of good governance; improvement of healthcare services, promotion
of mechanized agriculture, trade and industrialization as well as empowerment of special
interest groups for the people of Siaya under the “Nyalore” manifesto. Implementation of the
preceding CIDPs was derailed by financial resource constraints and human resource
shortages among other challenges which the government is actively addressing through
proactive engagements with development partners and fixing human resource gaps to ensure
successful future implementation. Preparation of the third CIDP benefited from broad based
sectoral and public engagements as required by law. The Plan therefore, reflects the
aspirations of the government and that of the people of Siaya.
Implementation of this plan will be done through Annual Development Plans and budgets
while tracking of results will be achieved through routine monitoring and regular evaluation
of program objectives to provide a platform for continuous improvement of implementation
strategies. The bold interventions proposed in this document call for concerted efforts by all
actors for them to be achieved. I therefore call upon all government entities, the people of
Siaya and development actors to effectively play their respective roles towards the realization
of the aspirations of this CIDP whose theme is “Economic Transformation for Shared
Growth”
Preparation of this CIDP has been a widely consultative process that brought together
stakeholders representing various interest groups, the general public and a team of
government officers from both County and National Government. The broad programmes,
strategic interventions and priorities captured in the document will provide a basis for
addressing the needs of Siaya County residents by both levels of government.
I wish to underscore the consequential role of the entire county leadership in the preparation
of this document. Specifically, I express my gratitude to the Governor and the Deputy
Governor; the entire County Assembly leadership and the County Executive Committee
Members for providing leadership, vision, and resources for the preparation of this plan.
Secondly, I also wish to appreciate the role of chief officers and directors in coordinating
sector working group discussions and providing technical and logistical support incidental to
the preparation of this document. In addition, I acknowledge the entire CIDP Secretariat for
working tirelessly and providing technical backstopping in the preparation of the CIDP 2023-
2027.
Finally, the preparation of this document received contributions from development partners
and civil society organizations that highly enriched its content.
Chapter One provides an overview of the county by: giving background information (i.e.
establishment of the county, its location and size, administrative headquarters, ethnic and
religious composition, main economic activities and membership to regional economic
blocs); describing national and county government administrative units, political units as well
as physiographic and natural conditions (physical and topographic features, climatic and
ecological conditions,); analysing demographic structure, human development and
multidimensional poverty indices and blue economy potential. This overview brings out the
naturally existing potential of the county that sectors have leveraged on to design intervention
in chapter four that address the needs of the different age cohorts and strengthen
administrative governance across all the decentralized service delivery points.
Chapter Two reviews implementation of the preceding CIDP in terms of; actual sectoral
achievements against planned targets; mobilization of resources to finance the CIDP and
absorption of allocated funds. The chapter also highlights key challenges that hampered
implementation and lessons learnt in the course of implementing sectoral programs and
projects. the chapter concludes by analysing the county’s natural resource endowment as well
as development issues their current status, constraints towards achieving desired status and
opportunities that can be leveraged on. The challenges and lessons learnt helped improve
programming while the analysis of development issues sharpened sectoral strategic
interventions in chapter four.
Chapter three provides the spatial framework within which development projects and
programs have been prioritized in chapter four. The spatial framework has been discussed
under the thematic areas of: resource potential growth areas, enhancing county
competitiveness; modernizing agriculture; diversifying tourism; managing human settlement;
conserving the natural environment; transportation network; providing appropriate
infrastructure and industrialization as guided by three broad zones (the Green Spatial
Development, Brown Spatial Development and the Blue Spatial development).
Chapter five provides the implementation framework in terms of the institutions required to
successfully implement programs and projects discussed in chapter four. the institutional
Framework is described in the form of an organizational chart that provides clarity on the
flow of functions from the lowest to the highest office and vice versa. The chapter further
analyses the resource requirement for successful implementation of programs and projects,
revenue projection for the planning period based on known sources, the financing gap thereof
and strategies for bridging the resource gap. Additionally, the chapter demonstrates how
existing assets and those acquired during the implementation period will be managed. The
chapter concludes by the risks that are likely to derail implementation of programs and
projects during the plan period, the implication of the said risk on implementation and
mitigation measures to manage adverse impacts of the risks.
Chapter six provides the monitoring and evaluation and learning framework to ensure
implementation remains on course, program objectives are being met and general
organizational agenda is being achieved. The chapter therefore analyses the monitoring and
evaluation structure, the capacity of the directorate responsible for coordinating M&E,
Outcome indicators and their targets, data collection, analysis and reporting tools; evaluation
plan and dissemination of M&E findings to relevant stakeholders.
1.1 Background
Siaya County is one of the devolve units established under the Constitution of Kenya, 2010.
There are six sub counties and thirty wards with the County Headquarters located in Siaya
Town and sub-county headquarters located in Yala, Bondo, Aram, Ukwala and Ugunja. The
County is predominantly inhabited by the Luo community with minority communities such as
Luhya and Basuba commonly found in the border points. Emerging communities such as the
Maasai, Somalis, Kisii among others have immigrated into the county after devolution.
Majority of the residence are Christians with Islam and other African traditional
denominations also being practiced.
The main economic activity is agriculture comprising of crop and livestock production as
well as fishing. Crop and livestock production in the area is largely subsistence with a key
focus on maize, beans, cassava, finger millet, sweet potatoes, bananas, tomatoes, sorghum,
cattle, sheep, goats and chicken. Other economic activities include micro, small and medium
enterprises (SMEs) such as boda boda, jua kali, groceries, transport and retail stores. The
County also hosts two light industries that produce; Oxygen and Construction materials
(nails, chain link fence). The county has potential in irrigation agriculture, ranching, fish
processing, apiculture, textile industry and tourism.
The County is a member of the Lake Region Economic Bloc (LREB) comprising; Kisumu,
Migori, Homa Bay, Kericho, Bomet, Bungoma, Busia, Nandi, Kisii, Nyamira, Trans Nzoia,
Kakamega and Vihiga. The bloc aims at leveraging on economies of scale, optimizing
utilization of shared resources and maximization on member counties competitive and
comparative advantages in accelerating economic growth and improving the livelihood of the
people of the region.
The County is situated in the Western part of Kenya within Nyanza region. It approximately
lies between latitude 0º 26´ South to 0º 18´ North and longitude 33º 58´ and 34º 33´East.
Siaya County neighbours Vihiga and Kakamega Counties to the North-East, Kisumu County
to the South-East, Busia County to the North west and Homa Bay County across the Winam
Siaya County has three major geomorphological areas namely: Dissected Uplands, Moderate
Lowlands and Yala Swamp. These areas have different relief, soils and land use patterns. The
altitude of the County rises from 1,140m on the shores of Lake Victoria to 1,400m above sea
level on the North.
The Lower Midlands (LM 1-3) are sub-humid and humid zones with reliable precipitation.
Areas under LM5 are found in the lower parts of the County around the shores of Lake
Victoria. Both LM4 and LM5 are semi-humid, semi-dry lower midland zones classified as
marginal cotton and livestock and millet zones respectively. Figure 3 below gives county’s
Agro-ecological zones.
The county comprises of six constituencies and thirty wards. Alego Usonga, Bondo and Gem
constituencies have six wards each; Rarieda, Ugenya and Ugunja constituencies have five,
four and three wards respectively.
Constituency County Assembly Wards Ward Area
Alego- Usonga Township 42.6
Usonga 79.2
North Alego 53.8
South East Alego 191.5
Central Alego 139.8
West Alego 98.9
Gem North Gem 86
South Gem 63.3
In 2019, the population of the county was 993,183 consisting of 471,669 (47.5%) males and
521,496 (52.5%) females. This was projected to increase to 1,040,616 consisting of 525,833
males and 514,782 females in 2022. It is further projected to rise to 1,097,141 comprising
552,387 males and 544,755 females and 1,136,553 comprising 571,351 males and 565,202
females in 2025 and 2027 respectively. Population size, structure and distribution determines
how resources are allocated towards basic infrastructure as well as utilities. Table 5 below
presents the population and population projections for Siaya Sub-counties for the planning
period
Table 4; Population projection ( By Sub County and Sex)
Sub- Census (2019) 2022 Projection Projection
County (Projection) (2025) (2027)
M F Inter- T M F T M F T M F T
sex
Figure 6: Population Pyramid (Source: KNBS- Kenya Housing and Population Census, 2019)
There has been an increase in the number of urban centres both in the country and also within
Siaya County which is an indicator of increase in population and also rural to urban
migration. The most populous urban center is Siaya followed by Bondo, Usenge and Ugunja.
Urban populations should also be enumerated to assist in urban planning. It is common for
the younger populations to migrate to urban centers in search of a modern lifestyle and
employment opportunities and other economic activities. Table 7 below gives population
projections for urban centers in Siaya County.
Projection
Census (2019) 2022 (Projection) Projection (2025)
Urban Area (2027)
Total Total Total Total
Siaya 33,133 34,714 36,600 37,915
Bondo 22,694 23,777 25,069 25,969
Usenge 7,975 8,355 8,809 9,126
Ugunja 7,060 7,396 7,798 8,079
Sega 4,172 4,371 4,608 4,774
Nyandiwa Beach 4,033 4,225 4,455 4,615
Ndori 3,770 3,949 4,164 4,314
Yala 3,237 3,391 3,575 3,704
Sigomere 1,527 1,599 1,686 1,747
Ukwala 1,346 1,410 1,486 1,540
Ragengni 457 478 504 522
Table 7: Population Projections by Urban Centre (Source: KNBS)
Ugunja sub-county has the highest population density followed by Gem while Bondo sub-
county has the lowest population density. The County government will ensure that plans are
in place to relieve pressure on the available social amenities in the densely populated areas
and allocate adequate resources to less dense areas.
Table 9 presents data on population projections disaggregated by special age groups. This is
essentially a representation of the different planning requirements of the different segments of
the population.
Under 5 Years
The population of children under 5 in the 2019 population and housing census was 121,658
comprising of 60,867 male and 60,791 female. This is projected to increase to 138,339 with
68,930 males and 69,410 females in 2022, 142,288 comprising of 71,152 males and 71,136
females in 2025 while in 2027 it is projected to increase to 143,299 consisting of 71,646
males and 71,657 females. These children are vulnerable to many diseases and conditions
which require increased investment in mother to child health services, support infrastructure
The County Government in collaboration with the National Government will be working to
put more investment that generate employment for the youth and also embarking on building
more technical training institutes and youth polytechnics to enable the young people to
acquire technical, vocational and entrepreneurial skills to enhance their employability. The
County has also sensitization programmes for creating awareness among the youth on the
dangers associated with drug abuse, unprotected sex and exposure to HIV/AIDS among other
vices.
There is need for proper planning for persons with disability through establishment of a
system that improves disability inclusivity, access to education, employment opportunities,
financial services, housing, health care and welfare. Specifically, the County government will
provide tools, disability sensitive project designs and construct sheltered workshops during
the plan period.
Due to the above issues, the County government will address these challenges through
deliberate investment in programmes that create an enabling environment for enterprise,
industrial development and improvement of other social amenities and utilities. The county
government will also bring on board all development partners to develop and implement
policies and programs that integrate population dynamics, environment/climate change
during this plan period.
Lake Victoria, Lake Kanyaboli and the major rivers in the county support transport, fisheries
and agricultural production. However, the county is yet to explore blue economy fully. It is
imperative that the county put in place mechanisms to make the over 60 existing beaches
more economically active in terms of fishing, hospitality, transport, energy and tourism. In
addition, the county should take advantage of the expansive blue economy potential to invest
in;
This chapter reviews implementation of the 2018-22 CIDP. It presents an analysis of county
performance in terms of revenue, expenditure and key outcomes as well as major sector
challenges, emerging issues, lessons learnt, natural resource assessment and development
issues.
The Administration and Intergovernmental Relations sector is one of the eight (8) sectors that
have been created to ensure efficient approach to County Governance, Administration,
Financial Management, Economic Planning, ICT operations and County Legislation. It
consists of three subsectors namely: Finance and economic planning; Governance,
Administration and ICT, and County Assembly. The sector also consists of one Semi-
Autonomous Government Agency namely, the County Public Service Board.
The sector envisions quality service delivery through provision of efficient, effective, ethical,
equitable services and transformative leadership. The sector’s goal is to provide good
governance in service delivery.
The assembly approved oversight reports including a report on vetting of CECs, County
Secretary, County Attorney, Chief Officers and members of the County Public Service
Board; developed standard procedures for Committees and revised its Standing Orders.
To strengthen the representation role, the assembly: handled all petitions submitted;
conducted public participation programs; conducted awareness surveys and constructed 30
ward offices. Furthermore, the assembly initiated the construction of halls in 30 ward offices
and civil works in 4 ward offices.
During the plan period the assembly recruited staff; trained and provided loans and mortgage
facility to the staff; improved the transport system by acquiring vehicles; connected the
[Type text] Page 25
county assembly sewer system to the main sewer line; acquired and installed the hansard
system; upgrade the CCTV system; developed the ICT infrastructure; and developed the
Document Management System. The assembly further restructured and organized the wired
and wireless infrastructure; installed the virtual conference facilities; installed the PABX
within the offices and boardrooms; developed the E-business Process Management System;
and Implementation of Security Systems i.e., active directory with domain controller. The
assembly also provided good working environment by renovating and maintaining 50 car
parking and shades; completing sanitary installation; improving surface drainage at the
headquarters; improving leadership offices; refurbishing staff offices; completion of
committee boardrooms block; and completing electric-fencing the assembly headquarters.
The challenges faced by the assembly during the implementation period include: Poor target,
objectives and outcomes setting and formulation of the at the CIDP development level, and
low appreciation of the newly developed ICT systems. Specific emerging issue was court
cases surrounding the land for construction of the Assembly Complex.
To provide a conducive work environment, the department constructed and equipped the
county administrative Office (headquarters); recruited, promoted and trained officers;
provided enhanced Medical Cover to all staff; enhanced capacity building through
partnership with the World Bank- Kenya Devolution Support Programme (KDSP); paid
liabilities of the defunct Local authority staff and Improved payroll management.
Challenges experienced during the plan period include: Weak human resource and records
management system; Weak fleet management system; Weak enforcement and compliance
unit and Ineffective public participation and civic education.
[Type text] Page 26
During the implementation period the learnt that; Effective public participation and civic
education enhances good governance and ownership of county programmes and projects in
the county; Strengthening decentralized units enhances service delivery; a robust
performance management system enhances service delivery.
The department improved procurement services by ensuring strict adherence to relevant laws
;timely preparation of statutory and administrative reports; training of staff and suppliers/
contractors on E- Procurement module.
The Department improved policy formulation and execution through timely preparation of
statutory planning documents (CIDP, ADPs, CBROP,CFSP, CDMSP,SWG reports and
Budget estimates); establishment of the County Budget and Economic Forum (CBEF);
Preparation of periodic Budget Execution reports; improved Networking and Partnership with
key stakeholders (CRA, KNBS, COB)
To improve the work environment and service delivery, the department: constructed Archives
and offices; improved physical structures in the County Treasury; procured operational tools
and equipment; recruited 220 Revenue officers and facilitated training on E-Promis and
IFMIS.
Produced 30,000 MT of capture fish valued at about 4.42 billion Kenya shillings and 147.6
MT of culture fish. This was as a result of enhanced stakeholder engagement, fisherfolk
training, improved surveillance and provision of inputs.
Key Challenges during the implementation period included: Declining soil fertility; Pests and
diseases burden; Minimal processing and value addition; High cost of farm inputs; weak
extension and farmer linkages; Pre- and post-harvest losses; Over reliance on rainfed
agriculture; Low uptake of credit and technology; Low youth involvement in agricultural
value chains; land fragmentation and degradation.
During implementation, the department Learnt that: Effective extension delivery contributes
to higher adoption of agricultural technologies and leads to higher productivity; Effective
intergovernmental relations lead to synergy in control of diseases, project implementation and
partner coordination.
During the plan period, the county, under Water Supply and Management, planned to
increase water access and coverage from 55.1% to 65%. Currently the water access and
[Type text] Page 28
coverage stand at 58% which is attributed to: continued Support to 2 Water Service
Providers (SIBO & Maji Milele) and 10 Community Managed Water Schemes; drilling and
equipping of 140 Boreholes against a target of 100; laying of 381km of water pipeline against
a target of 350km; desilting of 75 Water pans against a target of 70; protection of 45 Springs
against a target of 60; augmentation and expansion of 9 water supply schemes against a target
of 10; construction of 24 water harvesting tanks against a target of 220 in public institutions.
The increase in water access and coverage is also attributed to investments by National
Government (Siaya – Bondo Water and Sanitation project and Ugunja – Sega – Ukwala water
project) and partners ( Maji Milele and Pisoko).
The sector planned to increase sewerage coverage from 5 percent to 15 percent but managed
to increase sewerage access to 5.5 percent through; Last Mile Connectivity Project in Bondo
and Siaya towns covering 204 connections which include institutions such as County Referral
Hospital and Jaramogi Oginga Odinga University of Science and Technology (JOOUST).
In the plan period, the sector planned to increase tree cover by 9 percent from 5.2 percent to
14.2 percent. During the period, the department increased tree cover by 1 percent from 5.2
percent to 6.2 percent through; establishment of 10 tree nurseries against a target of 190;
distribution and planting of 2,000,000 tree seedlings in 50 woodlot creations against a target
of 10 woodlots in public spaces. The riparian land along the 4 target rivers was conserved
(Sianda in East Ugenya, Nyandiwa in East Asembo, River Nzoia and Abura Dam).
The department also rehabilitated Lake Kanyaboli dyke against a target of 5 dykes. Number
of hilltops afforested were 3 (Got Mbaga, Got Regea and Got Rawalo) against a target of 12.
The sector planned to improve work environment and service delivery and achieved the
following; recruited 3 officers against a target of 50;trained 6 officers against a target of 25,
procured one vehicle against a target of 2; established 647 Management committees (target
of 771); increased revenue collection by 10 percent in the 1st year but there was a decline in
the subsequent years due to covid-19 restrictions.
Key Challenges experienced by the department during the period under review included: Old
and dilapidated water infrastructure; Vandalism of water infrastructure; Weak compliance
with the stipulated environmental and social safeguard systems; Low prioritization of
Environment projects; High cost of electricity; Lack of effective governance structure for
community managed water schemes.
During the plan period the department learnt that: Enhanced Partnership and linkages leads to
improved innovation in water service provision e.g. Prepaid metres and inline chlorination
techniques; Solarization of existing water supply schemes leads to sustainable operations.
At the beginning of the plan period, gross enrolment in Early Childhood Education was
76,680. At the end of the plan period, the number stood at 81,771. This achievement can be
attributed to construction of 96 ECDE centres, equipping of 35 ECD centres, establishment of
two centres of excellence in Bondo and Yala and implementation of school feeding programs
on pilot basis in East Asembo and West Alego.
Gross enrolment in vocational training centres was 1,580 at the beginning of the plan period.
At the end of the plan period, the enrolment stood at 3,706. This achievement is attributed to;
construction of 8, equipping of 31 and renovation 34 classrooms; construction of 2 computer
laboratory and administration blocks; provision of tuition support to 10,460 trainees through
capitation.
During the period under review, the sector improved livelihoods for vulnerable groups by
providing bursary to 45,266 students, construction of 2 sheltered workshops and provision of
996 assistive devices for PWD, celebration of annual international days for women and
persons with disability, training of 1,200 youth on positive behaviour change and leadership,
and 700 women on skilful parenting; supporting 30 youth groups to establish tree nurseries as
income generating activities in the 30 wards and training of 6 youth theatre groups in
partnership with Kenya Film Commission.
During the period under review the sector implemented the following projects outside the
plan; establishment of CT scan, renal, Intensive care, isolation units and blood bank. This was
done to improve quality of healthcare services, manage COVID 19 patients and limit referral
cases outside the county.
Key challenges during implementation included: Commodity stock outs; Inadequate medical
infrastructure and equipment; High disease burden; Low capacity and inadequate resources to
undertake research; weak referral system and reduced health financing due to declining
partner support
In the review period, the sector targeted to reduce land related conflicts and improve investor
confidence through land surveying and mapping of principal towns, intermediate urban
centres, public land, markets and county roads. The sector also targeted to improve efficiency
of land records through automation of public land and land banking. At the end of the
planning period, the sector managed to: erect nine control pillars in three principal towns and
intermediate urban centres; surveyed and demarcated boundaries for 100 public parcels, 200
Kms of county roads and 1 hectare of Got Ramogi heritage site.
To ensure efficiency in management of public land the sector: established land records office
at the County headquarters; digitized 7,000 public land records in five sub counties; acquired
22.13 Ha of land to increase its land bank; held 37 sensitization fora on land issues; delineated
12 Urban boundaries; approved 12 Market layout plans and prepared Siaya County Valuation
and Rating Bill, 2021. In addition, the sector planned to develop land use plans for principal
towns and markets. At the end of the plan period, the sector managed to develop 12 urban
plans and the County Spatial Plan.
To improve urban infrastructure and deliver affordable housing units to all, the sector
planned to improve motorized and non-motorized (NMT) transport infrastructure, construct
new and renovate existing housing units. At the end of the plan period the sector managed to;
establish Siaya Municipality which rehabilitated 2 recreational parks, constructed 2 km of
NMT and 0.7 km sewer extension. In housing development, the sector renovated 31 staff
housing units.
To improve working environment and service delivery, the sector planned to recruit and
promote staff, develop policies and acquire office operational tools, equipment and
machinery. In the review period, the sector recruited 6 officers, developed 5 policies and
procured 10 office equipment, two towing machines, a lawn mower and a field vehicle. The
sector also capacity built Siaya Municipality and the proposed Bondo and Ugunja
Municipality Boards.
Key challenges during implementation included: Limited public awareness on land matters;
Conflicts arising from encroachment on public land; absence of an updated Local Land Use
Plan; Historical double public land allocation hampering development; absence of a
[Type text] Page 33
Validated County Public Land Inventory limiting land administration and planning and Non-
responsive bids for land purchase.
During implementation, the sector learnt that: transfer of functions and resources will
strengthen municipality operations; operationalization of the valuations roll will improve own
source revenue and surveying and demarcating of public land reduces encroachment and
related conflicts.
Towards creating a conducive business environment, the sector: installed 53 high mast and 30
solar lamps; established 16 market management committees, constructed 68 sanitation
facilities, constructed 4 modern market sheds and 21 market sheds and undertook
infrastructural improvement in 44 markets.
To improve fair trade practices and consumer protection, the sector enforced compliance with
Weights and Measures Act, Cap 513 Laws of Kenya by: annual verification of 11,993
trader’s equipment; conducting 142 sensitization and awareness campaigns, undertaking 1292
impromptu inspections and test purchases at the trader’s premises and prosecuting 3 reported
offences.
Towards Improved administration and control of alcoholic drinks and substance abuse, the
sector issued cumulatively 2147 licenses to the liquor outlets and developed a business map
for all the alcoholic drinks outlet within the county.
The sector improved working environment and service delivery by recruiting 7 officers,
training of 3 officers; prepared 4 annual progress reports; purchased a set of operation
equipment and one motor vehicle; refurbished two office blocks.
To improve tourist attraction sites, the sector; undertook phased development of Got Ramogi
Hills; restored Mageta and Odero Akang’o Colonial Cells.
To promote Siaya as a tourism destination of choice, the sector; 1 policy and guideline;
distributed 10,507 publicity materials; organised 18 cultural and 7 talent search events;
attended 19 events; designated 7 parcels of land for tourism development; collaborated with
National Museums of Kenya and Kenya Forest Services on conservation and protection of
heritage sites.
To increase accessibility and mobility within the County the sector planned to; open 860km
of new roads; maintain 1850Km of existing roads, upgrade 23 km of roads to bitumen
standards; construct and maintain 16 bridges and upgrade 4 airstrips across the county.
To enhance building safety in the built environment the sector provided designs and bills of
quantities; supervised and inspected the construction of all public buildings.
The sector planned to improve adoption of climate friendly sources of energy by; equipping
50 boreholes with solar power; promoting use of renewable energy sources in 6000
households, establishing an energy center. At the end of the plan period, the sector
collaborated with the department of water and equipped 100 boreholes with solar power.
To Improve working environment, security and emergency response the sector planned to;
construct and equip a fire station, install solar lights and flood lights in urban centres and
markets. During the period under review the sector managed to strengthen operational
capacity through acquisition of a motor vehicle and laptops and training of eight officers.
During implementation, the sector learnt that: Collaboration with National government
agencies, in tarmacking of roads bridges technical capacity gaps; Involvement of surveyors
and locals in project identification and implementation reduces conflict; Implementation of
macro projects creates impact, reduces cost of supervision and improves quality; orientation
of contractors reduces conflicts during project implementation.
In the course of implementing the previous CIDP, the County government learnt that:
Participatory planning, budgeting, monitoring and evaluation lead to effective
implementation and ownership of projects and programs; decentralizing financial services
enhance implementation of programs and projects; provision of good working environment
and tools enhances staff productivity; adoption of ICT improves service delivery; robust
performance management system enhances service delivery.
Lake Agriculture, Fishing both capture Culture fishing Increasing water Existing Fisheries Act 0f
(Victoria, Irrigation Food and culture (Cages) levels 2017
Kanyaboli, and fisheries Irrigated farming Irrigation Crocodile menace Existing Soil Management
Sare, policy
Nyamboyo) Water hyacinth Existing Agriculture
policy
Upwelling
High cost of inputs
Water, Water levels expected Environmental Deteriorating water Lake conservation and
Environment and to decline with conservation area quality; rehabilitation programme
natural resources increasing irrigation
activities
Water levels expected Existing Public water Declining water Monitor water levels.
to rise due to effects source levels through
climate change irrigation;
Potential for revenue Sedimentation; Maintenance of dykes,
collection from water canals;
supply.
Overfishing Prepare and implement
leading to lake Water Resource
ecosystem Management plan
imbalance;
Eutrophication as a Collaborate with relevant
result of pollution; water Agencies (NEMA,
WRA etc)
Transport and Water transportation Transportation of goods Poor landing Construct jetties and
energy and people between infrastructure harbours in partnership
counties and countries with Kenya Maritime
Authority
Unpredictable Monitor and sensitize on
weather patterns meteorological trends
Trade, Declining raw Tourist attraction site Political interests -Enforcement of relevant
Industrialization materials for cottage environmental
and Tourism industries due to management laws
human encroachment
for irrigation
Fisheries resources Establishment of cottage Human-wildlife -formulation of
declining with industries conflict investment policy
intensified
exploitation -Over-
exploitation of
wetlands leading to
destruction of the Intensification of fish Resource-use -Establishment of land use
swamp farming conflict plan
Transport and Water transportation Increase connectivity by Rising water levels Monitoring and
energy construction of bridges leading to accidents sensitization on
meteorological trends to
limit water accidents
Sand harvesting income generation to Unpredictable Monitor and sensitize on
sand harvesters weather patterns meteorological trends
leading to flooding
Collaboration with
relevant water Agencies
(NEMA, WRA etc)
Trade, Land degradation due -Building material Land Degradation -Environmental
Industrialization to over-exploitation conservation -Alternative
and tourism source of livelihood
Publics Works -Employment Health hazards -Public sensitization on
Housing opportunity the effects of quarrying
Transport and Highly utilized in Income generation for Inaccessible roads Increasing access through
energy general construction sand harvesters and leading to sand opening and maintenance
works transporters harvesting sites of roads
Own source revenue for Rising water levels Monitoring of water
the County limiting sand levels
harvesting
Excavation of gravel Income generation for Excavation has Backfilling of existing
used in construction land owners, plant resulted to land borrow pits for sustainable
works operators and owners degradation agricultural use
Forests Water, Declining due to Water catchment Population increase -Development of Forest
(Got Environment and over-exploitation management plan
Ramogi natural resources (commercial and
and Got domestic use)
Abiero, 17
Community
forests)
Business Encroachment Afforestation Programmes
opportunity(beekeeping) (long rains and short
rains)
Improved economic Little legal Gazettement of
activity as a result of framework to community forests.
improved agriculture manage forests.
(micro climate)
Collaboration with
relevant water Agencies
(NEMA, KFS etc)
Trade, Deforestation due to Tourist attraction site Encroachment -Development of Forest
Industrialization over exploitation population and use plan
and Tourism agriculture
activities
Water catchment Competition for -Afforestation programme
forest resources-
wood and charcoal
Business opportunity -Multi-agency
(bee-keeping) collaboration in enforcing
relevant legislations
Support from
development partners
land Agriculture, Crop Farming, Reclamation of idle land High inputs cost, Existing Fisheries Act 0f
Irrigation Food Livestock keeping, prevalence of pests 2017
and fisheries Aquaculture and diseases, land Existing Soil Management
degradation policy
Existing Agriculture
policy
Lands, physical Unplanned Existence of County Budgetary/financial Development of urban
planning, housing settlements and urban Spatial Plan and land constraints planning policies
and Urban centers use plans
Development Untitled public and Existing partnership Out dated land use Development of land
private lands with National Land plans administration policies
Commission
Unsecured Modern technology in Budgetary Establish partnership with
boundaries land survey constraints development partners and
stakeholders
Ndanu falls Transport and Untapped hydro Generation of hydro The energy unit yet Monitoring of water levels
energy power generation power to be established
thus, limiting
implementation
Sunlight Solar power used for Use of Green energy Lack of funding to Establishing an energy
generation of support energy unit in the county
electricity programmes
Table 15: Natural Resource Analysis
46
12. Proposed increment in total government expenditure in the agricultural sector (strengthening
agricultural research and extension, credit to farmers, revival of farmers’ institutions and control of
crop and animals’ diseases).
3.1.2 Enhancing County Competitiveness
County Competitiveness positions the County for partnerships and economic development. The County is
predominantly rural with significant reliance on agriculture and local trade to spur its economic
development. The Siaya CSP now proposes leveraging on the Counties strengths i.e. Lake Front, Cultural
heritage, Natural resources i.e. Yala Swamp, Land mass and Minerals as well as opportunities in Tourism,
Fishing, Mining and ICT to make Siaya competitive and attractive to investors with a view to growing its
economy. To enhance the county’s competitiveness, the county will give focus to the following sectors;
Tourism:
Siaya County is strategically located next to the lake front which offers diverse tourism opportunities,
especially relating to water sports and outdoor water based restaurants. The County also boasts of cultural
heritage sites which have not been utilised to full potential as tourism attraction sites. To position Siaya
County as a premier tourism hub in the lake region, the following strategies should be implemented;
1. Construction and equipping of cultural centres.
2. Undertaking and developing a business and conference tourism initiative.
3. Developing water sports tourism (boat, racing, water skiing, swimming competitions, boat tours
4. Development of high-end hotel and Conference facilities in Siaya County.
5. Development of Community-Based Tourism activities.
6. Marketing Initiatives to enhance visibility of Siaya County.
7. Partnerships on the development of Wildlife Conservancies to promote tourism and solve wildlife-
human conflict;
8. Establishment of standards for tourism products and services in Siaya county; and
9. Development of road network within Siaya County for rural and urban areas targeting unique
heritage facilities and sceneries around and within the County.
Fishing
Fishing is a major economic activity in the county, with potentials for both local and export market. The
county borders Lake Victoria, the largest fresh water lake in Africa and second in the world and has the
potential for development of fish ponds. The county will invest in the industry to make it realise its potential
and its products competitive in the international market. Towards this, the county will put in place measures
to increase production, value addition and marketing. The industry is expected to contribute immensely to
47
the county’s local revenue generation and employment creation, thereby supporting poverty reduction
strategies in the Nyalore Manifesto.
Mining
Deposits of minerals, precious stones and rare earth elements have been traced in several areas within Siaya
County. Gold has been identified in Bondo, Siaya, Rarieda, Ugunja and Gem sub counties, Fluorite deposits
in Rata, Asembo, Granite and black sand in Yala valley and sand harvesting along beaches. The county shall
leverage on the availability of the minerals and precious stones to foster mining activities within the County.
Energy
Population of Siaya County is projected to increase to 1,136,554 in 2027. This point at an increased demand
for energy, hence need to explore untapped alternative sources of energy. This will improve reliability and
access to power while steering growth for other sectors such as agriculture, tourism, communication,
industries and trade. To realise improved reliability and accessibility to power, the county will deploy the
following strategies:
1. Tap on green energy sources and identify sites suitable for wind and solar energy plants.
2. Partner with developers of green energy.
3. Explore the possibility of hydropower generation (R. Nzoia and Yala, Dominion Farm).
4. Improve connectivity to power.
5. Improve the service quality.
3.1.3 Modernizing Agriculture
Kenya Vision 2030 identifies agriculture as one of the key sectors in the delivery of the 10 percent annual
economic growth rate envisioned under the economic pillar. This will be achieved through an innovative,
commercially oriented and modern agriculture, livestock and fisheries sector. The agricultural sector is the
backbone of County’s economy and supports livelihood for over 80 percent of the rural population and
contributes over 60 percent of the household income. Sustaining agricultural growth is critical to uplifting
the living standards of the residents apart from generating rapid economic growth.
The use of irrigation and trainings on modern farming and livestock keeping practices will be used as a
strategy to modernize agriculture. The training of farmers on emerging knowledge on modern livestock
processes is aimed at improving the quality of livestock. The use of irrigation on the other hand will improve
food security by mitigating challenges of unreliable rainfall which is utilized to feed agriculture in the
County. The use of fish cages will improve fish production which has been in the decline. To modernize
agriculture, the county will;
48
i. Set minimum farm holdings for mechanized agriculture to increase food security through increased
mechanized agriculture.
ii. Improve soil fertility through erection of gabions to arrest soil erosion and encouraging use of farm
yard manure and fertilizers thereby enhancing productivity.
iii. Train farmers on emerging knowledge on modern farming practices to mitigate against limited access
to extension services while enhancing knowledge on modern farming practices.
3.1.4 Diversifying Tourism
Kenya’s Vision 2030 identifies tourism as one of the six priority sector with high potential of spurring the
economic growth and development. Whereas the county’s tourism is not well developed, it is composed of;
a game reserve, forests, cultural heritage centres, wildlife, diverse fish species, hotels, beaches, islands,
various species of snakes and birds as well as bars and restaurants. There is also a diverse range of natural,
social, human and physical resources which include lakes, rivers, and cultural assets in form of built sites,
living heritage expressed in distinctive local customs, songs, dances, history, art and handicrafts.
The County hosts several cultural sites including; Olua Sacred Trees, Holy Got Adodi, Bullock of Got
Podhe, Rambugu hills, Got Ramogi, Jaramogi Oginga Odinga Mausoleum, Achieng’ Oneko Mausoleum,
Mageta Island, Odera Akang’o office and cells in Yala. It also hosts diverse varieties of wildlife such as
hippopotamus (Lake Victoria, River Yala), Crocodiles (Yala Swamp, parts of the Lake Victoria), Sitatunga
(Yala Swamp), monkeys, bush pig (mainly in Yala Swamp), Hyenas (Got Abiero, Utonga) and Leopards.
The fish species within the bounds of Siaya County is equally diverse and includes; Nile Perch,
Rastrineobolaargentea (locally known as Omena), Hatlochromines (locally known as Fulu or Wiu) and
Tilapia. To harness and diversify tourism potential, the county will;
1. To partner with Tour Operators for development of tourist attraction packages for various classed
including medium and economy tourist packages as well as educational, heritage and cultural tours.
2. Identify and map out potential areas for tourism development including the lake front beaches or
shorelines, cultural, archaeological and heritage sites.
3. Construction and equipping of cultural centres.
4. Tourism planning in social, economic and environmental dimensions
5. Developing sports tourism ie boat, racing, water skiing, swimming competition, boat tours amongst
others
6. To create an enabling environment for development of high-end hotel and Conference facilities in
Siaya County.
7. Development of Community-Based Tourism activities.
49
8. Marketing Initiatives to enhance visibility of the County.
9. Partner with relevant stakeholders for the development of Wildlife Conservancies to promote tourism
and solve wildlife-human conflict;
10. Establishment of standards for tourism products and services in the County; and
11. Development of road network within Siaya County for rural and urban areas targeting unique
heritage facilities and sceneries around and within the County.
3.1.5 Managing Human Settlement
The Kenya Vision 2030 anticipates that more than half of our nation’s population will be residing in urban
areas following the current population trends. The County hosts residents in its rural, urban and peri-urban
centres. While a significant part of the population still resides in the rural centres, there has been continuous
migration towards the urban centres in search for better work opportunities and quality services. The rural-
urban migration has resulted in pressure on the limited resources in the urban and peri –urban centres which
are trying to meet the growing demand. As a result, it is important that the respective areas enhance their
capacity for service delivery with relevant infrastructure and governance structures.
To address the challenges of the growing human settlement and strain on existing infrastructure, the county
proposes the following strategies;
1. De-densify existing housing in the urban areas to protect the land and assigning new housing spaces
on need basis.
2. Concentrate human settlements in the specified growth corridors and urban areas to protect
agricultural land.
3. Provide technical and social infrastructure as well as sufficient services in relation to the specific
urban functionalities and growth corridors.
4. Promote equitable distribution and offering subsidies for accelerated economic development in
underdeveloped areas
5. Provide unique living conditions for the urban growth centres and corridors
6. Ensure access to quality infrastructure and services to the inhabitants
7. Concentrate human settlements in the specified growth corridors and urban areas to protect
agricultural land.
The following are the six categories of growth centres and their functionalities:
1. County growth centres
50
These are areas which have the potential for urban and industrial growth. They have the capability to induce
growth in larger centres which offer specialized growth functions and can accommodate major redistribution
of the population i.e. Siaya, Bondo and Usenge.
2. Sub County Growth centres
These are areas which shall serve the administrative functions of sub-counties. They should have the
capacity to increase socio-economic activities and are designed with specialized facilities and higher level of
infrastructure i.e. Bondo, Siaya, Yala, Ugunja, Ukwala and Rarieda.
3. Urban centres
These areas are divided into two tiers:
i). The first tire will focus on decongesting the sub-county centres and developments in the surrounding
region i.e.
Town Functionality
Usenge Fishing, Transport, Ecotourism, Commercial
Ugunja Transport, Commercial
Yala Transport, Education, Governance, Industrial, Communications
Ukwala Commercial
Nyadorera Commercial, Transport
Luanda K’Otieno Commercial, Fishing
Ndori, Akala, Sega Commercial, Transport
ii). The second tire will serve as intermediary towns to promote rural development for balanced
distribution of growth and development. It comprises of the following areas; Boro, Kobare,
Nyangoma, Aboke, Sihayi, Ndori, Sigomere, Sidindi, Kodiaga, Nyangweso, Apuoyo, Kobare, Bar-
Kalare, Nango, Bar-. Chando, Wich Lum, Kapuoyo, Usigu, Uhanya, Asembo Bay, Mahaya,
Ragengni, Ndigwa, Misori.
4. Market centres
These are small areas with linkages with the intermediate rural hinterlands. They serve as higher order
villages with central locations and potential for development within the catchment area. The areas include;
Aram, Aboke, Ragengni, Wich Lum, Wagusu, Yenga, Misori, Usigu, Ngiya, Boro, Madiany.
5. Local centres
These areas comprise of main village settlement which are predominantly agricultural and have the lowest
threshold shopping centre.
6. Rural centres
51
These areas cater for the rural hinterland as agro service centres for collection and distribution of agricultural
goods and services. They will have processing, marketing, warehousing and storage facilities. The areas will
include; Sidundo, Bar Okwako, Lukhano, Nyaola, Rabango, Obet, Awelo, Ngiya, Sidindi, Rwambwa,
Nango, Nyalula, Manyuanda, Mahaya, Ratado, Ligega, Kobare, Amoyo, Liganwa, Ndigwa, Wagai, and
Sikalame. Map: Proposed Human Settlement Strategy
The County also proposes growth corridors which will guide the delivery of housing, employment, transport.
It proposes two categories of growth corridors, Regional corridors and County Growth Corridors.
1. Regional corridors
They are aimed at enhancing regional connection and economic development with a proposed buffer radius
of 1 kilometre. The corridors will include;
i). Usenge-Bondo-Kisumu corridor: Growth drivers in this corridor includes education facilities
(JOOUST, KMTC, Technical colleges, National Schools) fishing and ecotourism, direct connection
to Kisumu city and the administrative functions of Bondo and Usenge town.
ii). Nyadorera-Siaya-Kisumu Corridor: Regional connection-direct connection to Kisumu County, strong
governance (County Headquarters in Siaya town) and ecotourism activities.
iii). Busia-Ugunja-Yala-Kisumu corridor: Regional connection to Kisumu County, Busia County and
Uganda, governance and ecotourism.
2. County Growth corridors
52
The corridors seek to enhance connection within the County, Sub Counties, Wards and Villages to promote
economic growth and development in the areas. They will have a proposed buffer radius of 500 meters. The
corridors will include;
i). Luanda Kotieno-Bondo-Siaya corridor: The drivers of growth and development in this corridor
includes: Educational facilities - JOOUST, proposed Barack Obama University, KMTCs’, technical
colleges, national schools, fishing and ecotourism, strong governance, and a strong political history
(Jaramogi, Obama).
ii). Nyadorera-Ukwala-Ugunja Corridor: This corridor shall develop as a result of ecotourism activities
and influence of Busia-Ugunja- Kisumu corridor.
iii). Siaya-Kakamega-Luanda K’Otieno Corridor: Development and growth of this corridor shall be
influenced by ecotourism and fishing in Lake Victoria, influence from Usenge-Bondo- Kisumu
corridor, and influence of the proposed ring road along Lake Victoria.
iv). Bondo-Amoyo-Wichlum Corridor: Growth stimulus in this corridor shall be as a result of ecotourism
and fishing in Lake Victoria, influence from Usenge-Bondo-Kisumu corridor and tertiary education
institutions.
v). Kodiaga- Ngiya-Ndori-Asembo-Luanda Kotieno corridor: Growth in this corridor is stimulated by
ecotourism and fishing activities in Lake Victoria and influence from Usenge-Bondo- Kisumu
corridor. Map: Proposed Growth Corridor
53
3.1.6 Conserving the Natural Environment
Environment is a broad term representing the totality of the surrounding such as plants, animals,
microorganisms, socio economic and cultural factors. It includes the physical factors of the surroundings of
human beings such as land, water, atmosphere, sound, odour, taste; the biological factors of animals and
plants and the social factors of aesthetics including both natural and built environment.
The right to a clean and healthy environment is one of the rights safeguarded under the Constitution of
Kenya, 2010. To ensure its protection not only for the present generation, but also the future generations as
envisioned, it is critical that Siaya County puts in place measures to conserve the environment. The main
activities contributing to environmental degradation in the County include unsustainable land use practices,
poor soil and water management practices, unsustainable fishing, and deforestation, overgrazing, over
exploitation of wetland resources, encroachment of riparian reserves, pollution and effects of climate change.
To address the challenges, the county outlines a strategy to promote sustainable natural resource
management in Siaya County focusing on the following aspects;
54
5. Protection of water catchment and environmentally fragile ecosystems. The water resources in the
county comprise of rivers (Yala, Nzoia and other smaller ones and their tributaries, water pans,
boreholes, dams, wetlands (Yala swamp) and lakes (Lake Victoria and Lake Kanyaboli). Both
surface water and ground water resources are currently being exploited to address rising demands.
Resources should therefore be planned to ensure adequate water is available to meet the demand by
consumers while preserving aesthetics and environmental safety.
6. To safeguard the resources, the county proposes the protection of water intake/sources by providing a
protection belt (buffer) for underground water intake i.e.
Protection belt Direct (Radius) protection Indirect (Radius) protection
Borehole 10m 50m
Well 10m 50m
River 10-50m 50m
55
Environmentally friendly industrial development
Wildlife conservation
Cultural sporting artistic hub
Water and waste management systems
Tourism
The project will be implemented as a flagship project.
56
2. Air Transport- to promote international, national and regional growth. The county identifies the
existing air transport facilities and challenges affecting their efficiency. It also proposes setting up
additional ones. The air transport facilities are as follows:
i). Gombe Airstrip (Existing): located within Siaya Municipality to the North and occupies a land
area of 31.8 acres. (paving, fencing, equipping and staff recruitment)
ii). Sega Airstrip (Existing): located at about 2 kilometres to the South of Sega town and occupies a
land area of 48.3 Acres. (paving, fencing, equipping and staff recruitment)
iii). Migwena (Proposed Airstrip): This site is proposed 7.5 kilometres South of Bondo town and has
a land area of 80 Acres.
iv). Yala (Proposed Airstrip): This site is proposed in Yala town and should have a land area of
50Acres. Map: Proposed Airstrips in Siaya County
3. Water transport – Lake Victoria links Siaya to Migori, Homabay. Kisumu and Busia counties and
also neighbouring countries, Tanzania and Uganda. There is a huge potential for water transport that
the county will explore individually and through LREB. Towards this, the county will undertake the
following:
57
i). Identification and development of landing bays.
ii). Linkage to the mainland and islands.
iii). Public-private partnerships to provide for more ferries.
iv). Putting in place security patrols and rescue services.
v). Construction of Parking bays and installations of high mast/security lighting.
Map: Proposed Waterways in Lake Victoria
4. Non-motorized transport – as a mechanism for lowering carbon emissions, the county proposes a
shift from motorized means of transport to walking and cycling for short –medium distance trips. The
county also proposes the following strategies;
i). Provision of comfortable pedestrian walkways with; trees planted along the streets for shade;
appropriate street furniture (street naming, benches along walkways for rest, bollards at crossings
to prevent illegal movement or entrance , street lights for illumination and waste containers to
promote cleanliness)
ii). Permeable street layouts for walking comfort
iii). Putting in place mitigation measures for street disconnections to improve permeability
iv). Create continuous active street frontages for economic and business activities and to enhance
pedestrian movements
58
v). Provide safe walking routes to schools through putting up fencing along pedestrian walkways and
shelter.
vi). Provision of safe and comfortable cycling network i.e. cycling land, sufficient and secure bicycle
parking facilities at major destination points or transit point.
3.1.8 Providing Appropriate Infrastructure
Infrastructure is an enabler of development and is the core for efficient and effective service provision. To
stimulate growth within the County and improve service delivery, the county has proposed strategies and key
areas to invest in infrastructure.
Sewerage: Water and Sanitation is a key component in development, it is an enabler for agriculture and a
safeguard in improving general health of the populace. Sewerage service provision has been a challenge in
Siaya due to inadequate infrastructure. To mitigate this challenge, the county proposes a sewerage and
sanitation development strategy to improve access to sewerage as well as improve existing infrastructure. It
proposes that a decentralized sewerage treatment facility in urban centres and septic tanks/ponds or low cost
sanitation facilities for rural areas is most ideal due to the undulating topography of the County and the
scattered urban centres. This is as opposed to a central facility which would be uneconomical due to costs
relating to sewage pumping. To implement the sewerage and sanitation strategy, the county proposes the
following activities:
1. Operationalization of existing sewerage systems and treatment plants in Siaya and Bondo and
installation in other towns in the County (deployment of sewer network, pumping station and
treatment facilities)
2. Decentralizing the sewerage treatment facilities to be provided for each urban centre including
properly designed sewerage network and waste stabilization pond technology
3. small bore sewerage system and on-site sanitation schemes like septic tanks for rural centres
4. Each urban area shall have a garbage collection site located on the leeward side of the urban area and
have a 100m-protection belt.
5. Provide toilet facilities at convenient sites in all types of centres, schools, hospitals and parks.
6. Sensitize the public on the installation and use of pit latrines in the rural areas.
7. Re-use of sewage or treated sewage to help in conserving natural water resources and reduce raw
water demand which is already scarce.
The county has also identified opportunities for re-use of the treated sewage such as: irrigation of agricultural
crops or forests due to the fertilizer value of the treated sewage which includes nitrogen and traces of other
elements such as phosphorous and potassium. It can also be used fish farming, where the sewage ponds are
59
used for breeding fish. The treated sewage can also be used for ground water recharge to supplement
underground water and for industrial use.
Information, Communication and Technology (ICT)
The nature of engagements and service precision has greatly evolved. Businesses now have both online and
physical presence, while some are solely online due to the convenience they afford to the users. The shift is
evident in both the private and public sector. The Government for instance is using various ICT enabled
platforms to offer services such as tax administration (iTax), procurement (IFMIS), basic education
registration (NEMIS) among other services. Communication has also migrated largely to online interactions
through different platforms such as zoom, webinar, email and social media applications i.e. WhatsApp and
Facebook. Map: Proposed ICT network plan
Energy:
The county will harness hydro power generation at Ndanu Falls on River Yala and strengthen the use of solar
power during the plan period. In this regard, the county plans to:
1. Tap on green energy sources: harness solar energy through solar photovoltaic system for electricity
and solar thermal system for heat.
2. Promotion of renewable energy through identification of sites suitable for wind and solar energy
plants
3. Partner with developers of green energy
60
4. Explore the possibility of hydropower generation (R. Nzoia and Yala, Dominion Farm)
5. Improve connectivity to power through distributed energy system with cluster of small/medium
power generation.
6. Improve the service quality.
3.1.9 Industrialization
Industrialisation in the county is generally underdeveloped. The county features low value addition
undertaken by micro, small and medium sized firms, commonly referred to as the jua kali sector. Most of
the activities are in quarrying and mining and construction activities. There are opportunities to spur
industrialisation in the following areas:
1. Fish processing industries in Bondo and Rarieda sub counties at Wagusu, Usigu, Usenge, Luanda
Kotieno, Misori and Asembo Bay which are beach landing points that should be supported with fish
processing infrastructure/plants.
2. Agro based enterprises in honey, grain, groundnut and peanut butter processing and their value chain
addition in East Ugenya, West Ugenya, North Ugenya and Ukwala wards
3. Distilling industrial plants in other parts in Ugenya such as Ukwala or Sihayi
4. Intensify Sun flower oil production in Gem Sub County
5. Sugarcane industries at Yala Wetland in Alego Usonga Sub County and sugarcane production at Yala
in Gem Sub County and Uholo in East Ugenya.
6. Ginnery and textile at Ndere in Alego Usonga.
The County will focus on industrial diversification and upgrading based on modernization of agriculture,
value addition of products and introduction of new technology in industries; gradual integration into regional
production networks and the global value chain; development of high-skilled human resource and creation of
more employment opportunities with quality jobs in industries. Industrial production with value addition by
rural areas has also been proposed as a strategy to support industrialisation while also reducing rural poverty
and disparities in rural and urban areas. To implement the proposed strategy, the county has outlined the
following activities:
1. Establishment of fish industries (Bondo, Usenge, Wichlum, and Luanda K’Otieno),
2. Sugar processing industry (Uholo, Yala),
3. Mining industry (Gold- Wagusu),
4. Groundnut industry (Diego)
5. Fruit/ juice processing industries (Akala and Tingwangi),
6. Honey processing plant (Ukwala),
61
7. Meat processing industry (Usenge, Bondo, Siaya, and Ugunja),
8. Rice milling plant (Nyadorera),
9. Oil processing plant (Sunflower-Gem),
10. Cotton and textile industry (Siaya) and
11. A distillery in Ugunja
Proposed Industrial Development Strategy
The county will therefore, work towards an enabling environment through the following initiatives:
1. To address the challenges of inadequate industries it proposes the demarcation of more land for
industrial use in all core urban centres as well as development of processing industries for livestock
products and by products.
2. To propose minimum farm holdings for mechanized agriculture to enhance mechanized agriculture.
3. To provide incentives to farmers to revamp collapsed cotton and sugarcane industries.
4. To facilitate processing of Environmental Impact Assessments in all mining sites to promote
sustainable sand mining.
5. Training of stakeholders including members of the community to enhance awareness on mining
technologies with a view to promoting sustainable mining methods i.e. for areas that mine Gold (
Wagusu and Kogelo), Fluorite (Rata) and Granite and Black sand ( Yala valley).
6. Improve road network to mining sites to enhance access.
7. To prepare urban plans for citing of industrial parks within the County to increase investments.
62
3.1.10 Thematic Spatial Development Frameworks
Thematic County Spatial Plan proposals and strategies identified will be guided by three broad spatial
development frameworks to guide:
1. Green Spatial Development
2. Brown Spatial Development and
3. Blue Spatial Development
3.1.10.1 Green Spatial Development (Zone I)
The Green Spatial Development (Zone I) is developed in recognition of the significant role natural capital
has in enhancing socio-economic development. The Zone will highlight environmentally significant areas
and habitat conservation areas as envisioned under the Environmental Management and Coordination Act,
1999 and the Agriculture Act, 2003.
The Zone will focus on:
1. Ensuring that ecological goods and services and natural capital is available and guaranteed for the
present and future generations through the allocation of space for conservation, preservation and
protection of all environmentally significant areas in the County.
2. Ensuring that areas for productive engagement in agriculture for food production and raw material
through allocation of space at all times to realize food security and value addition in manufacturing.
Zone I is categorized into two sub-zones;
1. Zone 1 A (Ecological integrity zone)
The areas within the ecological integrity zone include forests, hilltops and migratory corridors. The county
proposes the establishment of buffer zones in the areas within the zone to reduce encroachment to important
biological diversity areas. It also proposes reduced human activities by restricting human settlement in the
area especially to areas that are prone to sever environmental degradation or loss of biological habitat.
The county proposes the following strategies to secure the ecological integrity zone:
i). Collaborative gazettement of areas within the zone by the National and County Government.
ii). Creation of buffers zones through demarcation.
iii). Enhancement of preservation, protection and conservation efforts
iv). Promotion of ecotourism to enhance revenue collection
v). Development of relevant policies, strategies, standards, guidelines and legislation to govern and
manage the areas within the zone to enhance environmental quality.
2. Zone 1 B (Agricultural integrity zone)
63
This sub-zone will focus on areas designated for agricultural production within the Green Spatial Zone.
Human settlement shall be permitted within the sub-zone provided they conform to the green agenda. The
Siaya County proposes green cover of 10% for built homes and 70% for undeveloped areas which should
mirror the natural habitat. The county proposes the following strategies to secure the agricultural integrity
zone:
1. Pursue collaboration between the National and County Governments to develop policies, strategies,
guidelines, standards and legislation to govern and manage areas within the zone.
2. Training on use of appropriate, affordable and reliable crop and livestock husbandry methods and
technology to promote local economic growth and enhance profitable agriculture.
3. Expansion of land under agriculture, through small-holder farmer participation and increased farmer
extension services.
4. Market agriculture as a viable investment pathway for the local populace that is capable for creating
employment and increasing income.
5. Expansion of land under agriculture through irrigation programmes to cushion farmers from impact
of unreliable rainfall (drought).
6. Increase agricultural productivity through improved technology uptake, and mechanization.
7. Enhance value addition in agricultural products through use of creativity, innovation, technology and
market efforts to provide an avenue for industrialization.
Map: Siaya County Green Spatial Development Zone
64
3.1.10.2 Brown Spatial Development (Zone II)
The Brown Spatial Development provides a linkage between human settlement and infrastructural
development with a view to promoting socio-economic transformation. It will also have some elements of
green spaces for integrated and balanced development for enhanced environmental quality. It will comprise
of human settlement development areas designated as; growth centres (7 km radius), sub-county growth
centres (5 km radius), urban centres (3 km radius), rural and local centres and transport growth corridors.
The zone will focus on:
1. Enhancing harmonious and sustainable urban development for liveable towns and rural settlements.
2. Promoting sustainable human settlements with the growth corridor and special economic zones
transform the county local economy.
Zone II has been categorized into four sub zones
1. Zone II A - Urban Développent Zone
This sub-zone proposes the following strategies;
i). Collaboration between the National and County Governments to develop policies, strategies,
guidelines, standards and legislation to govern and manage urban development and affordable,
sustainable housing within the liveable urban area in the County.
ii). Promotion of commercial development areas for sustained local economic development as well as
appropriate markets to promote small and medium enterprises (SME).
iii). Promotion of industrialization through creativity, innovation and technology thereby shifting the
labour market from agriculture to industrial development
iv). Develop affordable housing to enhance social inclusivity, equity and liveable environment for the
urban population in the area.
v). Provision of education and health services to improve social development in the area.
vi). Planning for public –purpose land uses to promote governance, security as well as the cultural and
spiritual well-being of the population and devolved service delivery to the local population.
vii). Development of public utilities (electricity, energy, water sanitation, sewer line, telephone,
Information Communication and Technology (ICT) hubs, dumping sites, cemeteries) county-wide
to enhance liability of the urban settlements.
viii). Enforcement of development control to ensure orderly development in the area
65
2. Zone II B – Transport Growth Corridors
The Transport Growth Corridors (Zone II B) provides a framework for linkage between growth corridors and
the transport network. The county proposes the following growth corridors:
i). Regional Development Corridor of 1 Kilometre radius and
ii). County Development of 0.5 Kilometre radius.
The county also proposes the enforcement of development control to ensure orderly development in the area.
3. Zone II C – Rural Sottement Zone
This sub-zone provides a transition between the green zone and the brown zone. It proposes a nuclear
settlement in a rural and local centre of a radius of 0.5 Kilometres equipped with well serviced socio-
economic facilities.
The county proposes the following strategies for implementation within the area;
i). Resettlement programmes to deepen nucleation while releasing land for agricultural productivity.
ii). Provision of education and health services to improve social development in the area.
iii). Planning for public –purpose land uses to promote governance, security as well as the cultural and
spiritual well-being of the population and devolved service delivery to the local population.
4. Zone II D- Spécial Economic Zone
The Special Economic Zone is proposed to accelerate socio-economic transformation in industrialization, the
commercial hubs, ICT hubs and smart city. The following strategies are proposed for implementation in the
area:
i). Use of public-private partnership framework to develop a special economic zone through effective
infrastructure development to facilitate these areas as impetus for growth while embracing the
backward and forward linkages concepts.
ii). Promotion of industrialization through creativity, innovation and technology thereby shifting the
labour market from agriculture to industrial development.
iii). Development of public utilities i.e. Information Communication and Technology (ICT) hubs,
commercial hubs and a smart city county-wide to enhance liability of the urban settlements.
Map: Siaya County Brown Spatial Development Zone
66
3.1.10.3 Blue Spatial Development (Zone III)
The Blue Spatial Development Zone seeks to tap into the blue economy, an emerging area with significant
potential. It seeks to tap into opportunities for economic development in the water environment. The county
will focus on fishing, tourism, the marine economy (ship building and boat making), water transport
(shipping, harbours) and exploration energy (wind and solar power).
Zone III seeks to:
1. Explore, establish and promote tourism development in the area in order to shift labour engagement
to new areas of economic transformation.
2. Initiate and formulate policies, strategies, guidelines and standards that promote blue economy
development.
3. Enhance and strengthen the development of fisheries both capture and culture fisheries to promote
food security and enhance value addition in manufacturing.
It is categorized into three sub-zones;
1. Zone III A-Tourism Promotion Zone
It focuses on the lakefront which is comprised of Lake Victoria, Lake Kanyaboli, Lake Nyamboyo and Lake
Sare. It also utilizes the wetland i.e. the Yala Swamp Ecosystem. The county proposes use of the lakefront
area for development of marinas, lodges, resorts, restaurants and hotels, water sports and leisure sports to
develop and promote tourism in the area. The county proposes the following strategies for implementation
in the area:
67
i). Collaboration between the National and County Governments to develop policies, strategies,
guidelines, standards and legislation for sustainable tourism development.
ii). Designation of the Lake Front as an exclusive tourism development zone.
iii). Mobilization of land resources in the Lakefront, through acquisition, purchases, compensation, and
land banking for utilization in tourism promotion.
iv). Mobilization of funds for capital investment to develop the area as a Lakefront (infrastructure,
building lodges, resorts). The Capital Investments shall be through Public-Private Partnership,
National and County Government, Foreign Direct Investment and local investors.
v). Linkage of County Tourism initiatives with the regional circuit (Western Kenya) and the national
circuit to promote visibility and benefit from synchronized branding and marketing.
The county also proposes development of tourism industry 5 km inland (marinas, resorts etc.)
2. Zone III B- Fisheries Development Zone
This sub-zone focuses on the fishing industry as a major economic activity in the County due to the existence
of the Lake Front and the existing fish landing beaches. The county proposes the following strategies to
promote development of the zone:
i). Collaboration between the National and County Governments to develop policies, strategies,
guidelines, standards and legislation to promote fishery development.
ii). Gazettement and designation of fish landing sites to encourage local ownership and participation.
iii). Development of fish landing beaches along the lakes to promote clean, safe and healthy capture of
fish resources.
iv). Planning and budgeting for development of associated infrastructure i.e. roads, telephone, electricity,
water and sanitation in the fish landing beaches.
v). Preparation of the spatial development for the relevant fish landing beaches and markets where
applicable.
vi). Establish programmes to develop and improve fish culture development county-wide.
3. Zone III C-Marine Industry and Commerce Zone
The Marine Industry and Commerce zone provides a framework for development of the port in areas such as
Asembo Bay and Port South Bay. It also envisions implementation of other activities including; ship and
boat building, water and leisure sports, boat racing, water transport, ferry services, hauling traded goods and
services, logistical support (clearing and forwarding, warehousing, safety and security operations). The
county proposes the following strategies for implementation in the area;
68
i). Collaboration between the National and County Governments to develop policies, strategies,
guidelines, standards and legislation to promote development of marine industry and commerce.
ii). Designation and gazettement of a suitable location for marine industry and commercial development
iii). Development of special area plans (spatial) for development of the selected marine environment i.e.
landing beaches and islands (Mageta, Oyamo, Ndeda).
iv). Development of appropriate infrastructure and social amenities in the area.
Map: Siaya County Blue Spatial Development Zone
69
70
Chapter Four
Development Priorities, Strategies and Programmes
4.0 Introduction
The chapter discusses county’s sectoral development priorities, strategies, programmes and flagship projects
to be implemented in the next five years and cross-sectoral linkages.
Cross cutting issues such as climate change; environmental degradation; HIV/AIDS; Gender, Youth and
Persons Living with Disability (PLWD) and Disaster Risk Reduction (DRR) have been mainstreamed into
proposed programmes and projects.
The sector envisions quality service delivery through provision of efficient, effective, ethical, equitable
services and transformative leadership. The sector’s goal is to provide good governance in service delivery.
71
Attorney/Legal Affairs office. It will be responsible for the provision of overall strategic leadership and
responsive development planning with the aim of securing effective, efficient and timely delivery of quality
services to citizens. Emphasis will be directed in developing policies and legislative frameworks to improve
intergovernmental relations and provide a platform for integrated planning and effective coordination of
development programmes in the county. The county will put emphasis on strengthening public participation
in governance, and increasing accountability in management of public resources. Strengthening of
Monitoring and Evaluation systems will be prioritized for better policy, programme and projects outcomes.
ICT operational mandate include: development of Local ICT Infrastructure; promotion of ICT Skills and
Digital Entrepreneurship; investment in e-Governance and cybersecurity
County Assembly
The sub sector comprises the county assembly service board, office of the speaker and the clerk and is
mandated to provide legislative, oversight and representation services. It envisions an effective and efficient
legislature committed to an accountable government through quality legislation, oversight and
representation.
73
Goals Sector Priorities Strategies
Strengthen Strengthen linkage among fiscal policy documents
planning, research Strengthening information and documentation services
and development Recruit and employ additional technical staff
Develop policy to guide research and development
74
4.2.1 Sector Programmes
To ensure good governance in service delivery, the sector will invest in the following key interventions areas: Strengthen Monitoring and
Evaluation; Human Resource Management; Devolved Governance; Improve E-Governance; Strengthen Citizen Engagement; Financial
Management; Enhance Revenue Collection; Improve Policy Formulation and County Legislation. Specifically, the sector shall invest in
construction of Speaker’s residence, Assembly Complex, Completion of ward offices, CPSB Office Complex, Construction of ward
administration offices; Establish Special Programme, Improve E-Governance, Operationalize Village Administration Units and Automate
revenue collection.
Programme/ Key Outputs Key Performance Linkage Planned Targets and indicative budgets (Ksh in million )
Sub-Programme Indicator ( KPI) to SDG 2023-2024 2024-2025 2025-2026 2026-2027 2027-2028
Targets Target Cost Target Cost Target Cost Target Cost Target Cost TOTAL
75
Programme/ Key Outputs Key Performance Linkage Planned Targets and indicative budgets (Ksh in million )
Sub-Programme Indicator ( KPI) to SDG 2023-2024 2024-2025 2025-2026 2026-2027 2027-2028
Targets Target Cost Target Cost Target Cost Target Cost Target Cost TOTAL
prepared
No. of policies 7.1 9.6 12.5 14.2 16.5 59.9
developed
No. of Bills developed 7.1 9.6 12.5 14.2 16.5 59.9
No. of plans prepared 7.1 9.6 12.5 14.2 16.5 59.9
(procurement, work
plans and budgets)
Assembly’s ICT Assembly’s ICT No of ward offices 30 21.3 0 0.0 0 0.0 0 0.0 0 0.0 21.3
connected to the
electricity grid
Linked No of ward offices 30 17.7 0 0.0 0 0.0 0 0.0 0 0.0 17.7
communication linked to WAN
technologies between
HQ and ward offices
Developed advance % of the back-up system 100 7.1 0 0.0 0 0.0 0 0.0 0 0.0 7.1
back-up system developed
Develop the physical % of the back-up system 100 21.3 0 0.0 0 0.0 0 0.0 0 0.0 21.3
infrastructure for the developed
e-library
sub total 1,173.0 1,501.5 1,883.7 2,129.2 2,473.8 9,161.2
Programme: County Economic Planning Services
Objective: To build capacity in policy formulation and execution
Outcome: Enhanced Planning and research
Economic Enhanced Policy, No of plans approved: 11 21.3 4 26.3 5 34.2 4 38.5 5 45.0 165.2
Planning services Program Coordination CIDP (23-27), ADP,
and formulation DMSP, SPs, SWGs
Operational No of publications 10 1.4 10 1.8 10 2.1 10 3.2 10 3.4 11.8
information and automated
documentation centres No of publications 10 1.4 10 1.8 10 2.1 10 3.2 10 3.4 11.8
sourced and classified
County Statistical Improved county data 0.0 0.0 0.0 0.0 0.0 0.0
services management processes 0.0 0.0 0.0 0.0 0.0 0.0
Copy of updated 1 0.0 1 0.0 1 0.0 1 0.0 1 0.0 0.0
Factsheet
No of surveys done: 4 0.0 4 0.0 4 0.0 4 0.0 4 0.0 0.0
Ø Impact Survey 0.0 0.0 0.0 0.0 0.0 0.0
Ø Household survey 0.0 0.0 0.0 0.0 0.0 0.0
Ø Prefeasibility studies 0.0 0.0 0.0 0.0 0.0 0.0
Ø Data gap analysis 0.0 0.0 0.0 0.0 0.0 0.0
Approved statistical SDG 8.5 1 7.8 1 11.4 1 14.5 1 16.0 1 19.1 68.8
abstract , 1b
Budget Statutory documents Budget circular issued SDG 8.5 1 61.0 1 83.2 1 107.6 1 121.9 1 141.7 515.4
Formulation, prepared , 1b
coordination and No of Budget policy SDG 8.5 2 0.0 2 0.0 2 0.0 2 0.0 2 0.0 0.0
Management papers Approved , 1b
(CBROP, CFSP)
Approved annual budget SDG 8.5 1 0.0 1 0.0 1 0.0 1 0.0 1 0.0 0.0
Estimates , 1b
77
Programme/ Key Outputs Key Performance Linkage Planned Targets and indicative budgets (Ksh in million )
Sub-Programme Indicator ( KPI) to SDG 2023-2024 2024-2025 2025-2026 2026-2027 2027-2028
Targets Target Cost Target Cost Target Cost Target Cost Target Cost TOTAL
Administrative reports No. of budget execution SDG 8.5 5 0.0 5 0.0 5 0.0 5 0.0 5 0.0 0.0
prepared reports prepared , 1b
sub total 92.9 124.3 160.4 182.9 212.5 773.1
Programme: Financial services
Objective: To raise fiscal resources efficiently and manage county government assets and liabilities effectively.
Outcome: A transparent and accountable system for the management of public financial resources
Accounting Administrative and No of administrative SDG 8.5 12 17.0 12 22.8 12 30.0 12 33.2 12 39.4 142.3
Services Statutory reports reports prepared , 1b
prepared No. Pending bills SDG 8.5 4 0.0 4 0.0 4 0.0 4 0.0 4 0.0 0.0
Reports prepared , 1b
No of statutory reports SDG 8.5 5 0.0 5 0.0 5 0.0 5 0.0 5 0.0 0.0
(quartely & annual FR) , 1b
submitted
Resource Improved Own Source Approved map of SDG 8.5 1 22.7 1 30.6 1 40.4 1 46.0 1 52.9 192.5
Mobilization Revenue collection revenue streams , 1b
No. of monthly SDG 8.5 12 0.0 12 0.0 12 0.0 12 0.0 12 0.0 0.0
inspections visits reports , 1b
prepared
No of new revenue SDG 8.5 3 0.0 3 0.0 3 0.0 3 0.0 3 0.0 0.0
streams identified , 1b
Operational revenue SDG 8.5 1 0.0 1 0.0 1 0.0 1 0.0 1 0.0 0.0
board/PPP arrangement , 1b
No of revenue streams SDG 8.5 20 0.0 3 0.0 3 0.0 20 0.0 20 0.0 0.0
automated (digitized) , 1b
No of intra and inter SDG 8.5 12 0.0 12 0.0 12 0.0 12 0.0 12 0.0 0.0
departmental revenue , 1b
coordination meetings
held
Procurement Improved supply No of Consolidated SDG 8.5 1 10.6 1 14.9 1 18.6 1 21.4 1 24.7 90.3
services chain management procurement plans , 1b
systems prepared
No of statutory and SDG 8.5 5 0.0 5 0.0 5 0.0 5 0.0 5 0.0 0.0
administrative reports , 1b
prepared
No. of Prequalified SDG 8.5 2 0.0 2 0.0 2 0.0 2 0.0 2 0.0 0.0
Suppliers Register , 1b
Updates prepared
County Hospitals SDG 8.5 0 0.0 1 0.0 0 0.0 0 0.0 0 0.0 0.0
Procurement Policy , 1b
prepared
% of procurement plan SDG 8.5 100 0.0 100 0.0 100 0.0 100 0.0 100 0.0 0.0
implemented , 1b
Internal Audit Financial practices no of planned audit SDG 8.5 8 11.3 8 21.9 8 22.8 8 25.7 8 25.9 107.5
services and systems reports prepared , 1b
management no of special audit SDG 8.5 8 0.0 8 0.0 8 0.0 8 0.0 8 0.0 0.0
established reports prepared , 1b
No o spot check audit SDG 8.5 4 0.0 4 0.0 4 0.0 4 0.0 4 0.0 0.0
Reports prepared , 1b
No of audit committee SDG 8.5 5 0.0 5 0.0 5 0.0 5 0.0 5 0.0 0.0
78
Programme/ Key Outputs Key Performance Linkage Planned Targets and indicative budgets (Ksh in million )
Sub-Programme Indicator ( KPI) to SDG 2023-2024 2024-2025 2025-2026 2026-2027 2027-2028
Targets Target Cost Target Cost Target Cost Target Cost Target Cost TOTAL
reports prepared , 1b
No. Audit software SDG 8.5 0.0 1 0.0 0.0 0.0 0.0 0.0
(Team mate( procured , 1b
sub total 61.7 90.2 111.8 126.2 142.8 532.7
Programme 2: Office of the Governor
Objective: To provide strategic leadership and overall coordination of county affairs
Outcome: Improved county administration and governance system
County Functional County % of CEC resolutions 100 1.4 100 1.8 100 2.1 100 2.1 100 2.2 9.6
Executive Executive Committee implemented
Committee No. of CECMs signing SDG 16 11 1.1 11 1.3 11 1.7 11 1.8 11 2.0 7.9
Performance contracts
Office of the Inter-governmental % of Council of SDG 11 100 3.5 100 4.4 100 5.2 100 5.3 100 5.6 24.1
Governor & services Governors (COG)
Deputy Governor meeting resolutions
implemented
No. of MoUs and SDG 11 6 2.1 6 2.7 6 3.3 6 3.5 6 3.8 15.5
Agreements signed
No. of Reports on Chief SDG 8 24 1.1 24 1.3 24 1.6 24 1.6 24 1.7 7.2
Officer’s Progress
Review Meetings held
Advisories and policy No. of policy briefs SDG 8 36 7.7 36 9.5 36 11.2 36 11.5 36 12.1 52.0
briefs prepared prepared to the Governor
No of advisories SDG 8 36 3.8 36 4.7 36 5.6 36 5.8 36 6.1 26.0
prepared and submitted
No. of Reports on SDG 8 4 0.9 4 1.1 4 1.2 4 1.3 4 1.3 5.8
implementation of
Office of Governor’s
Work plan
Governor’s office 0.0 0.0 0.0 0.0 0.0 0.0
workplan developed No. of consultative SDG 8 4 3.4 4 4.2 4 5.0 4 5.1 4 5.4 23.1
meetings between
Executive and Assembly
held
No. of consultative 4 3.4 4 4.2 4 5.0 4 5.1 4 5.4 23.1
meetings between
Executive, National
Government officials
and Members of
parliament
Functional Governor's No. of Governor’s press 48 0.4 48 0.4 48 0.5 48 0.5 48 0.6 2.4
press unit releases
Functional Strategic No. of Resource 0 0.0 1 1.8 0 0.0 0 0.0 0 0.0 1.8
Service Delivery & mobilization strategy
Resource mobilization developed
Unit
No. of PPP agreements 2 0.7 3 1.3 2 1.0 2 1.1 2 1.1 5.3
signed
79
Programme/ Key Outputs Key Performance Linkage Planned Targets and indicative budgets (Ksh in million )
Sub-Programme Indicator ( KPI) to SDG 2023-2024 2024-2025 2025-2026 2026-2027 2027-2028
Targets Target Cost Target Cost Target Cost Target Cost Target Cost TOTAL
Citizen service charter Citizen Service Charters 1 0.3 0 0.0 0 0.0 0 0.0 0 0.0 0.3
revised
Established strategic No. of 2 0.1 2 0.2 2 0.2 2 0.2 2 0.2 1.0
partnerships with agreements/MOUs
CSOs and other signed
partners No of County CSOs/ 1 0.7 1 0.9 1 1.0 1 1.1 1 1.1 4.8
partners fora held
Established citizen No. of citizen 0 0.0 10 35.0 10 41.4 10 42.8 0 0.0 119.2
participation/ service participation/service
centres at ward level centers
Public Functional public No. of public 10 14.2 10 17.5 10 20.7 10 21.4 10 22.5 96.3
Participation & participation & civic participation for a held
Civic Education education unit
80
Programme/ Key Outputs Key Performance Linkage Planned Targets and indicative budgets (Ksh in million )
Sub-Programme Indicator ( KPI) to SDG 2023-2024 2024-2025 2025-2026 2026-2027 2027-2028
Targets Target Cost Target Cost Target Cost Target Cost Target Cost TOTAL
Public Citizen participation Citizen participation 1 0.4 0 0.0 0 0.0 0 0.0 0 0.0 0.4
Participation and charter developed charter
Civic Education Citizen satisfaction No. of survey reports 1 0.7 1 0.9 1 1.0 1 1.1 1 1.1 4.8
survey done
Established feedback No. of feedback reports 4 0.3 4 0.4 4 0.4 4 0.4 4 0.4 1.9
mechanism on input
from the public
Approved County PP No. of PP guidelines 1 0.4 0 0.0 0 0.0 0 0.0 0 0.0 0.4
guidelines approved
Signed strategic No. of 2 0.4 2 0.4 2 0.5 2 0.5 2 0.6 2.4
partnerships/MOU agreements/MOUs
with CSOs and other signed
partners No of County CSOs/ 1 1.4 1 1.8 1 2.1 1 2.1 1 2.2 9.6
partners fora held
Stakeholders mapping No. of stakeholder’s 48 0.7 0 0.0 0 0.0 48 1.1 0 0.0 1.8
undertaken registers established at
all levels
Established citizen No. of citizen 0 0.0 10 43.8 10 51.7 10 53.5 0 0.0 149.0
participation/ service participation/service
centres at ward level centres
Functional public No. of public 37 2.1 98 4.4 0 0.0 0 0.0 0 0.0 6.5
participation participation committees
structures/ formed
committees. No. of citizen fora 30 42.6 30 52.5 30 62.1 30 64.2 30 67.5 288.8
reports submitted
Functional Civic Civic Education 1 4.3 1 3.5 0 0.0 0 0.0 0 0.0 7.8
education framework curriculum and training
manual/module
No. of Civic education 2,000 1.4 2,000 1.8 2,000 2.1 1,000 2.1 2,000 2.2 9.6
Curriculum & training
manuals printed
No. of civic education 30 4.3 30 5.3 30 6.2 30 6.4 30 0.0 22.1
sessions/trainings
conducted
No. of IEC materials 5,000 1.1 5,000 1.3 5,000 1.6 5,000 1.6 500 1.7 7.2
printed to support CE
Functional GRM No. of Public 5 0.4 5 0.4 5 0.5 5 0.5 5 0.6 2.4
framework Complaints reports
submitted
Civic Education Civic education Civic Education 1 4.3 1 3.5 0 0.0 0 0.0 0 0.0 7.8
(CE) curriculum curriculum and training
domesticated & manual/module
training No. of civic education 4 7.1 4 8.8 4 10.3 4 10.7 4 11.2 48.1
manual/module for a held
developed
CE curriculum & Attendance list 0 0.0 1 0.5 0 0.0 0 0.0 0 0.0 0.5
manual officially
launched
81
Programme/ Key Outputs Key Performance Linkage Planned Targets and indicative budgets (Ksh in million )
Sub-Programme Indicator ( KPI) to SDG 2023-2024 2024-2025 2025-2026 2026-2027 2027-2028
Targets Target Cost Target Cost Target Cost Target Cost Target Cost TOTAL
Printed CE curriculum No. of Civic education 1,000 0.4 1,000 0.4 1,000 0.5 1,000 0.5 1,000 0.6 2.4
and training manuals Curriculum printed
No. of CE training 1,000 0.4 1,000 0.4 1,000 0.5 1,000 0.5 1,000 0.6 2.4
manuals printed
County leadership Induction report 0 0.0 1 0.2 0 0.0 0 0.0 0 0.0 0.2
inducted on CE
curriculum
Established CE units No. of CE units 1 0.0 7 0.0 15 0.0 15 0.0 0 0.0 0.0
No. of equipment 7 1.1 4 0.7 0 0.0 0 0.0 0 0.0 1.7
purchased
Focal point persons 37 0.0 0 0.0 0 0.0 0 0.0 0 0.0 0.0
appointed
Trained county No of TOTs trained on 0 0.0 300 2.4 150 1.4 150 1.5 0 0.0 5.3
officers & members of CE
the public on CE No. of civic education 30 3.2 30 3.9 30 4.7 30 4.8 30 5.1 21.7
sessions/trainings
conducted
Printed IEC materials No. of IEC materials 5,000 0.7 5,000 0.9 5,000 1.0 5,000 1.1 500 1.1 4.8
printed to support CE
Grievance Established GRM in GRM Policy & 1 0.6 1 0.8 0 0.0 0 0.0 0 0.0 1.4
Redress the county legislation/Act
Mechanism No. of GRM committees 19 0.0 30 0.0 0 0.0 0 0.0 0 0.0 0.0
(GRM) established
No. of Public 5 0.4 5 0.5 5 0.6 5 0.6 5 0.6 2.7
Complaints reports
submitted to CAJ
Access to Sensitized county No. of awareness 3 0.3 7 0.4 7 0.4 7 0.4 7 0.4 1.9
information leadership, staff and creation/sensitization
(ATI) members of the public reports
on ATI/ATI & CSC
Approved ATI policy No. of policy & 2 1.3 0 0.0 0 0.0 0 0.0 0 0.0 1.3
and legislation legislation
Sub Total 98.4 14,576 195.7 14,296 213.0 13,344 221.2 5,111 121.9 850.2
Programme: County Public Service Board
Objective: To reposition the Human Resource Management for efficient and effective service delivery
Outcome: High quality, accessible ,timely, consistent and comparable service Delivery
Human Resource Strengthened Human No of reports on Human 1 0.4 1 0.4 1 0.5 1 0.5 1 0.6 2.4
management Resource management Resource Audit reports
prepared and submitted
No. of departmental 5 0.7 6 0.9 8 1.0 8 1.1 10 1.1 4.8
organogram and staff
establishments approved
No. of staff promotion 1,000 0.4 1,000 0.4 2,000 1.0 2,000 1.1 2,000 1.1 4.0
reports prepared and
submitted
No. of training reports 4 4.3 6 5.3 8 6.2 10 6.4 10 6.7 28.9
on values and principles
Number of Staffs 1,500 0.4 1,800 0.4 2,100 0.5 2,400 0.5 2,700 0.6 2.4
signing Performance
82
Programme/ Key Outputs Key Performance Linkage Planned Targets and indicative budgets (Ksh in million )
Sub-Programme Indicator ( KPI) to SDG 2023-2024 2024-2025 2025-2026 2026-2027 2027-2028
Targets Target Cost Target Cost Target Cost Target Cost Target Cost TOTAL
Contracts.
No.of signed recognition 2 2.1 1 1.3 1 1.6 0 1.6 0 1.7 8.3
agreements with
respective trade unions
for purposes of CBA
No.of staff trained on 100 2.1 100 2.6 100 3.1 100 3.2 100 3.4 14.4
Industrial relations
No.of staff welfare and 1 2.1 1 2.6 1 3.1 1 3.2 1 3.4 14.4
wellness programme
undertaken
No. of Statutory Reports 1 0.7 1 0.9 1 1.0 1 1.1 1 1.1 4.8
prepared.
General Enhanced operational No of vehicles procured 1 4.3 1 5.3 1 6.2 0 0.0 0 0.0 15.7
administration capacity No. of assorted 20 1.4 30 2.2 20 2.1 20 2.1 20 2.2 10.1
equipment procured
Authentication of 0 0.0 1 4.4 0 0.0 0 0.0 0 0.0 4.4
Documents and
Shortlisting system
procured
Service delivery charter 1 0.7 0 0.0 0 0.0 0 0.0 0 0.0 0.7
developed and
implemented
No. of training needs 1 0.7 1 0.9 1 1.0 1 1.1 1 1.1 4.8
assessment report
prepared and
implemented
No. of board Staff in 12 3.5 2 0.9 3 1.6 5 5.3 5 5.6 16.9
post
No. of plans prepared 1 0.4 1 0.4 1 0.5 1 0.5 1 0.6 2.4
and approved
County Public Service 1 70.9 0.0 0.0 0.0 0.0 70.9
Board office constructed
and equipped
Improved performance County Job analysis 1 3.5 0.0 0.0 0.0 0.0 3.5
management report implemented
No of staff welfare 1 0.7 0.0 0.0 0.0 0.0 0.7
policies developed and
implemented
No. of Performance 12 0.7 12 0.9 12 1.0 12 1.1 12 1.1 4.8
managment reports
prepared and submitted
functional human Intergrated human 1 14.2 0.0 0.0 0.0 0.0 14.2
resource management resource management
system system
Sub Total 114.2 29.8 30.5 28.9 30.4 233.7
Programme 5: Coordination of Devolved Units
Objective: To champion devolution at grass root level
Outcome: Improved service delivery
Devolved Functional devolved No of ward Offices SDG 8 6 17.0 6 21.0 8 33.1 8 34.2 8 36.0 141.4
83
Programme/ Key Outputs Key Performance Linkage Planned Targets and indicative budgets (Ksh in million )
Sub-Programme Indicator ( KPI) to SDG 2023-2024 2024-2025 2025-2026 2026-2027 2027-2028
Targets Target Cost Target Cost Target Cost Target Cost Target Cost TOTAL
84
Programme/ Key Outputs Key Performance Linkage Planned Targets and indicative budgets (Ksh in million )
Sub-Programme Indicator ( KPI) to SDG 2023-2024 2024-2025 2025-2026 2026-2027 2027-2028
Targets Target Cost Target Cost Target Cost Target Cost Target Cost TOTAL
No. of Contracts and 16.00 10 0.1 10 0.1 10 0.1 10 0.1 10 0.1 0.5
Agreement reviewed and
drafted
No. of court sessions 16.00 25 0.7 25 0.9 25 1.0 25 1.1 25 1.1 4.8
attended
No. of matters settled 16.00 10 3.5 10 4.4 10 5.2 10 5.3 10 5.6 24.1
out of court
No. of legal libraries 4.00 0.0 0.0 0.0 1 5.3 0.0 5.3
established
No. of staff legal clinics 4 1.4 4 1.8 4 2.1 4 2.1 4 2.2 9.6
conducted
No. of county courts 1 8.5 1 10.5 1 12.4 1 12.8 1 13.5 57.8
established
Sub Total 15.3 18.9 22.5 28.6 24.4 109.6
Programme 9: Information, Communication and Technology
Objective: To provide quality ICT services and solutions that supports County operations
Outcome: Improved E-Government Services in the County
ICT Electronic Records & Number of county SDG 9 1 7.1 1 17.5 1 5.2 1 5.3 1 5.6 40.7
Document records and documents
management digitized
Business Continuity Time taken to recover SDG 9 1 0.7 1 1.8 1 2.1 1 2.1 1 2.2 8.9
Centre from a system downtime
County CCTV No. of CCTV sites and SDG 9 1 0.4 6 2.6 30 10.3 2 1.1 2 1.1 15.5
surveillance Cameras installed
Unified No. of offices with SDG 9 1 1.4 1 0.9 1 1.0 1 1.1 1 1.1 5.5
intercom
Digital Skills Training Number of individuals SDG 4 2 0.4 4 1.8 4 2.1 4 2.1 4 2.2 8.6
trained &8
Establishment of ICT Number of start-ups SDG 8 0 0.0 1 8.8 1 10.3 1 10.7 1 11.2 41.0
incubation center incubated
Establish of Number of public Wi-Fi SDG 9 6 3.5 10 8.8 10 10.3 5 5.3 5 5.6 33.6
community public Wi- installed
Fi
Establishment of E- Number of online SDG 1 1 1.4 1 4.4 1 2.1 1 2.1 1 2.2 12.3
commerce platform services &2
E-Governance Establishment of Number of online SDG 10 1 1.4 1 4.4 1 2.1 1 2.1 1 2.2 12.3
County e-government services being offered.
portal
establishment of a Number of MIS SDG 16 1 1.4 1 8.8 1 5.2 1 5.3 1 2.2 22.9
county management developed
information system
(MIS)
Integrated County percentage of revenue SDG 9 1 35.5 1 8.8 1 10.3 1 10.7 1 11.2 76.5
collected
County-Wide Digital Percentage of county SDG 9 1 7.1 1 4.4 1 5.2 1 5.3 1 5.6 27.6
Infrastructure offices with high-speed
internet access
County Enterprise Timely access to SDG 9 1 28.4 1 4.4 1 3.1 1 3.2 1 3.4 42.4
Resource Planning information
85
Programme/ Key Outputs Key Performance Linkage Planned Targets and indicative budgets (Ksh in million )
Sub-Programme Indicator ( KPI) to SDG 2023-2024 2024-2025 2025-2026 2026-2027 2027-2028
Targets Target Cost Target Cost Target Cost Target Cost Target Cost TOTAL
(ERP)Management
Information System
Sub-Total Sub-Total 88.7 77.1 69.3 56.7 56.2 348.0
Programme Name 10: Nurturing Care for Early Childhood Development (Smart Start Siaya)
Objective: To enable all children in Siaya County up to five years of age grow and develop to their full potential
Outcome: Children survive and thrive
NCfECD No. of policies with 1 1.8 0.0 0.0 0.0 0.0 1.8
Coordination integrated NC
Collaboration approaches.
and Partnerships
Nurturing Care for Early 1 0.0 0.0 0.0 0.0 0.0 0.0
Childhood Development
Programme made an
expenditure item in the
budget
No. of NCfECD 0.0 4 1.8 4 2.1 4 2.1 0.0 6.0
Policies and Guidelines
disseminations
conducted
NCfECD Advocacy and 1 2.1 0.0 0.0 0.0 0.0 2.1
outreach action plan
prepared
No. of ESSEC/ MST 12 2.6 12 3.2 12 3.7 12 3.8 12 4.0 17.3
Coordination meetings
held
No. of network./ 25 2.7 25 3.6 25 4.7 25 5.3 25 6.2 22.5
collaborative activities
implemented
Facility capacity 1 0.6 0.0 0.0 0.0 0.0 0.6
building needs
assessment Report
No. of staff trained on 71 3.9 0.0 0.0 0.0 0.0 3.9
NCfECD skillsets
NCfECD Indicator 1 1.3 0.0 0.0 0.0 0.0 1.3
handbook developed
No. of Evaluations 1 1.8 1 2.4 1 3.1 1 3.5 1 4.0 14.9
Conducted
No. of Periodic Progress 5 1.8 5 2.2 5 2.6 5 2.7 5 2.8 12.0
reports prepared and
disseminated.
No. of NCfECD Data 1 2.5 0.0 0.0 0.0 0.0 2.5
Management System
Sub-otal Total 20.9 13.1 16.2 17.5 17.1 84.8
Programme Name: legislation and Representation
Objective: To strengthen the representation function of the assembly
Outcome: Effective representation
Representation Representative No. of trainings 4 7.8 4 9.6 4 11.4 4 11.8 4 12.4 53.0
capacity of members conducted
and staff built
86
Programme/ Key Outputs Key Performance Linkage Planned Targets and indicative budgets (Ksh in million )
Sub-Programme Indicator ( KPI) to SDG 2023-2024 2024-2025 2025-2026 2026-2027 2027-2028
Targets Target Cost Target Cost Target Cost Target Cost Target Cost TOTAL
Equipment acquired No. of wards offices 30 10.6 0 0.0 0 0.0 0 0.0 0 0.0 10.6
and distributed to the equipped
ward offices
Office spaces leased No. of office spaces 12 1.6 12 1.9 12 2.3 12 2.4 12 2.5 10.6
leased for the non-
elected members
Legislation Legislative capacity of No. of trainings 4 7.8 4 9.6 4 11.4 4 11.8 4 12.4 53.0
members and staff conducted
built
Assembly complex % completion of 50 177.3 50 218.9 0 0.0 0 0.0 0 0.0 396.2
constructed Assembly complex
Acquisition of 2.8 0 0.0 0 0.0 0 0.0 0 0.0 2.8
alternative land for
construction of the
Speaker’s Residence
Construction of the % completion of 100 24.8 0 0.0 0 0.0 0 0.0 0 0.0 24.8
Speaker’s Residence speaker’s residence
Technical staff No. of technical staff 4 2.7 0.0 0.0 0.0 0.0 2.7
recruited recruited
Sub Total 235.5 240.1 25.0 25.9 27.2 553.8
Programme Name: Oversight
Objective: To strengthen the oversight function of the assembly
Outcome: Effective oversight
Oversight Legislative capacity of No. of trainings 4 8.1 4 9.6 4 11.4 4 11.8 4 12.4 53.3
members and staff conducted
built
Sub Total 8.1 9.6 11.4 11.8 12.4 53.3
Grand Total 2,240.0 2,463.7 2,710.1 2,981.1 3,279.2 13,674.0
87
4.1.2 Agriculture and Livestock
Sector Introduction
The sector is among the key sectors that is critical in revitalizing the county’s economic growth under the
Vision 2030. It contributes to economic and social development of the county through enhancing food
security; income generation; employment and wealth creation. The sector also contributes significantly to
socio-economic growth and development through forward and backward linkages with other priority sectors
of the economy.
The sector is composed of three execution units namely; Crops; Livestock and Veterinary; Fisheries. The
mandate of the sector is to increase crop, livestock and fisheries production and productivity. It envisions a
food secure county focused on commercially oriented agriculture. The mission of the sector is to transform Crop,
Livestock and Fisheries industry for sustainable food security and income generation. The sector goal is to
improve agricultural production and productivity and promote commercial agriculture.
89
Sector Programmes and Flagship Projects
To improve agricultural production and productivity the sector will invest in the following key interventions; enhance extension services;
establishment of Agricultural Training Centre (ATC), agricultural subsidy programs (food, horticulture, industrial crops, fish inputs); develop
irrigation infrastructure; production of dairy, beef, apiculture and poultry; promote artificial insemination and vaccination; establish fish
hatchery and demonstration centres. The sector will also promote commercial agriculture through establishment of agri-business fund and agro-
processing infrastructure for value addition in rice, cotton, sunflower, groundnuts, and fish.
Sector Programmes
Sub program Key Output Key Performance Indicators Linkages to Planned Targets and Indicative Budget (KSh. Millions
SDG Targets 2023 2024 2025 2026 2027 Total
- - - - - Budg
2024 2025 2026 2027 2028 et
Tar Co Tar C Tar C Tar Co Tar Co
get st get os get os get st get st
t t
PROGRAMME 1: General Administration, Planning and Support Services
Objective: To strengthen coordination of sectoral and inter sectoral programmes
Outcome: Improved sector performance
General Improved extension Services No of farmers trained (000) 2.1, 2.2, 2.3 100 2 115 2 120 3 125 3.5 130 4 14.5
administration No. of agricultural demonstrations 30 3 30 3 30 3 30 3 30 3 15
Functional agricultural show 1 10 1 3 1 2 1 2 1 2 19
No of trade fairs and exhibitions 5 5 5 5 5 5 5 5 5 5 25
Functional Agricultural Training Centre (ATC) 1 25 1 25 1 0 1 0 0 0 50
Functional agricultural laboratory 1 6 1 3 1 2 1 2 1 2 15
No. of staff in post (including promotions) 234 15 294 16 354 18 414 19 474 219 916
0 5 1. 9.6 .61
5 5 5
No. of sector TNA reports prepared, submitted 1 3 0 0 0 0 1 3 0 0 6
and implemented
No of sector committees meeting 4 1 4 1 4 1 4 1 4 1 5
Assorted Operational tools and equipment 59 8 46 3 49 3 45 3 45 3 20
acquired
No. Vehicles procured 0 0 1 5 0 0 1 5 0 0 10
No Motorcycles procured 4 1.6 4 1. 4 1. 4 1.6 4 1.6 8
6 6
No. of sector asset reports prepared and 1 0.1 1 0. 1 0. 1 0.1 1 0.1 0.5
updated 1 1
Planning and Support Performance management No of Signed Performance Contracts 1 2 1 2 1 2 1 2 1 2 10
services strengthened No. of administrative reports prepared 4 3.2 4 0. 4 0. 4 0.2 4 0.2 4.05
5 2 2
No of policies, strategies, bills, regulations and 1b,17.13 8 0.7 5 1. 7 7. 4 2.5 4 1.5 13.75
plans developed 5 5 5
SUB TOTALS 22 22 21 23 245 1131.
0.7 0. 1. 3.5 .01 565
4 9 5 5
90
Sub program Key Output Key Performance Indicators Linkages to Planned Targets and Indicative Budget (KSh. Millions
SDG Targets 2023 2024 2025 2026 2027 Total
- - - - - Budg
2024 2025 2026 2027 2028 et
Tar Co Tar C Tar C Tar Co Tar Co
get st get os get os get st get st
t t
Programme 2: Crop and Land Management
Objective: To increase crop production and productivity
Outcome: Increased food security and incomes
Land management Increased acreage through Acreage ploughed (Ha) under subsidy SDG 2.1, 2.1, 1,87 5.6 7,50 22 22,5 67 22,5 67. 22,5 100 263.1
Mechanization programme 2.3, 2.4, 2.5 and 5 0 .5 00 .5 00 5 00
2.a
No of tractors acquired 5 20 15 75 15 75 0 0 15 75 245
Enhanced soil management and No of soil samples taken for testing 5500 0.5 7000 0. 9000 0. 1000 1 1100 1.1 4.25
conservation 5 7 9 0 0
No of soil testing kits acquired 30 0.3 30 0. 30 0. 30 0.3 30 0.3 1.5
3 3
Increased acreage under irrigation Area under Irrigation (Ha) SDG 2.1, 2.1, 0.00 0 1,71 54 2,42 54 3,21 72 4,00 85 265
2.3, 2.4, 2.5 and 5 9 5 0
2.a
County Irrigation Profile developed 1 15 0 0 0 0 0 0 0 15
Crop Production Increased production and MT of fertiliser distributed SDG 2.1, 2.1, 600 40 600 40 1,20 78 1,60 11 1,20 78 347
productivity of Food crops 2.3, 2.4, 2.5 and 0 0 1 0
2.a
MT of assorted food crop Seed distributed A 100 25 150 52 200 78 250 13 250 135 425.7
.7 5
Pesticides (Lts/ Kgs) distributed 3000 6 3500 7 400 8 500 10 500 10 41
Increased production and Number of horticultural crop seedlings SDG 2.1, 2.1, 25,0 6.5 38,0 9 30,0 9 30,0 12 38,0 8.2 44.75
productivity of horticultural Crops distributed 2.3, 2.4, 2.5 and 00 00 00 00 00 5
2.
Number of horticultural packhouses 1 5 0 0 0 0 0 0 0 0 5
constructed
Increased production and MT of seed distributed 6 4 8 5 10 6 12 8 14 10 33
productivity of Rice Development Project 12 17 192 496.9
industrial/commercial Crops 5 9.7 .2
25 26 37 59 694 2187.
2.9 5. 7. 6.5 .85 2
5 5 4
Programme: Agri business development
Objective: To enhance commercialization in the agrifood sector
Outcome: increased agricultural income ( on farm and county GDP
Agro processing Improved Agro processing and No of agribusiness incubation activities for SDG 2.1, 2.1, 8 4 8 4 8 4 8 4 8 4 20
value addition of agricultural cottage industries. 2.3, 2.4,
produce
Improved infrastructure for Agro No. of agro processing infrastructure SDG 2.1, 2.1, 1 88. 2 10 1 10 0 0 3 3 206.5
industrial processing and value established and operationalized 2.3, 2.4, 2.5 55 5 5
addition No of market linkage programmes undertaken 1 5 2 5 3 5 4 5 5 5 25
Agricultural financing Improved access to Agricultural Number of Agribusiness entrepreneurship fund 8.1 1 24 1 24 1 24 1 24 1 24 120
Financial services established
Agricultural Improved agricultural marketing Number of crop, livestock and fish aggregation SDG 2.1, 2.1, 5 25 5 25 5 25 5 25 5 25 125
91
Sub program Key Output Key Performance Indicators Linkages to Planned Targets and Indicative Budget (KSh. Millions
SDG Targets 2023 2024 2025 2026 2027 Total
- - - - - Budg
2024 2025 2026 2027 2028 et
Tar Co Tar C Tar C Tar Co Tar Co
get st get os get os get st get st
t t
marketing infrastructure centres/ and or cooling structures 2.3, 2.4, 2.5 and
2.a
No of Agribusiness industrial parks established 0 0 0 0 1 10 0 0 0 0 100
0
No of market linkage activities 30 0.6 30 0. 30 0. 30 0.6 30 0.6 3
6 6
Youth in agribusiness Improved access to Agricultural Number of Youth financed SDG 2.1, 2.1, 200 40 200 40 200 40 200 40 200 40 200
Financial services young people 2.3, 2.4, 2.5 and
Enhanced Skills for youth in No of 4k clubs, community outreach and award 2.a 30 1 30 1 30 1 30 1 30 1 5
agribusiness systems revamped
Number of youth agri-business innovations 6 3 6 3 6 3 6 3 6 3 15
developed
No of youth friendly Smart farms 6 1 2 1 2 2 4 1 2 1 2 12
No of youth farmer business schools 6 10 6 10 6 10 6 10 6 10 50
established to offer skills training
Information Improved No of Agriculture information management 9c 1 5 1 0. 1 0. 1 0.5 1 0.5 7
management in the systems in place and operational 5 5
agrifood sector Number of market surveys undertaken SDG 2.1, 2.1, 0 0 1 1 0 1 1 0 1 1 3
2.3, 2.4, 2.5 and
2.a
Total Sub Total 20 22 22 11 119 891.5
8.1 1. 8. 5.1 .1 5
5 1 1
Programme: Livestock Management and Development
Objective: To increase livestock production, productivity and value addition
Outcome: Increased food security and incomes
Apiculture Improved production and No of groups supported with hives and SDG 2.4 24 3 24 6 24 6 24 6 24 6 27
development productivity from apiculture beekeeping equipment
No of apiary demo centres established SDG 2.a 0 0 1 5 0 0 1 5 0 0 10
Meat production and Improved meat production 0
marketing No of feedlots established SDG 2.a 0 0 1 5 1 5 0 0 0 0 10
No of livestock markets improved SDG 2.a 0 0 2 20 2 20 2 20 1 10 70
No of goats and sheep multiplication centres SDG 2.5 0 0 1 10 0 0 0 0 1 10 20
established
Dairy production Improved dairy production and No of dairy cows distributed SDG 2.5 400 5 400 5 400 5 400 5 400 5 25
productivity No of dairy Strategies implemented SDG 2.4 1 8 1 8 1 8 1 8 1 8 40
No of processing equipment distributed SDG 2.a 26 5 26 5 26 5 26 5 26 5 25
No of feed mills operationalized SDG 2.4 1 5 0 0 1 20 0 0 0 0 25
No of fodder barns constructed SDG 2.4 2 5 2 10 3 15 3 15 2 10 55
Poultry production Improved poultry production and No of breeding stock distributed SDG 2.4 30,0 5 30,0 5 30,0 5 30,0 5 30,0 5 25
and marketing productivity 00 00 00 00 00
No of Colleges expanded to offer livestock SDG 2.a 0 0 1 0 1 0 0 0 0 0 0
training
Sub Total 36 79 89 69 59 332
92
Sub program Key Output Key Performance Indicators Linkages to Planned Targets and Indicative Budget (KSh. Millions
SDG Targets 2023 2024 2025 2026 2027 Total
- - - - - Budg
2024 2025 2026 2027 2028 et
Tar Co Tar C Tar C Tar Co Tar Co
get st get os get os get st get st
t t
PROGRAMME FOUR: Fisheries Management and Aquaculture Development
OBJECTIVE: To Sustainably develop and manage the Fisheries Resources for Increased Fish Production and Productivity
OUTCOME: Sustainable Utilization of Fisheries Resources
Capture fisheries Sustainable exploitation of capture No. of fisheries surveillance reports SDG 2.1, 2.1, 12 3 12 3 12 3 12 3 12 3 15
fisheries resources No of County Fish Breeding Areas Map 2.3, 2.4, 2.5 and 0 0 1 4 0 0 0 0 0 0 4
developed 2.a
No. of fisheries surveillance motorized boats 2 4 7 21 6 10 6 10 5 5 50
acquired
No of BMUs supported with fishing inputs 5 5 5 5 5 5 5 5 5 5 25
No. of Quarterly stakeholders‘ meetings by 4 1 4 1 4 1 4 1 4 1 5
riparian counties and governments
No. Surveys (FS and FCS) 13 2.5 12 2. 13 2. 12 2.5 13 2.5 12.5
5 5
No. of BMUs supported with fish weighing 5 1 5 1 5 1 5 1 5 1 5
platforms
Aquaculture Improved production of fish from No. of Aquaculture support enterprises SDG 2.1, 2.1, 20 0.1 20 0. 20 0. 20 0.1 20 0.1 0.5
development aquaculture 2.3, 2.4, 2.5 and 1 1
No of public dams re-stocked with fish 2.a 10 10 0 0 10 10 0 0 10 10 30
No of direct beneficiaries of targeted fisheries 50 10 50 10 50 10 50 10 50 10 50
support programmes ( culture units-cages and
ponds)
Functional Fish Hatchery and Demonstration 1 10 1 15 0 0 0 0 0 0 25
Centre
Post-harvest Fisheries Enhance safety & quality of fish No. of fish handling infrastructure SDG 2.1, 2.1, 4 4 4 4 4 4 4 4 4 4 20
Management and fisheries products marketed established 2.3, 2.4, 2.5 and
No. of fish inspectors trained and gazetted 2.a 0 0 5 1. 5 1. 5 1.5 0 0 4.5
5 5
No. of inspections reports for fish management 13 1 13 1 13 1 13 1 13 1 5
value chain prepared
No of stalled fish handling projects completed 1 20 1 10 0 0 0 0 0 0 30
No of fresh fish retail outlets supported 0 10 5 10 5 10 5 10 5 10 50
No of fish marketing platforms developed 0 0 1 1 0 0 0 0 0 0 1
Sub Total 81. 90 59 49. 52. 332.5
6 .1 .1 1 6
Programme: Veterinary services
Objective: To improve animal health and welfare
Outcome: Reduced disease prevalence, morbidity and mortality
Animal Breeding Improved livestock breeds No. of animals inseminated SDG 2.1, 2.1, 1,00 0.8 1,00 1 1,00 1 1,00 1 1,00 1 4.8
2.3, 2.4, 2.5 and 0 0 0 0 0
No. of animals vaccinated 2.a 1000 5 1000 5 1000 5 1000 5 1000 5 25
Disease and vector Improved livestock health No. of animals sprayed SDG 2.1, 2.1, 1750 2.5 1750 3. 1750 3. 1750 3.5 1750 3.5 16.5
management services 2.3, 2.4, 2.5 and 5 5
No of crush pens constructed 2.a 6 1.5 6 1. 6 1. 6 1.5 6 1.5 7.5
5 5
93
Sub program Key Output Key Performance Indicators Linkages to Planned Targets and Indicative Budget (KSh. Millions
SDG Targets 2023 2024 2025 2026 2027 Total
- - - - - Budg
2024 2025 2026 2027 2028 et
Tar Co Tar C Tar C Tar Co Tar Co
get st get os get os get st get st
t t
No. of animals inspected ante mortem 60,0 0.8 60,0 1. 60,0 1. 60,0 1.2 60,0 1.2 5.6
00 00 2 00 2 00 00
Animal product safety Improved safety of animal product No. of carcasses inspected SDG 2.1, 2.1, 60,0 2.5 60,0 2. 60,0 2. 60,0 2.5 60,0 2.5 12.55
2.3, 2.4, 2.5 and 00 00 5 00 5 00 5 00
No of slaughterhouses operationalized 2.a 0 0 1 4 1 3 1 3.5 1 3.7 14.23
35 5
Sub Total 13. 18 17 18. 18. 86.18
1 .7 .7 25 435 5
GRAND TOTAL 81 89 98 10 118 4961
2.5 4. 3. 81. 9
8 2 5
94
4.1.3 Health and Sanitation
4.1.1.1 Sector Introduction
The mandate of the sector includes; Community health; health education; primary health care;
environmental health; disease control; County health facilities and pharmacies; ambulance services;
medical supplies; Medical machines and instruments; health facilities infrastructures; health care
systems amenities and medical waste management.
The sector is composed of two execution units namely; Curative, biomedical, rehabilitative and
referral services; preventive and promotive health services. The sector envisions a healthy and
productive county through provision of quality healthcare for all. The goal of the sector is to provide
accessible, quality and affordable healthcare.
95
Goals Sector Priorities Strategies
-Provide adequate office accommodation and operational equipment
-Strengthen partner and resource mobilization
-Strengthen policy formulation and implementation framework
-Recruit more human resource for health
Strengthening of -Implementation of universal health coverage
universal health -Capacity building on UHC agenda
coverage
96
Sector Programs and Flagship
The sector plans to provide accessible, quality and affordable healthcare through: Recruitment of healthcare workers; enhance universal
healthcare; construction of hospital complexes in Siaya and Bondo; equipping existing health facilities; establishment of model health
centres; strengthen management of health commodities; upscale the health referral system; strengthen management of communicable and
non-communicable diseases especially HIV, Malaria, TB and mental health.
Program/Sub key output Key Performance Linkage to SDGs 23/24 24/25 25/26 26/27 27/28 Total
program indicators cost cost cost cost cost Budget
No. of CHVs in post SDG 3 2123 100.00 2128 118 2128 143 2128 170 2128 196 727
TNA report developed and SDG 3 32 4.82 214 3.62 514 3.77 514 2.43 303 2.16 17
implemented
Reduced No of individual enrolled in SDG 3 40,000 60.00 60 15.08 75 11.08 90 11.16 100,000 12.00 109
health care UHC
cost
equipment No of assorted machinery SDG 3 22 14.86 23 12.97 21 7.98 21 9.29 22 60.08 105
and purchased and maintained
machinery No of assorted office SDG 3 100 6.02 100 5.43 100 4.65 100 8.44 100 6.48 31
equipment purchased
No of Ambulance SDG 3 6 19.27 6 14.78 6 16.08 6 11.30 6 62.48 124
purchased
no of medical equipment on SDG 3 6 40.15 7 30.16 8 50.15 9 34.31 11 145.99 301
service contract
Improved No. of performance SDG 3 12 1.61 12 1.21 12 0.89 12 0.57 12 0.96 5
staff management reports
performance
No of utilities procured SDG 3 192 100.00 192 51.87 192 138.55 192 75.48 192 95.60 461
No of facility reports SDG 3 173 6.42 173 5.43 175 5.10 178 8.58 1,800 6.48 32
generated
No of health facilities with SDG 3 20 1.20 50 6.03 80 5.32 20 5.29 10 2.88 21
automated services
Planning and Legislation No of developed SDG 3 2 1.61 1 0.60 1 0.44 1 0.29 1 0.48 3
Support ,and Policies
services developed
No of Health facilities and 12 4.02 0.00 12 2.22 0.00 0.00 6
Doctors with indemnity
cover
97
Program/Sub key output Key Performance Linkage to SDGs 23/24 24/25 25/26 26/27 27/28 Total
program indicators cost cost cost cost cost Budget
SUB TOTAL 1,909 2,170 5,945 2,387 6,083 2,465 2,834.46 11,765
Name of Programme: Curative, Biomedical ,Rehabilitative and Referral Services
Program Objective: To provide accessible, affordable and expanded diagnostic and curative services
Program Outcome :An affordable, accessible and appropriate diagnostic and curative services
Curative Improve ISO 15189 certified SDG 3 2 0.62 0 0.00 1 0.22 1 0.14 1 0.24 1
labaratory Laboratories on Diagnostic
and services
diagnostic
services
Blood Bank fully Equipped SDG 3 1 9.36 1 3.02 1 2.22 1 2.43 1 2.40 19
and Operational
Purchase of Laboratory SDG 3 4 12.49 4 12.06 4 8.86 4 5.73 4 16.60 56
diagnostic supplies and
reagents
Purchase of Laboratory SDG 3 4 6.24 4 6.03 4 4.43 4 7.86 4 11.80 36
diagnostic equipment
Establishment of county SDG 3 50 3.75 50 3.62 50 2.66 50 1.72 50 2.88 15
samples referral network
Strengthening SDG 3 200 0.94 200 0.90 200 0.66 200 0.43 200 0.72 4
Biosafety/Biosecurity and
Infection Prevention Control
measures in all functional
Laboratories
Improved Number of X- Ray premises 3 1 0.04 1 0.03 1 0.03 1 0.02 1 0.03 0
Radiology inspected and licences
services
To improve Medical supplies and 3 1 183.85 1 226.62 2 364.61 3 574.25 4 370.79 1,720
management technologies procured
of health
products and
technology
improved Assistive devices to 3 0 0.78 1 0.96 1 0.89 1 0.93 1 1.08 5
rehabilitation rehabilitative patients
services purchased
98
Program/Sub key output Key Performance Linkage to SDGs 23/24 24/25 25/26 26/27 27/28 Total
program indicators cost cost cost cost cost Budget
99
Program/Sub key output Key Performance Linkage to SDGs 23/24 24/25 25/26 26/27 27/28 Total
program indicators cost cost cost cost cost Budget
100
Program/Sub key output Key Performance Linkage to SDGs 23/24 24/25 25/26 26/27 27/28 Total
program indicators cost cost cost cost cost Budget
101
Program/Sub key output Key Performance Linkage to SDGs 23/24 24/25 25/26 26/27 27/28 Total
program indicators cost cost cost cost cost Budget
102
Program/Sub key output Key Performance Linkage to SDGs 23/24 24/25 25/26 26/27 27/28 Total
program indicators cost cost cost cost cost Budget
103
Program/Sub key output Key Performance Linkage to SDGs 23/24 24/25 25/26 26/27 27/28 Total
program indicators cost cost cost cost cost Budget
104
Program/Sub key output Key Performance Linkage to SDGs 23/24 24/25 25/26 26/27 27/28 Total
program indicators cost cost cost cost cost Budget
105
Program/Sub key output Key Performance Linkage to SDGs 23/24 24/25 25/26 26/27 27/28 Total
program indicators cost cost cost cost cost Budget
106
Program/Sub key output Key Performance Linkage to SDGs 23/24 24/25 25/26 26/27 27/28 Total
program indicators cost cost cost cost cost Budget
107
Program/Sub key output Key Performance Linkage to SDGs 23/24 24/25 25/26 26/27 27/28 Total
program indicators cost cost cost cost cost Budget
Improve Proportion of children aged SDG 2, 3,17 1 1.65 1 1.18 1 0.86 1 0.55 1 0.93 5
nutritional 12--59 months supplemented
status with Vitamin A
Vitamin A coverage 80% 1.28 83% 0.00 87% 0.66 89% 0.00 95% 0.00 2
Children 6-11 months
0.00 0.00 0.00 0.00 0.00
Proportion of children aged 1 0.43 1 0.30 1 0.22 1 0.14 1 0.24 1
12-59 months dewormed
Proportion of infants less 1 0.10 1 0.06 1 0.05 1 0.03 1 0.06 0
than 6 months old on
Exclusive Breastfeeding
Proportion of pregnant 58 0.43 1 0.30 1 0.22 1 0.14 1 0.24 1
women attending ANC who
received combined
iron/folate supplements
Proportion of children 0-59 SDG 2,3,17 1 0.85 1 0.45 1 0.33 1 0.21 1 0.36 2
months with Severe Acute
Malnutrition (SAM) who
recovered/cured from
treatment (Stabilization
Centre Recovery rate -
Nutrition)
Strengthen Primary Care Networks SDG 3 and 17 2 0.85 1 0.30 1 0.11 1 0.07 1 0.12 1
Primary established
Health care
services
Proportion of HIV positive 95% 2.13 95% 1.51 95% 1.11 95% 0.72 95% 4.80 10
clients linked to treatment
Proportion of HIV positive 1 2.13 1 1.51 1 1.11 1 0.72 1 4.80 10
clients who are on treatment
Percentage of HIV exposed 0 1.28 0 0.90 5% 0.66 3% 0.43 <1% 0.72 4
infants (HEI) who turn
negative at 18 months
Improve TB Number of TB clients 200 1.71 200 1.21 200 0.89 200 0.57 200 0.96 5
case admitted in the Isolation
management ward
108
Program/Sub key output Key Performance Linkage to SDGs 23/24 24/25 25/26 26/27 27/28 Total
program indicators cost cost cost cost cost Budget
109
Program/Sub key output Key Performance Linkage to SDGs 23/24 24/25 25/26 26/27 27/28 Total
program indicators cost cost cost cost cost Budget
response
111
4.1.4 Water, Environment and Natural Resources
Sector Introduction
The sector is mandated to oversee and coordinate water and sewerage services provision; ensure
development of water and sanitation infrastructure; ensure rehabilitation and expansion of forest and
tree covers; Enhance environmental conservation awareness and beautification activities; Manage the
Natural Resources with a view to ensuring sustainable utilization without degrading the environment;
Ensure effective noise and excessive vibrations pollution or nuisance regulation; promote climate
change mitigation and adaptation plans.
The Sector is composed of three execution units namely: Water Resource Management; Environment
and Natural Resources Management and Climate change. The sector envisions access to safe water
and sanitation in a secure and sustainable environment. The vision will be actualized through
improving access to safe water, sanitation and promoting environmental conservation. The goals of
the sector are; Provision of safe water and sewerage services; build resilience to impacts of climate
change and Environment conservation.
113
Sector Programmes and Flagship Projects
To provide safe water and sewerage services, the sector plans to; develop Siaya water masterplan; augmentation of Yala water intake;
Expansion of last mile connectivity (SIBOWASCO, Ugunja-Sega-Ukwala); construction of wichlum water project and construction of new
solar powered boreholes. The sector also plans to conserve the environment through reclamation of riparian land with bamboo and fruit
trees. afforestation of hill tops and beautification of urban areas. To build resilience to impacts of climate change, the sector will establish
climate change centres, climate change and adaptation projects and climate change awareness creation.
Sub Programme Key Output Key Performance Linkages Planned Targets and Indicative Budget (KSh. M) Total
Indicators to SDGs Budget
2023-2024 2024-2025 2025-2026 2026-2027 2027-2028
Target Cost Target Cost Target Cost Target Cost Target Cost
Programme: Water resources development and management
Objective: To provide safe water
Outcome: Improved access to safe water
Water resources Improved access No water pans SDG 6.1, 4 9 10 30 10 30 10 30 10 30 129
conservation and to quality water improved 6.3, 6.6
protection No of water Dams SDG 6.1, 0 0 5 51 5 52 5 53 5 54 210
rehabilitated 6.3, 6.6
No of existing SDG 6.1, 10 25 10 25 10 25 5 12.5 5 12.5 100
boreholes 6.3, 6.6
equipped with
solar pumps
Water Master SDG 6.1, 1 0 0 0 0 0 0 0 0 0
plan= Minus 6.3, 6.6
150M
No of water SDG 13 & 0
management 6
committees trained
No. water points SDG 13 & 0
survey conducted 6
Automation of SDG 13 & 1 3 0 0 0 0 0 0 0 0 3
services 6
Development of
USSD user
feedback interface
SIBOWASCO SDG 6.1, 0 0 0 0 0 0 1 50 0 0 50
Last-mile 6.3, 6.6
Connectivity
(Targeting
households and
public institutions)
Wichlum Water SDG 6.1, 0 0 1 50 0 0 0 0 0 0 50
Project 6.3, 6.6
114
Sub Programme Key Output Key Performance Linkages Planned Targets and Indicative Budget (KSh. M) Total
Indicators to SDGs Budget
2023-2024 2024-2025 2025-2026 2026-2027 2027-2028
Target Cost Target Cost Target Cost Target Cost Target Cost
Augmentation of SDG 6.1, 1 1 1 1 1 0
Yala Water Intake 6.3, 6.6
No of new SDG 6.1, 10 50 10 50 5 30 5 30 5 30 190
boreholes drilled/ 6.3, 6.6
Rehabilitated and
equipped with
solar
No of shallow SDG 6.1, 10 5 10 6 10 7 5 8 5 9 35
wells maintained 6.3, 6.6
No. of community SDG 6.1, 3 120 3 60 2 50 1 50 3 50 330
water supplies 6.3, 6.6
schemes
rehabilitated &
augmented
No of rain water SDG 6.1, 10 5 10 6 10 7 10 8 10 9 35
harvesting systems 6.3, 6.6
installed for ECDE
centers and
dispensaries
Km of water 10 30 5 20 5 20 10 30 0 0 100
pipeline extensions
laid
No of springs SDG 6.1, 12 5 12 6 12 7 12 8 12 9 35
protected and 6.3, 6.6
conserved
Siaya water and 1 12 0 0 0 0 0 0 0 0 12
sanitation project
(DorcasAid Maji
Milele and CGS)
Gazetted No of existing SDG 6.1, 1 50.83 1 51 1 52 1 53 0 0 206.826
Existing water gazetted water 6.3, 6.6
supply schemes supply schemes
rehabilitated and rehabilitated and
expanded expanded
Water supply and New sewerage No of urban SDG 6.1, 1 1 1 1 1 0
urban sewerage systems centers with new 6.3, 6.6
development sewer systems
No of public SDG 6.1, 2 2 2 2 2 0
institutions 6.3, 6.6
connected to the
sewer line
Expansion (Last 100 120 140 62 482
Mile
connectivity) for
60
Ugunja- Sega
Ukwala Water
Project
115
Sub Programme Key Output Key Performance Linkages Planned Targets and Indicative Budget (KSh. M) Total
Indicators to SDGs Budget
2023-2024 2024-2025 2025-2026 2026-2027 2027-2028
Target Cost Target Cost Target Cost Target Cost Target Cost
Siaya Bondo 0
Water Project 0
(National)
Climate change 0
Center
Establishment
Sub total 374.8 455 400 472.5 265.5 1967.826
Programme: Natural resources conservation and management
Objective: To attain a clean, secure and sustainable environment
Outcome: Improved natural resources management e.g water resources conservation and management
Natural resources Environment Number of SDG 6 and 6 6 10 3.5 10 3.8 10 4 10 4.5 21.8
development, conservation demonstration tree 13
conservation and nurseries
management (to developed
include mines, Km of riparian SDG 6 and 10 10 10 10.3 10 10.5 10 10.8 10 11 52.6
rivers, lakes) land reclaimed: 13
Bamboo and fruit
trees
No. of trees SDG 6 and 5 50 5 50 5 50 5 50 5 50 250
planted in Millions 13
(Tree planting
campaigns)
No. of SDG 6 and 11 1 11 1 11 1 11 1 11 1 5
environmental 13
calendar days
observed (11)
no. of SDG 6 and 2 0.5 0 0 0 0 0 0 0 0 0.5
environmental 13
natural resources
committee
established and
operationalized
No of hilltops SDG 6 and 21 10 6 10 6 10 6 10 6 10 50
gazetted and 13
afforested
No. natural 0 0 1 2 0 0 0 0 0 0 2
resources survey
conducted
Purchase of SDG 6 and 6 3 0 0 0 0 0 0 0 0 3
decimeter 13
No of urban areas SDG 6 and 3 2 2 2 2 0
beautified 13
Sub total 80.5 76.8 75.3 75.8 76.5 384.9
Programme: Climate Change Mitigation and Adaptation
116
Sub Programme Key Output Key Performance Linkages Planned Targets and Indicative Budget (KSh. M) Total
Indicators to SDGs Budget
2023-2024 2024-2025 2025-2026 2026-2027 2027-2028
Target Cost Target Cost Target Cost Target Cost Target Cost
Objective: To enhance resilience to climate change effects and impacts
Outcome: Improved adaptation to climate change effects and impacts
Climate change Climate smart No. of climate SDG 13 30 6 30 6 30 6 30 6 30 6 30
interventions projects change awareness
campaigns
No of climate SDG 13 3 1 3 1 3 1 0 0 0 0 3
change structures
established and
operationalized
No of climate SDG 13 3 6 0 3 7 0 0 3 8 21
change adaptation
and mitigation
projects
No of climate SDG 13 0 0 0 0 1 22 0 0 0 0 22
change centre
established and
equipped
international SDG 13 5 1 5 1 5 1 5 1 5 1 5
linkages and
collaboration
No of Biogas SDG 13 0 0 1 10 0 0 1 10 0 0 20
Centers
established
No of energy SDG 13 90 5 90 6 90 7 90 8 90 9 35
saving cook stoves
installed
Sub total 19 24 44 25 24 136
Programme Name: Administration, Planning and Support Services
Objective: To Ensure Efficient Functioning of the Department
Outcome: Enhanced sectorial performance and improved citizen satisfaction
General Efficient No. of Motor SDG 13 & 1 6 0 0 1 7 0 0 0 0 13
administration departmental vehicles purchased 6
operations
operations No.of motor-bikes SDG 13 & 3 2 3 2.5 3 3 0 0 0 0 7.5
procured 6
No.of motor SDG 13 & 3 1 4 1.5 3 2 5 2 5 2 8.5
vehicles 6
maintained
Governance of No of staff in post SDG 13 & 33 27 33 29.7 33 32.67 33 35.937 33 39.5307 165
rural water (Including 6
facilities Promotions)
Adequate & No.of staff SDG 13 & 7 6 0 0 7 5 7 6 0 0 17
motivated recruited 6
117
Sub Programme Key Output Key Performance Linkages Planned Targets and Indicative Budget (KSh. M) Total
Indicators to SDGs Budget
2023-2024 2024-2025 2025-2026 2026-2027 2027-2028
Target Cost Target Cost Target Cost Target Cost Target Cost
departmental
personnel
No.of staff SDG 13 & 10 1 10 1 10 1 10 1 10 1 5
capacity built 6
No of staff SDG 13 & 28 4 35 5 41 5 55 5 35 5 24
promotion 6
Planning and Sectoral No. of legislations, SDG 13 & 3 6 2 4 2 4 0 0 0 0 14
support services legislations policies and plans 6
formulated
No of surveys SDG 13 & 2 2 2 2 1 1 0 0 0 0 5
conducted and 6
design reports
prepared
No. of report SDG 13 & 20 3 20 4 20 5 20 6 20 7 25
prepared and 6
submitted
Office Operations SDG 13 & 1 11 1 11 1 11 1 10 1 10 53
6
General office SDG 13 & 10 2 10 3 10 3.5 10 4 10 4.5 17
equipment 6
procured and
purchased
Sub total 71 63.7 80.17 69.937 69.0307
354
Grand total 545.3 620 599.5 643.24 435.031
2,843
118
4.1.5 Transport and Energy
Sector Introduction
The sector is mandated is to improve County transport (county roads &bridges; street lighting; traffic
and parking; public road transport; and ferries and harbours); oversee County public works and
services (storm water management systems in built-up areas); undertake energy and gas reticulation
and regulation and provide fire-fighting services. The sector is composed of three execution units
namely; Transport, public works and Energy. Its vision is to be a premier county in infrastructure and
energy. The mission of the sector to provide quality public transport system, built environment and
promote efficient utilization of energy resources for sustainable socio-economic growth and
development. The goals of the sector are; accessible and well managed public transport system;
quality built environment and Sustainable energy solutions
120
4.2.1 Sector Programmes and Flagship Projects
The sector plans to improve accessibility and management of public transport through: Construction and maintenance of county roads and
bridges including tarmacking; construction of jetties, buffer wall along L. Victoria and feeder ports and upgrading of air strips. The sector
also plans to improve the quality of the built environment through firefighting services; preparation and supervision of building plans. To
provide sustainable energy solutions, the sector will construct energy centres and preparation of master plans for off-grid and on grid solar
power and Ndanu falls.
Sub Key Output Key Performance Indicator to SDG Planned Targets and Indicative Budget (KSh. M) Total
Programme Targets Year 1 Year 2 Year 3 Year 4 Year 5 Budget
* Targe Cost Targe Cost Targe Cost Targe Cost Targe Cost (KSh.
t (Millions t (Millions t (Millions t (Millions t (Millions M)*
) ) ) ) )
Programme 1: Transport Infrastructure Development
Objective: To increase accessibility and mobility within the county
Outcome: Improved accessibility within the county
Road Road Km of roads opened,graded and 9.1 15 30 13 30 15 20 10 15 10 15 110
Transport transport gravelled
infrastructur Km of existing roads 150 223 200 250 210 255 211 270 207 280 1278
e developed maintained
Km of roads tamarcked 6.6 231.1 6.1 212 8.4 293.15 11.1 389.215 14.2 496.635 1622.1
No of new box culverts 3 25 2 20 1 10 1 10 1 10 75
constructed
No of box culverts maintained 0 0 6 24 6 24 5 20 6 24 92
No of road construction 0 0 1 0 4 0 0 0 0 0 0
machinery acquired
No of road construction 2 3 5 10.5 9 13.5 0 0 0 0 27
machinery maintained
Air Transport Air transport No of airstrips upgraded 0 0 1 20 1 20 1 20 0 0 60
infrastructur
e developed
Water Water No of jetties constructed 1 10 0 0 1 10 1 10 0 0 30
transport transport (Asembo and Usenge)
infrastructur
e developed
Asembo bay feeder port 0 0 1 10 0 0 0 0 0 0 10
established
sub total 522.1 576.5 645.65 734.215 825.635 3304.1
Programme 2: :County Government Building Services
Objective:Enhanced building safety and output quality in the built Environment
Outcome:Enhanced building safety in the built environment
County Quality % of expected designs 9.1 100 5 100 5 100 5 100 5 100 5 25
public works control of developed
the built No. of supervion and inspection 12 3.6 12 3.6 12 3.6 12 3.6 12 3.6 18
environment reports prepared and submitted
121
Sub Key Output Key Performance Indicator to SDG Planned Targets and Indicative Budget (KSh. M) Total
Programme No. of sensitization reports on Targets 4 1 4 1 4 1 4 1 4 1 5Budget
building safety * (KSh.
Material laboratory equipped 1 10 1 4 0 0 M)*
14
sub total 19.6 13.6 9.6 9.6 9.6 62
Programme 3: Energy and Energy Reticulation
Objective:To promote energy and energy reticulation in the context of climate change.
Outcome:Increased number of households adopting climate friendly sources of energy
Energy and Energy Master plan on off grid, on grid 0 0 1 15 1 15 1 15 45
energy reticulation solar plant and Ndanu falls
reticulation hydropower plan prepered and
operational
No. of energy centres 1 10 1 10 1 10 0 0 0 0 30
constructed and equipped
No of households capacity built 2 2 2 2 2 10
on renewable energy 10,000 10,000 10,000 10,000 10,000
sub total 12 27 27 17 2 85
Programme 4: General Administration, Planning & Support services
Objective: To improve safety and security within the working environment and in the county
Outcome:Improved security in the working environment and Effective Emergency Response
General Strengthene No. of staff inpost (Including 8.3 53 35 63 38.5 73 42.35 83 46.585 93 51.265 213.7
administratio d operation Promotions)
n capacity
No. of staffs capacity built 10 0 10 0 10 0 10 0 10 0 0
Planning and Enhanced No. of office block renovated 1 5 0 0 2 3 0 0 0 0 8
support Operational Assorted office tools and 6 3 6 3 6 3 6 3 6 3 15
services capacity equipment procured(
laptops/computers,printers,offic
e furniture)
No. Of supervision vehicles 1 6 1 6 1 6 0 0 0 0 18
operational
No. Of policies developed and 4 6 0 0 0 0 0 0 0 0 6
approved
Mechanical transport yard 0 0 1 5 0 0 0 0 0 0 5
rehabilited and equipped
Strengthene No. of ME roports prepared and 4 0 4 0 4 0 4 0 4 0 0
d submitted
performance No. of performance contract 1 0.411 1 0.5 1 0.5 1 0.5 1 0.5 2.411
management prepared
sub total 55.411 53 54.85 50.085 54.765 268.111
Grand total 609.111 670.1 737.1 810.9 892 3719.21
1
122
4.1.6 Lands, Housing and Physical Planning
Sector Introduction
The sector is mandated to provide spatial framework that will coordinate land use development for
sustainable growth; secure land for public use and investments; provide adequate, affordable and decent
housing for all; urban development; develop public infrastructure and provide socio-environmental
services within the Municipality. The sector is composed of four execution units namely; Land Use
Planning; County Land Administration and Surveying; Housing and Urban Development; Municipalities.
The vision of the sector is to ensure sustainability in land and urban management and affordable housing
for all through sound planning, management of land resource and urban areas and access to better housing.
The sector goals are; to ensure sustainable land and urban management and to provide quality, adequate
and affordable housing.
4.1 Development Priorities and Strategies
From the analysis of development issues, the following priorities and strategies have been proposed for
implementation.
Goals Sector priorities Strategies
Ensure sustainable Provide quality urban infrastructure Install street lighting in urban areas
land and urban Develop motorized and non motorized facilities
management Develop waste management facilities
Develop storm water management infrastructure
Establish emergency response system
Install water connection infrastructure
Install sewerage connection infrastructure
Construct modern markets
Develop urban by laws
Establish urban governance structures
Delineate urban area boundaries
Effective land use plan Fast track approval of updated land use plans
Fast track approval of county spatial plan and local
land use plans
Enforce development control
Efficient land management Digitize public land record
Secure public land
Titling of public land
Implement land audit and inventory report
Acquire modern survey equipment
Develop valuation roll
Provide quality, Provide affordable and decent housing unit for all Construct government housing units
adequate and Renovate existing government housing units
affordable housing Acquire land for housing development
123
4.2.1 Sector Programmes
4.2 Sector Programmes and Flagship Projects
The sector plans to ensure sustainable land and urban management through: operationalization of the GIS laboratory; land banking;
implementation of Yala land use plan construction of storm water drainages, solid waste management motorized and non-motorized facilities
in urban areas. The sector also plans to provide affordable housing in Siaya and bondo, establish an eco-city in L.Kanyaboli, construct state
officers residence; county executive administrative headquarters
Sub programme Key Output Key Performance Linkages Planned Targets and Indicative Budget (Ksh. M)
Indicators to SDG Year 1 Year 2 Year 3 Year 4 Year 5
Targets Target Cost Target Cost Target Cost Target Cost Target Cost Total
Budget
Programme Name: General Administration, Planning and Support Services
Objective: To provide effective general administration planning and support service
Outcome: Efficient Service Delivery and Improved Working Environment
General Operational capacity enhanced No. of staff in post 63 56.2 30 27.0 30 27.0 30 27.0 30 27.0 164.2
administration (including promotions)
No. of TNA reports 1 8.0 1 8.0 1 8.0 1 8.0 1 8.0 40.0
prepared, submitted and
implemented
No of committees and 7 15.0 3 6.4 3 6.4 3 6.4 3 6.4 40.6
boards capacitated
No. of machinery procured 3 18.0 6 3.0 6 3.0 6 3.0 0 0.0 27.0
Utility costs 12 10.0 2 2.0 2 2.0 2 2.0 2 2.0 18.0
No. of assorted ICT tools 30 6.7 10 2.3 10 2.3 10 2.3 10 2.4 16.0
and equipment
No. of assorted physical 20 2.3 14 1.5 12 1.5 10 1.3 10 1.7 8.2
planning tools and
equipment acquired
No. of assorted survey tools 25 48.0 3 5.0 3 5.0 4 7.0 3 5.9 70.9
and equipment acquired
No. of asset reports prepared 1 3.0 1 3.0 1 3.0 1 3.0 1 3.0 15.0
and updated
Planning and Performance management No of Signed overall 1 0.7 1 0.7 1 0.7 1 0.7 1 0.7 3.5
Support services strengthened Performance Contracts
No. of progress reports 1 0.5 1 0.5 1 0.5 1 0.5 1 2.0
prepared
No. of policies developed 6 12.0 4 6.0 4 6.0 4 6.0 4 6.0 36.0
No. of Bills developed 3 20.0 4 12.0 4 12.0 4 12.0 4 12.0 68.0
No. of plans prepared 3 0.7 3 0.7 3 0.7 3 0.7 3 0.7 3.5
(procurement, work plans
and budgets)
No. of dispute resolution 1 1.0 0 0.0 0 0.0 0 0.0 0 0.0 1.0
frameworks
124
Sub programme Key Output Key Performance Linkages Planned Targets and Indicative Budget (Ksh. M)
Indicators to SDG Year 1 Year 2 Year 3 Year 4 Year 5
Targets Target Cost Target Cost Target Cost Target Cost Target Cost Total
Budget
No of sensitization forums 6 0.8 6 0.8 6 0.8 6 0.8 6 0.8 4.0
on ethics and integrity
undertaken
No of disaster risk strategies 1 0.3 1 0.3 1 0.3 1 0.3 1 0.3 1.5
developed and approved
Monitoring and Evaluation 5 0.6 5 0.6 5 0.6 5 0.6 5 0.6 3.0
SUB TOTAL 203.8 79.8 79.8 81.6 77.5 522.4
Programme Name: Land Use Planning
Objective: To provide a spatial framework that will guide and coordinate land use development for sustainable livelihood
Outcome: Well Planned Land and Urban Areas for Sustainable Development of The County
Land Use Land use plans developed and No. of County Spatial Plans SDG- 0 0.0 0 0.0 0 0.0 0 0.0 1 43.4 43.4
Planning approved reviewed 11.A,
No. of Municipality plans 11.3,11.7 2 0.0 2 0.0 2 0.0 2 0.0 2 0.0 0.0
prepared=Duplicated
No. of Town plans 3 0.0 1 0.0 0 0.0 0 0.0 0 0.0 0.0
prepared=Duplicate
No of market centre 2 20.0 1 10.0 1 10.0 1 10.0 1 10.0 60.0
physical and land use plans
prepared
No. of rural Market layout 3 9.0 6 12.0 6 12.0 6 12.0 6 12.0 57.0
plans prepared
No of public utility land use 15 7.5 7 3.5 7 3.5 7 3.5 3 1.7 19.7
plans prepared
No. of reports prepared and 4 1.0 4 1.0 4 1.0 4 1.0 4 1.0 5.0
submitted on development
controls
No.of Yala Land Use Plans 1 0.0 1 0.0 0 0.0 0 0.0 0 0.0 0.0
validated and
implemented=Justify
Sub Total 37.5 26.5 26.5 26.5 68.1 185.1
Programme Name: County Land Administration and Surveying
Objective: To secure land for public use and investments, property boundaries of public plot, government houses and trading centres
Outcome: Reduced Land Conflicts and Improve Investor Confidence
Land Survey and Public land surveyed No. of public plots surveyed SDG-11.A, 15 3.0 5 1.0 5 1.0 5 1.0 5 1.0 7.0
mapping No. of Child open area 11.7, 16.3, 1 30.0 1 10.0 1 10.0 0 0.0 0 0.0 50.0
facilities developed for 16.7
nurturing care
No. of market centres 12 10.0 4 3.3 4 3.3 4 3.3 4 3.3 23.2
surveyed
No. of rural centres 12 9.0 6 4.5 6 4.5 6 4.5 6 4.5 27.0
surveyed
No. of public land and 4 4.0 4 4.0 4 4.0 4 4.0 4 4.0 20.0
community land boundaries
demarcated
125
Sub programme Key Output Key Performance Linkages Planned Targets and Indicative Budget (Ksh. M)
Indicators to SDG Year 1 Year 2 Year 3 Year 4 Year 5
Targets Target Cost Target Cost Target Cost Target Cost Target Cost Total
Budget
No of Topographic surveys 15 30.0 4 10.0 4 10.0 4 10.0 4 10.0 70.0
conducted
No of public spaces fenced 4 2.0 4 2.0 4 2.0 4 2.0 4 2.0 10.0
County Public Public land administered and Hectares(Ha) of land 5 30.0 3 19.2 3 19.2 3 19.2 2 11.0 98.6
Land managed acquired
Administration No. of parcels of land 100 12.0 40 4.8 40 4.8 40 4.8 40 4.8 31.2
repossessed
No. of land committees 4 9.0 3 7.0 0 0.0 0 0.0 0 0.0 16.0
established and
operationalized
% of land disputes resolved 100 7.0 50 3.5 50 3.5 50 3.7 50 3.5 21.2
No. of sensitization forums 12 6.0 3 1.5 3 1.5 3 1.5 3 1.5 12.0
held on land matters
No. of title deeds acquired 10 3.0 4 1.2 4 1.2 4 1.2 4 2.5 9.1
for public land
Valuation roll approved and 1 20.0 0 0.0 0 0.0 0 0.0 0 0.0 20.0
implemented
Supplementary valuation 0 0.0 1 2.0 1 2.0 1 2.0 1 2.0 8.0
roll prepared, approved and
implemented
No. of digital public land 1 20.0 1 2.0 1 2.0 1 2.0 1 2.0 28.0
databases developed and
updated
No of community lands 1 9.9 0 0.0 0 0.0 0 0.0 0 0.0 9.9
registered
No of leases processed 5 10.0 2 4.0 2 4.0 2 4.0 2 4.0 26.0
SUB TOTAL 214.9 80.0 73.0 63.2 56.1 487.2
Programme Name: Housing & Urban Development
Objective: To provide adequate, affordable, decent housing and quality estates management services
Outcome: Delivery of Adequate, Secure, Decent and Affordable Housing Units to All
Housing Housing infrastructure developed No. of housing Master Plans SDG-11.1 2 20.0 1 10.0 1 10.0 1 10.0 1 10.0 60.0
development prepared
Hectares(Ha) of land 1 20.0 1 20.0 1 20.0 1 20.0 1 20.0 100.0
purchased for construction
of housing units
No. of housing units 100 0.0 100 0.0 100 0.0 100 0.0 100 0.0 0.0
constructed=Duplication
No of Appropriate Building 1 50.0 1 50.0 0 0.0 0 0.0 0 0.0 100.0
Technology (ABT)
Machines procured and
maintained
Estates developed and managed No. of government housing 4 4.0 5 5.0 5 5.0 5 5.0 5 5.0 24.0
units/offices renovated
State Officers residence 2 80.0 0 0.0 0 0.0 0 0.0 0 0.0 80.0
126
Sub programme Key Output Key Performance Linkages Planned Targets and Indicative Budget (Ksh. M)
Indicators to SDG Year 1 Year 2 Year 3 Year 4 Year 5
Targets Target Cost Target Cost Target Cost Target Cost Target Cost Total
Budget
(Governors and Deputy
Governors)
No of Office blocks 1 400.0 0 0.0 0 0.0 1 20.0 1 20.0 440.0
constructed (County
Headquarters’ and sub
county HQ)
Km of storm water drainage 1 10.0 2 20.0 2 20.0 2 20.0 2 20.0 90.0
constructed
No of septic tanks 1 5.0 1 5.0 1 5.0 1 5.0 1 5.0 25.0
constructed
No. of Modern toilet 1 0.0 5 0.0 5 0.0 5 0.0 5 0.0 0.0
constructed=Justify
No of km Non-Motorized 1 10.0 1 10.0 1 10.0 1 10.0 1 10.0 50.0
Facilities constructed
Urban Urban Infrastructure improved No. of bus park SDG-11.2, 1 0.0 1 0.0 1 0.0 1 0.0 1 0.0 0.0
Development constructed=Duplication 11.3
No. of Km of urban access 2 20.0 1 10.0 1 10.0 1 10.0 1 10.0 60.0
roads maintained
No. Km of sewer line 1 0.0 1 0.0 1 0.0 1 0.0 1 0.0 0.0
improved=Duplication
No. of urban public spaces 1 10.0 1 10.0 1 10.0 1 10.0 1 10.0 50.0
(greening)
No of social halls 1 10.0 1 10.0 1 10.0 0 0.0 0 0.0 30.0
constructed
No of CCTV cameras 1 0.0 1 0.0 1 0.0 1 0.0 1 0.0 0.0
installed=Targets
No of billboards erected 1 5.0 1 4.0 1 4.0 1 4.0 1 3.2 20.2
urban management structures Municipal Boards 2 0.0 2 0.0 2 0.0 2 0.0 2 0.0 0.0
established and
operationalized=Justify
Town committees 4 0.0 6 0.0 8 0.0 10 0.0 12 0.0 0.0
established and
operationalized=Justify
Affordable Housing: Siaya 0.0 0.0
and Bondo
Facilitating Infrastructure 0.0 0.0
for Lake Kanyaboli Eco
City
No. of urban areas conferred 12 11.5 10 10.0 10 10.0 10 10.0 10 10.0 51.5
Sub Total 655.5 164.0 114.0 124.0 123.2 1,180.7
Grand Total 1,111.6 350.3 293.3 295.3 324.9 2,375.4
Siaya Municipality
127
Sub programme Key Output Key Performance Linkages to SDG Planned Targets and Indicative Budget (Ksh. M)
Indicators Targets Year 1 Year 2 Year 3 Year 4 Year 5
Target Cost Target Cost Target Cost Target Cost Target Cost Total
Budget
(KSh.
M)*
Programme Name: General Administration, Planning and Support Services
Objective: To provide effective general administration planning and support service
Outcome: Efficient Service Delivery and Improved Working Environment
General Enhanced staff No. of staff in-post 1b 119 10.0 150 10.0 200 10.0 250 20.0 300 10.0 60.0
Administration capacity (including recruitment and
promotions)
No. of training needs 1 2.0 1 2.0 1 2.0 1 2.0 1 2.0 10.0
assessments reports
prepared, submitted and
implemented
No. of assorted office 15 2.5 15 2.5 15 2.5 15 2.5 15 2.5 12.5
equipment procured
No. of machinery acquired 1 14.0 20 2.0 0 0.0 0 0.0 0 0.0 16.0
and operational
Planning and Strengthened No. of office space 1 25.0 0 0.0 0 0.0 0 0.0 0 0.0 25.0
Support services performance constructed and equipped
management No of Signed Performance 1 1.0 1 1.0 1 1.0 1 1.0 1 1.0 5.0
Contracts
No. of policies developed 2 3.0 1 2.0 1 2.0 1 2.0 0 0.0 9.0
and approved
No. of by laws developed 1 2.0 1 2.0 1 2.0 1 2.0 0 0.0 8.0
and implemented
No. of plans prepared and 5 2.0 5 2.0 5 2.0 5 2.0 5 2.0 10.0
implemented
No of Pre-feasibility Studies 1 5.0 1 5.0 1 5.0 1 5.0 1 5.0 25.0
reports prepared and
implemented
No. of Municipal board 4 2.0 4 2.0 4 2.0 4 2.0 4 2.0 10.0
resolution reports
implemented
Resource Own Source No. of Automated Revenue 0 0.0 1 5.0 0 0.0 0 0.0 0 0.0 5.0
Mobilization revenue collection system installed
generated No. of report on revenue 1 2.0 1 2.0 1 2.0 1 2.0 1 2.0 10.0
stream mapping approved
Fees & charges book 1 2.0 1 2.0 1 2.0 1 2.0 1 2.0 10.0
prepared and approved
External donor No. of investment plans 1 3.0 1 1.0 1 1.0 1 1.0 1 1.0 7.0
support operational
SUB TOTAL 75.5 40.5 33.5 43.5 29.5 222.5
Programme 2 : Urban infrastructure development and management
Programme Objective: To develop urban infrastructure that will ensure a clean, orderly, secure, attractive and business friendly Municipilaty
Outcome: Improved growth and development of Siaya Municipality
128
Sub programme Key Output Key Performance Linkages to SDG Planned Targets and Indicative Budget (Ksh. M)
Indicators Targets Year 1 Year 2 Year 3 Year 4 Year 5
Target Cost Target Cost Target Cost Target Cost Target Cost Total
Budget
(KSh.
M)*
Urban Motorized and No. of parking bays 11.3 1 15.0 0 0.0 0 0.0 1 15.0 0 0.0 30.0
infrastructure non motorized constructed
development facilities No. of parking lanes marked 400 1.5 0 0.0 0 0.0 400 1.5 0 0.0 3.0
developed Km of non-motorized 1 0.0 1 0.0 1 0.0 1 0.0 1 0.0 0.0
transport constructed
Km of non-motrized 2 5.0 2 5.0 2 5.0 2 5.0 2 5.0 25.0
transport maintained
Km of urban access roads 1 5.0 1 5.0 1 5.0 1 5.0 1 5.0 25.0
upgraded to bitumen
Km of sewer line extended 1 5.0 1 5.0 1 5.0 1 5.0 1 5.0 25.0
Km of drainage system 1 2.0 1 2.0 1 2.0 1 2.0 1 2.0 10.0
maintained
No. of municipal yards and 0 0.0 1 5.0 0 0.0 0 0.0 0 0.0 5.0
stores operational
No. of road signage 20 1.0 20 1.0 20 1.0 20 1.0 20 1.0 5.0
developed
Siaya bus park redesigned, 1 10.0 1 5.0 1 5.0 1 5.0 1 5.0 30.0
completed and maintained
No. of Bodaboda shades 0 0.0 5 2.0 5 2.0 5 2.0 5 2.0 8.0
constructed
No. of Street named 30 6.0 0 0.0 0 0.0 0 0.0 0 0.0 6.0
No. of streets lights installed 20 40.0 0 0.0 0 0.0 0 0.0 0 0.0 40.0
No. of bill boards erected 10 10.0 0 0.0 0 0.0 10 10.0 0 0.0 20.0
Market Modern market 1 50.0 0 0.0 0 0.0 0 0.0 0 0.0 0.0
infrastructure constructed(phased)
development No. of high mast installed in 2 5.0 2 5.0 2 5.0 2 5.0 2 5.0 25.0
markets
No. of abattoirs constructed 1 5.0 0 0.0 1 3.0 0 0.0 0 0.0 8.0
and maintained
Disaster Fire stations constructed and 0 5.0 0 5.0 0 5.0 0 5.0 0 5.0 25.0
management & equipped
response No. of water hydrants 5 2.0 5 2.0 5 2.0 5 2.0 5 2.0 10.0
installed
No. of staff capacity built on 2 1.2 2 1.2 2 1.2 2 1.2 2 1.2 6.0
disaster response
SUB TOTAL 168.7 43.2 41.2 64.7 38.2 356.0
Programme 3: Environment and Social Services
Objective: To provide effective and efficient environmental and social services
Outcome: Quality environmental and social services within Siaya Municipality
Environment and Improved HA of land acquired for 11.6 4 3.0 0 3.0 0 0.0 0 0.0 0 0.0 6.0
Social Services environmental waste management
Services No. of waste management 2 3.0 20 1.0 1 1.0 1 2.0 1 1.0 8.0
129
Sub programme Key Output Key Performance Linkages to SDG Planned Targets and Indicative Budget (Ksh. M)
Indicators Targets Year 1 Year 2 Year 3 Year 4 Year 5
Target Cost Target Cost Target Cost Target Cost Target Cost Total
Budget
(KSh.
M)*
machinery acquired
No. of enforcement and 100 1.0 100 1.0 100 1.0 100 1.0 100 1.0 5.0
demolition tools procured
No. of waste management 300 2.0 300 2.0 300 2.0 300 2.0 300 2.0 10.0
tools procured (waste bins,
skimps, wheelbarrow, rakes)
No. of public cemetery 1 0.5 1 5.0 1 0.5 1 0.5 1 0.5 7.0
developed and maintained
No. of open spaces 1 3.0 1 3.0 1 3.0 1 3.0 1 3.0 15.0
rehabilitated and developed
No. of Green spaces 2 2.0 2 2.0 2 2.0 2 2.0 2 2.0 10.0
Maintained and Managed
No. of water points 0 0.0 1 1.5 1 1.5 1 1.5 1 1.5 6.0
established
No. of modern toilets 1 3.0 1 3.0 1 3.0 1 3.0 1 3.0 15.0
constructed
Social Welfare Social welfare office 0 0.0 1 5.0 0 0.0 0 0.0 0 0.0 5.0
services operational
enhanced No. of stadia maintained 0 0.0 1 5.0 1 5.0 1 5.0 1 5.0 20.0
No. of public gymnasium 0 0.0 1 5.0 0 0.0 0 0.0 0 0.0 5.0
equipped and maintained
No. of social hall (resource 0 0.0 2 2.0 0 0.0 0 0.0 0 0.0 2.0
centers and ICT
hubs)constructed
No. of outreach programmes 4 0.5 4 1.0 4 1.0 4 1.0 4 1.0 4.5
conducted
Sub Total 18.0 39.5 20.0 21.0 20.0 118.5
Grand Total 262.2 123.2 94.7 129.2 87.7 697.0
Bondo Municipality
Sub Key Output Key Performance Linkages to SDG Planned Targets and Indicative Budget (Ksh. M)
programme Indicators Targets Year 1 Year 2 Year 3 Year 4 Year
5
Targe Cos Targe Cos Targe Cos Targe Cos Targe Cos Total
t t t t t t t t t t Budget
(Ksh.
M)*
Programme Name: General Administration, Planning and Support Services
130
Sub Key Output Key Performance Linkages to SDG Planned Targets and Indicative Budget (Ksh. M)
programme Indicators Targets Year 1 Year 2 Year 3 Year 4 Year
5
Targe Cos Targe Cos Targe Cos Targe Cos Targe Cos Total
t t t t t t t t t t Budget
(Ksh.
M)*
Objective: To provide effective general administration planning and support service
Outcome: Efficient Service Delivery and Improved Working Environment
General Enhanced No. of staff in-post 1b 120 10.0 150 10.0 200 10.0 250 10.0 300 10.0 50.0
Administration staff (including recruitment
capacity and promotions)
No. of training needs 1 0.5 1 0.5 1 0.5 1 0.5 1 0.5 2.5
assessments reports
prepared, submitted and
implemented
No. of assorted office 30 1.0 20 1.0 15 1.0 15 1.0 15 1.0 5.0
equipment procured
No. of machinery 4 3.0 2 3.0 1 2.0 1 3.0 0 0.0 11.0
acquired and operational
Planning and Strengthened No. of office space 1 5.0 0 0.0 0 0.0 0 0.0 0 0.0 5.0
Support services performance constructed
management No of Signed 1 1.0 1 1.0 1 1.0 1 1.0 1 1.0 5.0
Performance Contracts
No. of policies developed 1 2.0 1 2.0 1 2.0 1 2.0 0 0.0 8.0
and approved
No. of bylaws developed 1 2.0 1 2.0 1 2.0 1 2.0 0 0.0 8.0
and implemented
No. of plans prepared and 5 2.0 5 2.0 5 2.0 5 2.0 5 2.0 10.0
implemented
No of Pre-feasibility 1 0.5 1 0.5 1 0.5 1 0.5 1 0.5 2.5
Studies reports prepared
and implemented
No. of Municipal board 4 0.5 4 0.5 4 0.5 4 0.5 4 0.5 2.5
resolution reports
implemented
Resource Own Source No. of Automated 0 0.0 1 5.0 0 0.0 0 0.0 0 0.0 5.0
Mobilization revenue Revenue collection
generated system installed
131
Sub Key Output Key Performance Linkages to SDG Planned Targets and Indicative Budget (Ksh. M)
programme Indicators Targets Year 1 Year 2 Year 3 Year 4 Year
5
Targe Cos Targe Cos Targe Cos Targe Cos Targe Cos Total
t t t t t t t t t t Budget
(Ksh.
M)*
No. of report on revenue 1 0.5 1 0.5 1 0.5 1 0.5 1 0.5 2.5
stream mapping approved
Fees & charges book 1 0.5 1 0.5 1 0.5 1 0.5 1 0.5 2.5
prepared and approved
External No. of investment plans 1 0.5 0 0.0 0 0.0 0 0.0 0 0.0 0.5
donor operational
support
Sub Total 29.0 28.5 22.5 23.5 16.5 120.0
Programme 2 : Urban infrastructure development and management
Programme Objective: To develop urban infrastructure that will ensure a clean, orderly, secure, attractive and business friendly Municipality
Outcome: Improved growth and development of Bondo Municipality
Urban Motorized No. of parking bays 11.3 0 0.0 0 0.0 1 0.0 0.0
infrastructure and non constructed
development motorized No. of parking lanes 500 1.0 0 0.0 0 0.0 500 1.0 0 0.0 2.0
facilities marked
developed Km of non-motorized 0 0.0 0 0.0 0 0.0 0 0.0 0 0.0 0.0
transport constructed
Km of urban access roads 0 0.0 0 0.0 0 0.0 0 0.0 0 0.0 0.0
upgraded to bitumen
Km of sewer line 0 0.0 0 0.0 0 0.0 0 0.0 0 0.0 0.0
extended
No. of municipal yards 0 0.0 1 2.0 0 0.0 0 0.0 0 0.0 2.0
and stores operational
No. of road signage 20 0.5 20 0.5 20 0.5 20 0.5 20 0.5 2.5
developed
New Bus park designed 1 10.0 1 5.0 1 5.0 1 2.5 1 2.5 25.0
and constructed including
purchase of land
No. of Bodaboda shades 5 2.0 5 2.0 5 2.0 5 2.5 5 2.5 11.0
constructed
No. of Street named 15 3.0 0 0.0 0 0.0 0 0.0 0 0.0 3.0
132
Sub Key Output Key Performance Linkages to SDG Planned Targets and Indicative Budget (Ksh. M)
programme Indicators Targets Year 1 Year 2 Year 3 Year 4 Year
5
Targe Cos Targe Cos Targe Cos Targe Cos Targe Cos Total
t t t t t t t t t t Budget
(Ksh.
M)*
No. of streets lights 25 2.0 25 2.0 25 5.0 0 0.0 0 0.0 9.0
installed
No. of bill boards erected 0 0.0 0 0.0 0 0.0 0 0.0 0 0.0 0.0
Market No. of modern markets 0 0.0 0 0.0 0 0.0 0 0.0 0 0.0 0.0
infrastructur constructed(phased)
e No. of high mast installed 2 5.0 2 5.0 2 5.0 2 5.5 2 5.5 26.0
development in markets
No. of abattoirs 0 0.0 1 2.0 1 2.0 1 2.0 1 2.0 8.0
constructed and
maintained
Disaster No. of fire stations 0 0.0 0 0.0 0 0.0 0 0.0 0 0.0 0.0
management constructed and equipped
& response No. of water hydrants 5 2.0 5 2.0 5 2.0 5 2.5 5 2.5 11.0
installed
No. of staff capacity built 2 1.2 2 1.2 2 1.2 2 1.2 2 1.2 6.0
on disaster response
Sub Total 26.7 21.7 22.7 17.7 16.7 105.5
Programme 3: Environment and Social Services
Objective: To provide clean, effective and efficient environmental and social services
1.7
Environment Improved HA of land acquired for 11.6 1 1.3 0 0.0 0 0.0 0 0.0 0 0.0 1.3
and Social environment waste management
Services al Services No. of waste 1 3.0 1 3.0 0 0.0 0 0.0 0 0.0 6.0
management machinery
acquired
No. of enforcement and 100 0.5 100 0.5 100 0.5 100 0.5 100 0.5 2.5
demolition tools procured
No. of waste 400 3.0 400 3.0 300 2.0 300 2.5 300 2.5 13.0
management tools
procured (waste bins,
skimps, wheelbarrow,
133
Sub Key Output Key Performance Linkages to SDG Planned Targets and Indicative Budget (Ksh. M)
programme Indicators Targets Year 1 Year 2 Year 3 Year 4 Year
5
Targe Cos Targe Cos Targe Cos Targe Cos Targe Cos Total
t t t t t t t t t t Budget
(Ksh.
M)*
rakes)
No. of public cemetery 1 5.0 1 3.0 1 0.5 1 0.5 1 0.5 9.5
developed and
maintained
No. of open spaces 1 2.0 1 2.0 1 2.0 1 2.0 1 2.0 10.0
rehabilitated and
developed
No. of Green spaces 1 1.0 1 1.0 1 1.0 1 1.0 2 1.0 5.0
Maintained and Managed
No. of water points 0 0.0 1 1.5 1 1.5 1 1.5 1 1.5 6.0
established
No. of modern toilets 1 1.0 1 1.0 1 1.0 1 1.0 1 1.0 5.0
constructed
Social social welfare office 0 0.0 1 5.0 0 0.0 0 0.0 0 0.0 5.0
Welfare operational
services No. of stadia maintained 0 0.0 0 0.0 0 0.0 0 0.0 0 0.0 0.0
enhanced No. of public 0 0.0 1 5.0 0 0.0 0 0.0 0 0.0 5.0
gymnasium equipped and
maintained
No. of social hall 0 0.0 0 0.0 0 0.0 0 0.0 0 0.0 0.0
(resource centres and ICT
hubs)constructed
No. of outreach 0 0.0 0 0.0 0 0.0 0 0.0 0 0.0 0.0
programmes conducted
Sub Total 16.8 25.0 8.5 9.0 9.0 68.3
Grand Total 72.5 75.2 53.7 50.2 42.2 293.8
Ugunja Municipality
Sub programme Key Output Key Performance Indicators Linkages to SDG Targets Planned Targets and Indicative Budget (Ksh. M)
Year 1 Year 2 Year 3 Year 4 Year 5
134
Target Cost Target Cost Target Cost Target Cost Target Cost Total
Cost
Programme Name: General Administration, Planning and Support Services
Objective: To provide effective general administration planning and support service
Outcome: Efficient Service Delivery and Improved Working Environment
General Enhanced staff No. of staff in-post (including 1b 120 10.0 150 10.0 200 10.0 250 10.0 300 10.0 50.0
Administration capacity recruitment and promotions)
No. of training needs assessments 1 0.5 1 0.5 1 0.5 1 0.5 1 0.5 2.5
reports prepared, submitted and
implemented
No. of assorted office equipment 30 1.0 20 1.0 15 1.0 15 1.0 15 1.0 5.0
procured
No. of machinery acquired and 4 3.0 2 3.0 1 2.0 1 3.0 0 0.0 11.0
operational
Planning and Support Strengthened No. of office space constructed 1 5.0 0 0.0 0 0.0 0 0.0 0 0.0 5.0
services performance No of Signed Performance 1 1.0 1 1.0 1 1.0 1 1.0 1 1.0 5.0
management Contracts
No. of policies developed and 1 2.0 1 2.0 1 2.0 1 2.0 0 0.0 8.0
approved
No. of bylaws developed and 1 2.0 1 2.0 1 2.0 1 2.0 0 0.0 8.0
implemented
No. of plans prepared and 5 2.0 5 2.0 5 2.0 5 2.0 5 2.0 10.0
implemented
No of Pre-feasibility Studies 1 0.5 1 0.5 1 0.5 1 0.5 1 0.5 2.5
reports prepared and implemented
No. of Municipal board resolution 4 0.5 4 0.5 4 0.5 4 0.5 4 0.5 2.5
reports implemented
Resource Own Source No. of Automated Revenue 0 0.0 1 5.0 0 0.0 0 0.0 0 0.0 5.0
Mobilization revenue collection system installed
generated No. of report on revenue stream 1 0.5 1 0.5 1 0.5 1 0.5 1 0.5 2.5
mapping approved
Fees & charges book prepared and 1 0.5 1 0.5 1 0.5 1 0.5 1 0.5 2.5
approved
External donor No. of investment plans 1 0.5 0 0.0 0 0.0 0 0.0 0 0.0 0.5
support operational
Sub Total 29.0 28.5 22.5 23.5 16.5 120.0
Programme 2 : Urban infrastructure development and management
Programme Objective: To develop urban infrastructure that will ensure a clean, orderly, secure, attractive and business friendly Municipality
Outcome: Improved growth and development of Bondo Municipality
Urban infrastructure Motorized and No. of parking bays constructed 11.3 0 0.0 0 0.0 1 0.0 0.0
development non-motorized No. of parking lanes marked 500 1.0 0 0.0 0 0.0 500 1.0 0 0.0 2.0
facilities Km of non-motorized transport 0 0.0 0 0.0 0 0.0 0 0.0 0 0.0 0.0
developed constructed
Km of urban access roads 0 0.0 0 0.0 0 0.0 0 0.0 0 0.0 0.0
upgraded to bitumen
Km of sewer line extended 0 0.0 0 0.0 0 0.0 0 0.0 0 0.0 0.0
No. of municipal yards and stores 0 0.0 1 2.0 0 0.0 0 0.0 0 0.0 2.0
operational
135
Sub programme Key Output Key Performance Indicators Linkages to SDG Targets Planned Targets and Indicative Budget (Ksh. M)
Year 1 Year 2 Year 3 Year 4 Year 5
Target Cost Target Cost Target Cost Target Cost Target Cost Total
Cost
No. of road signage developed 20 0.5 20 0.5 20 0.5 20 0.5 20 0.5 2.5
New Bus park designed and 1 10.0 1 5.0 1 5.0 1 2.5 1 2.5 25.0
constructed including purchase of
land
No. of Bodaboda shades 5 2.0 5 2.0 5 2.0 5 2.5 5 2.5 11.0
constructed
No. of Street named 15 3.0 0 0.0 0 0.0 0 0.0 0 0.0 3.0
No. of streets lights installed 25 2.0 25 2.0 25 5.0 0 0.0 0 0.0 9.0
No. of bill boards erected 0 0.0 0 0.0 0 0.0 0 0.0 0 0.0 0.0
Market No. of modern markets 0 0.0 0 0.0 0 0.0 0 0.0 0 0.0 0.0
infrastructure constructed(phased)
development No. of high mast installed in 2 5.0 2 5.0 2 5.0 2 5.5 2 5.5 26.0
markets
No. of abattoirs constructed and 0 0.0 1 2.0 1 2.0 1 2.0 1 2.0 8.0
maintained
Disaster No. of fire stations constructed and 0 0.0 0 0.0 0 0.0 0 0.0 0 0.0 0.0
management equipped
& response No. of water hydrants installed 5 2.0 5 2.0 5 2.0 5 2.5 5 2.5 11.0
No. of staff capacity built on 2 1.2 2 1.2 2 1.2 2 1.2 2 1.2 6.0
disaster response
Sub Total 26.7 21.7 22.7 17.7 16.7 105.5
Programme 3: Environment and Social Services
Objective: To provide clean, effective and efficient environmental and social services
Outcome: Quality environmental and social services within Bondo Municipality
Environment and Improved HA of land acquired for waste 11.6 1 1.3 0 0.0 0 0.0 0 0.0 0 0.0 1.3
Social Services environmental management
Services No. of waste management 1 3.0 1 3.0 0 0.0 0 0.0 0 0.0 6.0
machinery acquired
No. of enforcement and demolition 100 0.5 100 0.5 100 0.5 100 0.5 100 0.5 2.5
tools procured
No. of waste management tools 400 3.0 400 3.0 300 2.0 300 2.5 300 2.5 13.0
procured (waste bins, skimps,
wheelbarrow, rakes)
No. of public cemetery developed 1 5.0 1 3.0 1 0.5 1 0.5 1 0.5 9.5
and maintained
No. of open spaces rehabilitated 1 2.0 1 2.0 1 2.0 1 2.0 1 2.0 10.0
and developed
No. of Green spaces Maintained 1 1.0 1 1.0 1 1.0 1 1.0 2 1.0 5.0
and Managed
No. of water points established 0 0.0 1 1.5 1 1.5 1 1.5 1 1.5 6.0
No. of modern toilets constructed 1 1.0 1 1.0 1 1.0 1 1.0 1 1.0 5.0
Social Welfare social welfare office operational 0 0.0 1 5.0 0 0.0 0 0.0 0 0.0 5.0
services No. of stadia maintained 0 0.0 0 0.0 0 0.0 0 0.0 0 0.0 0.0
136
Sub programme Key Output Key Performance Indicators Linkages to SDG Targets Planned Targets and Indicative Budget (Ksh. M)
Year 1 Year 2 Year 3 Year 4 Year 5
Target Cost Target Cost Target Cost Target Cost Target Cost Total
Cost
enhanced No. of public gymnasium 0 0.0 1 5.0 0 0.0 0 0.0 0 0.0 5.0
equipped and maintained
No. of social hall (resource centres 0 0.0 0 0.0 0 0.0 0 0.0 0 0.0 0.0
and ICT hubs) constructed
No. of outreach programmes 0 0.0 0 0.0 0 0.0 0 0.0 0 0.0 0.0
conducted
Sub Total 16.8 25.0 8.5 9.0 9.0 68.3
Grand Total 72.5 75.2 53.7 50.2 42.2 293.8
137
4.1.7 Trade, Industrialization and Tourism
Sector Introduction
The sector envisions sustainable enterprises for economic growth through development and
promotion of Trade, Industrialization and Tourism. The sector goals are to: Provide an enabling
environment that facilitates competitive trade, investment and industrialization; Market Siaya
county as a premier tourist destination. The sector is composed of two sub sectors namely;
Trade and Industrialization: the sub-sector mandates are: Formulation and implementation of
Enterprise and Industrial Development policies and regulations, Improvement of business and
entrepreneurial environment, Promotion of cooperative development and Marketing, Promotion
of fair-trade practices and consumer protection, Promotion and development of the Micro and
Small Enterprises sector, Improvement of solid waste management in market centres and
Alcoholic Drinks Control and drug abuse.
Tourism: Development and promotion of tourism industry in the county
From the analysis of development issues, the following priorities and strategies have been
proposed for implementation.
Goal Priorities Strategies
Provide an Improve Improve market infrastructure (Child Friendly Infrastructure)
enabling business Build capacity of MSMEs and Increase access to credit
environment that environment Provide market linkages
facilitates Secure markets
competitive trade, Strengthen waste management
investment and Strengthen cooperative movement/ Financing of Cooperative Societies
industrialization
Strengthen enforcement of legal metrology legislations
Develop manufacturing/processing industries
Strengthen market surveillance
Strengthen enforcement of Siaya County Alcoholic Drinks Act 2016
Develop relevant policies and legislations
Increase Develop tourist attraction sites
tourist Promote cultural events
arrivals promote conference tourism
Promote water sports tourism
Develop relevant policies and legislations
Strengthen tourism product marketing
Leverage on technology in tourism promotion
Develop database of tourists and recreational sites
Develop Develop sports infrastructure in the county
sports and
Provide sports equipment
talents
Talent identification, training and sports promotion
138
Sector Programmes
The sector plans to provide an enabling environment that facilitates competitive trade, investment and industrialization. This will be
realized through; establishment of cooperative and enterprise development funds; development of market infrastructure especially
high mast; establishment of an industrial park; establishment of legal metrology laboratory; construction of rehabilitation centre and
construction of solid waste recycling plant. The sector also plans to market Siaya county as a premier tourist destination through;
development of Siaya County Museum; completion of Siaya stadium and development of Migwena sports and cultural centre;
promote development of sports tourism, high end hotels and conference facilities within thelake region tourism circuit.
Sub - Key Output Key Performance Linkage Planned targets and indicative budgets in KSh M Total
programme Indicator s to 2023-2024 2024-2025 2025-2026 2026-2027 2027-2028 Budge
SDGs Target Cost Target Cost Target Cost Target Cost Target Cost t in
targets Ksh M
Programme 1: Trade Development and Promotion
Objective: To provide an enabling environment that facilitates a competitive local, regional and global trade and investment
Outcome: A conducive environment for trade
SP: 1 Expanded business Updated County SDG 8.2, 1 1.0 0 0.0 1 1.0 0 0.0 1 1.0 3.0
ventures and Business Mapping 8.3, 8,a
Training and innovations No. of exhibitions 2 2.0 2 2.0 2 2.0 2 2.0 2 2.0 10.0
Capacity and trade fairs held
Building for No. of exhibitions 3 3.0 3 3.0 3 3.0 3 3.0 3 3.0 15.0
SMEs and trade fairs
attended
No. of capacity 4 2.0 4 2.0 4 2.0 4 2.0 4 2.0 10.0
building for a reports
No. of round table 4 2.5 4 2.5 4 2.5 4 2.5 4 2.5 12.5
meetings held reports
SP:2 Market Improved market No. of markets with SDG 9.1, 10 25.0 6 15.0 5 12.5 5 12.5 0 0.0 65.0
infrastructure infrastructure lighting system 9.a
Development Highmast
No. of Solar Lamps 5 1.5 5 1.5 5 1.5 5 1.5 5 1.5 7.5
No. of Market 5 0.5 5 0.5 5 0.5 5 0.5 5 0.5 2.5
management
Committees
established and
operationalised
No. of Sanitation 10 0.5 10 0.5 10 0.5 10 0.5 10 0.5 2.5
facilities (Latrines)
Constructed in
Markets.
No. of sanitation 3 9.0 0 0.0 3 9.0 3 9.0 3 9.0 36.0
facilities (Modern
139
Sub - Key Output Key Performance Linkage Planned targets and indicative budgets in KSh M Total
programme Indicator s to 2023-2024 2024-2025 2025-2026 2026-2027 2027-2028 Budge
SDGs Target Cost Target Cost Target Cost Target Cost Target Cost t in
targets Ksh M
Washrooms)
constructed in
markets.
No. of modern 2 30.0 2 30.0 0 0.0 0 0.0 2 30.0 90.0
Market Shades
constructed.
No. of Highmasts 30 4.5 30 4.5 30 4.5 30 4.5 30 4.5 22.5
and solar lamps
repaired
No. of Boda boda 7 3.5 7 3.5 7 3.5 7 3.5 7 3.5 17.5
sheds Constructed
No. of Market 4 6.0 4 6.0 4 6.0 4 6.0 4 6.0 30.0
infrastructures
improved
No. of Market 3 15.0 3 15.0 3 15.0 3 15.0 3 15.0 75.0
Shades Constructed.
Enterprise Improved access to No of SMEs SDG 9.3 0 0.0 30 45.0 25 60.0 90 60.0 60 90.0 255.0
Development credit facility accessing the
Fund Enterprise
Development Fund
Market Solid Improved sanitation No. of Market SDG 150 30.0 150 30.0 150 30.0 150 30.0 150 30.0 150.0
Waste in urban and market cleaned 11.6,
Management centres No of dump sites 12.5 2 4.0 2 4.0 1 2.0 1 2.0 0 0.0 12.0
acquired
No. of clean up days 12 0.6 12 0.6 12 0.6 12 0.6 12 0.6 3.0
conducted
No. of NEMA 5 2.5 5 2.5 5 2.5 5 2.5 5 2.5 12.5
approved waste Bins
Installed
No. of PPEs acquired 2,100 4.9 2,100 4.9 2,100 4.9 2,100 4.9 2,100 4.9 24.5
No. self -loading 1 7.3 0 0.0 1 7.3 1 7.3 0 0.0 21.8
trucks acquired
No. of Tractors 1 2.5 1 2.5 1 2.5 1 2.5 1 2.5 12.5
Tonnage of refuse 1,500,00 10.0 1,500,00 10.0 1,500,00 10.0 1,500,00 10.0 1,500,00 10.0 50.0
collected and 0 0 0 0 0
dumped
Sub Total 167. 185. 183. 182. 221. 940.3
8 5 3 3 5
Programme 2: Fair Trade Practices and Consumer Protection Services
Objective: To enforce compliance with weights and measures Act Cap 513 and other subsidiary legislations
Outcome: Improved Consumer confidence on value for money
SP 1. Improved Legal No. of assorted legal 8.3, 8.a 3 6.9 0 0.0 3 7.2 0 0.0 3 7.5 21.6
Standards Metrology Services Metrology Standards & 17.10
Administratio Acquired
140
Sub - Key Output Key Performance Linkage Planned targets and indicative budgets in KSh M Total
programme Indicator s to 2023-2024 2024-2025 2025-2026 2026-2027 2027-2028 Budge
SDGs Target Cost Target Cost Target Cost Target Cost Target Cost t in
targets Ksh M
n and % of Metrology lab SDG 8.a 0 0.0 60 11.0 40 7.0 0 0.0 0 0.0 18.0
Conformity constructed and & 17.10
operationalised
(Phased approach)
% of traders’ SDG 8.a, 100 3.5 100 3.5 100 3.5 100 3.5 100 3.5 17.5
complying with legal 16.b &
metrology legislation 17.10
No of reports on SDG 4 1.4 4 1.5 4 1.5 4 1.6 4 1.6 7.5
awareness campaign 17.18
foras on legal 17.9
metrology
legislations
No. of market SDG 4 2.0 4 2.0 4 2.0 4 2.0 4 2.0 10.0
surveillance reports 10.3 16.b
on legal metrology
legislations (Test
purchases,
Inspections,
investigations and
prosecution)
Sub Total 13.8 18.0 21.2 7.1 14.6 74.6
Programme Name 3: Co-operative Development & Management
Objective: To provide an enabling environment that facilitates sustainable growth of cooperative sub sector for socio-economic development.
Outcome: Expanded cooperative business and a vibrant cooperative subsector
Cooperative Improved No of cooperative SDG 40 0.3 40 0.3 43 0.3 44 0.3 45 0.3 1.6
governance, cooperative audit reports 10.3
regulation and governance produced
supervision No. of Inspections 12 0.5 12 0.5 12 0.5 12 0.5 12 0.5 2.5
and inquiries
Co-operative Enhanced value No. of Coops SDG 9.b 12 2.0 13 2.3 13 2.3 17 2.7 20 3.0 12.3
Marketing And addition in adopting value
Value Addition Cooperative addition
Societies No of sensitization SDG 4 1.4 4 1.4 4 1.4 4 1.4 4 1.4 7.0
reports 17.9
Market survey report SDG 12 1 1.5 1 1.5 1 1.5 1 1.5 1 1.5 7.5
Access to affordable No. of Cooperative SDG 9.3 7 42.0 7 42.0 7 42.0 7 42.0 10 60.0 228.0
credi Societies accessing
affordable credit
County Enhanced capacity in No. of new SDG 6 0.7 6 0.7 6 0.7 6 0.7 6 0.7 3.5
Cooperative cooperative societies cooperatives 17.9
Extension promoted
Services No of new dormant 5 0.8 5 0.8 5 0.8 5 0.8 5 0.8 4.0
societies revitalized
No. of Cooperative 12 1.0 12 1.0 12 1.0 12 1.0 12 1.0 5.0
141
Sub - Key Output Key Performance Linkage Planned targets and indicative budgets in KSh M Total
programme Indicator s to 2023-2024 2024-2025 2025-2026 2026-2027 2027-2028 Budge
SDGs Target Cost Target Cost Target Cost Target Cost Target Cost t in
targets Ksh M
Awareness
campaigns reports
No of Training 12 1.6 12 1.6 12 1.6 12 1.6 12 1.6 8.0
reports
Annual Report on 1 0.5 1 0.5 1 0.5 1 0.5 1 0.5 2.5
cooperatives
submitted
Sub Total 52.3 52.6 52.6 53.0 71.3 281.9
Programme Name 4: Alcoholic Drinks Control
Objective: To control and manage alcoholic drinks and drugs
Outcome: Improved control and management of alcoholic drinks and drug abuse
Market surveillance SDG 16b 6 0.6 6 0.6 6 0.6 6 0.6 6 0.6 3.1
report onalcoholic
drinks control
No. training reports SDG 12 3.0 12 3.0 12 3.0 12 3.0 12 3.0 15.0
No. of awareness 17.9 4 1.2 4 1.2 4 1.2 4 1.2 4 1.2 6.0
campaigns r
No. of Rehabilitation SDG 0 0.0 0 0.0 1 8.0 0 0.0 0 0.0 8.0
Centre constructed 17.1
Sub Total 4.8 4.8 12.8 4.8 4.8 32.1
Programme Name 5: Industrial Development and Promotion
Objective: To provide an enabling environment for sustainable industrial development and Investment
Outcome: Economic and job creation
Industrial Expanded Industrial No. of Feasibility SDG 9.4 1 8.0 0 0.0 0 0.0 0 0.0 0 0.0 8.0
Development Development and Study reports on
and Investment promotion Industrial Park,
Industrial Park, Land SDG 0.0 0 0.0 0 0.0 1 52.0 1 20.0 72.0
purchased and 15.4.2
developed
Investment SDG 1 2.5 2 2.5 2 2.5 2 2.5 2 2.5 12.5
conferences attended 17.5
Investment 1 2.5 2 2.5 2 2.5 2 2.5 2 2.5 12.5
conferences held
No. of Industrial SDG 9.3 1 2.0 0 0.0 1 2.5 0 0.0 1 3.0 7.5
mapping conducted
No. of incubations SDG 8.2 6 24.0 0 0.0 0 0.0 6 24.0 2 10.0 58.0
centres established
Solid Waste SDG 0 0.0 1 50.0 1 0.0 0 0.0 0 0.0 50.0
recycling plant 12.4.2,
established 6,a
No of industries SDG 0 0.0 0 0.0 1 50.0 0 0.0 1 100. 150.0
established (Fish 9.2.1 0
Processing, sugar,
rice, Fruit)
142
Sub - Key Output Key Performance Linkage Planned targets and indicative budgets in KSh M Total
programme Indicator s to 2023-2024 2024-2025 2025-2026 2026-2027 2027-2028 Budge
SDGs Target Cost Target Cost Target Cost Target Cost Target Cost t in
targets Ksh M
No. of Micro Small SDG 8.2 0 0.0 0 0.0 13 52.0 20 80.0 0 0.0 132.0
& Medium
Enterprises start ups
facilitated
Sub Total 39.0 55.0 109. 161. 138. 502.5
5 0 0
Programme Name 6: Tourism Development and promotion
Objective: To position siaya county as a leading regional tourist attraction
Outcome: Economic growth and job creation
Tourism Functional Siaya Develop SCM SDG 1 10.0 0 0.0 0 0.0 0 0.0 0 0.0 10.0
Infrastructure County Museum architectural plans 11.4
Development (SCM) Review & register
SCM architectural
plans Construction of
SCM. Equipping &
operationalisation of
SCM
Got Ramogi Forest Got Ramogi Cultural SDG 1 5.0 1 15.0 1 23.0 1 10.0 1 30.0 83.0
Development Centre. Develop 11.4
design for conference
facility. Construction
of conference
facility. Equipping &
operationalisation of
cultural cenre
Got Ramogi Construction of Got SDG 9.5 1 6.0 1 20.0 1 3.0 1 10.0 1 30.0 69.0
KOpondo Ramogi Heritage &
Development Cultural Centre -
Kopondo Grounds
With all proposed
facilities
Development of No. of functional SDG 9.5 1 10.0 1 10.0 0 0.0 0 0.0 0 0.0 20.0
Odera Akang’o Cultural heritage,
cultural and heritage performance and
centre information centre
constructed &
operationalized
(Phased)
Tourism Mapping and No. of reports of SDG 1 1.5 1 1.5 1 1.5 1 1.5 1 1.5 7.5
Development & profiling of tourism tourist facilities 14.2
Promotion sites mapped using GPRS.
Conservation of
natural sites
No. of reports 14.2 1 1.5 1 1.5 1 1.5 1 1.5 1 1.5 7.5
prepared heritage
143
Sub - Key Output Key Performance Linkage Planned targets and indicative budgets in KSh M Total
programme Indicator s to 2023-2024 2024-2025 2025-2026 2026-2027 2027-2028 Budge
SDGs Target Cost Target Cost Target Cost Target Cost Target Cost t in
targets Ksh M
sites gazetted &
branded annually
Tourism product 1 3.0 1 3.0 1 3.0 1 3.0 1 3.0 15.0
development annual
report prepared
Homestay Concept No. homes identified 11.4 1 2.0 1 2.0 1 2.0 1 2.0 1 2.0 10.0
Development & profiled. Capacity
Building for
practitioners
Marketing of
homestays
Branded County Branding of signages 11.4 2 7.0 3 7.5 0 0.0 0 0.0 3 7.5 22.0
at key entry points
and construction of
boundary gantry at
all boundaries of
Siaya
Erection of 11.4 1 1 2 1 1
monuments of Siaya
County Hereos
Sensitisation of hotel No. of sensitisation 16a 2 2.0 2 2.2 2 2.4 2 2.6 2 2.9 12.1
owners on programmes
classification conducted
standards
Tourism Tourism stakeholders No. of community 16a 4 1.0 4 1.0 4 1.0 4 1.0 4 1.0 5.0
Development & capacity building engagements held
Promotion /capacity building of
stakeholders
Heritage & Cultural performance No. festivals held (2) 2 8.0 2 8.0 2 8.0 2 8.0 2 8.0 40.0
Culture & exhibitions No. of SDG 2 5.0 2 5.0 2 5.0 2 5.0 2 5.0 25.0
Management festivals/events/expo 11.4
s attended (4)
Got Ramogi Hill Inscription dossier SDG 5 5.0 5 5.0 5 5.0 0 0.0 0 0.0 15.0
/Forest & its developed (research 11.4
activities in-scribed & documentation)
Involvement of local
communities Hosting
of final ceremonies
and sensitisation at
community, county
& national levels
High level
engagements with
state parties for
support nationally &
144
Sub - Key Output Key Performance Linkage Planned targets and indicative budgets in KSh M Total
programme Indicator s to 2023-2024 2024-2025 2025-2026 2026-2027 2027-2028 Budge
SDGs Target Cost Target Cost Target Cost Target Cost Target Cost t in
targets Ksh M
internationally
Digitisation of No. of community 11.4 15 1.5 15 1.5 15 1.5 15 1.5 15 1.5 7.5
indigenous/intangibl cultural
e knowledge (IK) practitioners/groups
contributing
intangible asset and
genetic knowledge
for documentation &
digitisation and
storage in the county
and national
repository(databases)
Arts & Culture Art talent No. of art talent 11.4 56 9.0 56 9.0 56 9.0 56 9.0 56 9.0 45.0
Management development identified, nurtured
and exposed
Capacity building of 11.4 30 3.0 30 3.0 30 3.0 30 3.0 30 3.0 15.0
identified
artists/Talents
Nurture & Expose 11.4 1 1 1 1 1
Siaya County Staff
Choir
145
Sub - Key Output Key Performance Linkage Planned targets and indicative budgets in KSh M Total
programme Indicator s to 2023-2024 2024-2025 2025-2026 2026-2027 2027-2028 Budge
SDGs Target Cost Target Cost Target Cost Target Cost Target Cost t in
targets Ksh M
No, of sports 1 5.0 1 5.0 1 10.0 1 10.0 1 5.0 35.0
facilities equipped
Sports Talent No. of sports 41 25.0 41 25.0 41 25.0 41 25.0 41 25.0 125.0
development tournaments
organized or
participated in (ward,
sub-county, national
and international
levels)
No. of sports officials 90 3.0 100 3.5 50 1.5 50 1.8 50 2.2 12.0
trained
No. of clubs 10 3.0 10 3.0 10 3.0 10 3.0 10 3.0 15.0
supported
(registration, sports
equipment, transport
and affiliation)
No. of athletes 30 3.0 65 4.5 65 4.5 100 7.0 100 7.0 26.0
supported (scouting
and nurturing)
No of aquatic and 2 3.0 4 6.0 4 6.0 4 6.0 4 6.0 27.0
beach sports
organised (Including
Lake Kanyaboli
water-front sports
events)
No. of Paralympic 30 3.0 75 7.8 75 7.5 100 10.0 100 10.0 38.3
athletes trained and
supported (deaf
football, sitting
volleyball)
No. of sports 2 0.8 2 1.0 2 1.0 2 1.0 2 1.0 4.8
influencers recruited
No. of National 7 2.0 7 2.0 7 2.0 7 1.0 7 1.0 8.0
Sports Days held
Sub Total 150. 165. 228. 264. 251. 1,061.1
8 8 5 8 2
Programme Name 6: General Administration, Planning and Support Services
Objective: To provide transformative leadership, capacity and policy direction in service delivery
Outcome: an enhanced Institutional framework for excellent, efficient and effective service delivery within the sector
Trade and General No. of regulations SDG 1.b, 3 4.5 2 3.0 0 0.0 0 0.0 0 0.0 7.5
Industry Administration formulated (trade 8.3
fund, liquor and
cooperative fund
regulations, County
146
Sub - Key Output Key Performance Linkage Planned targets and indicative budgets in KSh M Total
programme Indicator s to 2023-2024 2024-2025 2025-2026 2026-2027 2027-2028 Budge
SDGs Target Cost Target Cost Target Cost Target Cost Target Cost t in
targets Ksh M
Board Fund Bill and
weights and
measures policy
No of Acts developed 2 4.0 0 0.0 0 0.0 0 0.0 0 0.0 4.0
(Enterprise
Development Fund,
and industrial
development Acts)
No of progress SDG 12 0.8 12 0.8 12 0.8 12 0.8 12 0.8 3.8
reports developed 17.18
No. of operational SDG 10 15.0 10 15.0 0 0.0 6 10.0 6 10.0 50.0
tools and equipment
acquired &
maintained
Staff in post: Trade 8.5 43 39.9 45 43.8 46 47.4 50 53.2 49 58.5 242.9
Training of staff and 16.a 16 4.0 10 3.0 10 3.0 5 1.5 5 1.5 13.0
capacity building
Planning and No of office blocks SDG 2 10.0 2 10.0 0 0.0 0 0.0 0 0.0 20.0
Support Services constructed, 11.7.1,
refurbished and 8.8
rehabilitated
Tourism and General No. of regulations SDG 1.b, 2 3.0 0 0.0 0 0.0 0 0.0 0 0.0 3.0
Sports Admistration formulated (Culture 8.3
policy and Tourism
Policy)
No of progress SDG 12 0.8 12 0.8 12 0.8 12 0.8 12 0.8 3.8
reports developed 17.18
No. of operational SDG 6 8.0 12 16.0 0 0.0 4 8.0 4 8.0 40.0
tools and equipment
acquired &
maintained
Staff in post:Tourism 8.5 41 37.0 45 41.6 45 43.4 45 46.9 49 51.7 220.7
Training of staff and 16.a 16 4.0 10 3.0 10 3.0 5 1.5 5 1.5 13.0
capacity building
Planning and No of office blocks SDG 0 0.0 0 0.0 0 0.0 0 0.0 1 10.0 10.0
Support Services constructed, 11.7.1,
refurbished and 8.8
rehabilitated
Sub Total 130. 136. 98.4 122. 142. 631.6
9 9 6 7
Grand Total 648. 0 713. 0 785. 0 863. 0 950. 3,961.6
9 8 2 7 0
147
148
4.1.8 Education, Social Protection, Culture and Recreation
Page 149
4.2.1 Sector Programmes
The sector plans to provide quality Pre-primary education and vocational training through recruitment of ECD and VTC instructor; construction and
equipping of ECD and VTCs; provision of bursary, VTC capitation and scholarship. The sector also plans to support special interest groups through
establishment of affirmative action funds; construction of GBV and child rescue centres.
Sub Program Key Output Key Performance Linkage s Planned Targets and Indicative Budget (KSh. M) Total
Indicators to SDG 2023-2024 2024-2025 2025-2026 2026- 2027-2028 Budget
Targets* 2027 (KSh.
Tar Cost Ta Cost Tar Cost T Co Targ Co M)*
get rge get ar st et st
t ge
t
Programme 1 General Administration, Planning and Support Services
Objective: To ensure provision of effective service to the clients
Expected outcome: Effective service delivery
General Operational capacity No. of staff in-post 733 160.0 1,0 200.0 1,1 230.0 1, 28 1,34 30 1,170.0
Administration enhanced 14 94 29 0.0 4 0.0
4
No. of training needs 1 3.0 1 3.0 1 3.0 1 3.0 1 3.0 15.0
assessment report
prepared and implemented
No. of assorted equipment 20 10.0 20 10.0 20 10.0 20 10. 20 10. 50.0
acquired 0 0
No. of vehicles purchased 1 6.0 1 6.0 0 0.0 0 0 0.0 12.0
Planning and Improved service delivery No. of facilities integrated 10 3.0 5 1.5 5 1.5 5 1.5 5 1.5 9.0
support services with ICT
No. of policies, Bills, and 2 2.0 3 3.0 0 0.0 0 0.0 0 0.0 5.0
Regulations developed
No. of performance 1 0.2 1 0.2 1 0.2 1 0.2 1 0.2 1.0
contract signed
No. of progress reports 10 5.0 10 5.0 10 5.0 10 5.0 10 5.0 25.0
prepared and submitted
No. of libraries equipped 1 2.0 1 2.0 1 2.0 0 0.0 0 0.0 6.0
Digital Library 0 0.0 1 2.0 0 0.0 0 0.0 0 0.0 2.0
constructed and equipped
Improved Retention and No. of students supported 20,0 90.0 20, 90.0 20, 90.0 20 90. 20,0 90. 450.0
Page 150
Sub Program Key Output Key Performance Linkage s Planned Targets and Indicative Budget (KSh. M) Total
Indicators to SDG 2023-2024 2024-2025 2025-2026 2026- 2027-2028 Budget
Targets* 2027 (KSh.
Tar Cost Ta Cost Tar Cost T Co Targ Co M)*
get rge get ar st et st
t ge
t
completion in schools through 00 00 000 ,0 0 00 0
bursary/scholarship 0 00
Sub Total 281.2 322.7 341.7 38 40 1,745.0
9.7 9.7
Programme 2: County Pre-Primary Education
Objective: To provide quality Pre- Primary Education in the County
Expected Outcome: Improved Access to quality Pre-Primary Education
ECD ECDE centres developed and No. of ECDE centres 70 14.0 80 16.0 70 14.0 30 6.0 30 6.0 56.0
operational equipped with furniture
No. of ECDE centres 10 40.0 10 40.0 7 28.0 5 20. 5 20. 148.0
constructed 0 0
No. of model ECDE 1 15.0 1 15.0 0 0.0 1 15. 0 0.0 45.0
centres constructed per 0
Municipality
No. of ECD centres 130 26.0 13 26.0 130 26.0 13 26. 130 26. 130.0
provided with recreational 0 0 0 0
equipment,
No of ECD centres 700 28.0 70 28.0 700 28.0 70 28. 700 28. 140.0
provided with teaching 0 0 0 0
and learning materials
No. of learners benefitting 100, 10 100 10 100, 0.0
from school feeding 000 0,0 ,00 0, 000
program 00 0 00
0
No of ECD learners 100, 30.0 10 20.0 100 20.0 10 10. 100, 10. 90.0
provided with digital 000 0,0 ,00 0, 0 000 0
learning gargets 00 0 00
0
Sub Total 153.0 145.0 116.0 10 90. 609.0
5.0 0
Programme 3: Vocational Education, Youth Training and Development
Page 151
Sub Program Key Output Key Performance Linkage s Planned Targets and Indicative Budget (KSh. M) Total
Indicators to SDG 2023-2024 2024-2025 2025-2026 2026- 2027-2028 Budget
Targets* 2027 (KSh.
Tar Cost Ta Cost Tar Cost T Co Targ Co M)*
get rge get ar st et st
t ge
t
Objective: To Provide Access to Quality and Relevant Training to the Youth
Outcome: Appropriate Skills Developed
Vocational VTCs developed and No. of workshops 3 10.5 3 10.5 3 10.5 2 7.0 2 7.0 45.5
Training Centres operationalized constructed
No, of learners supported 3,70 27.8 3,9 29.3 4,0 30.0 4, 30. 4,20 40. 158.5
with Capitation 0 00 00 10 8 0 8
0
No of classrooms 2 5.0 2 5.0 2 5.0 2 5.0 2 5.0 25.0
constructed
No of computer labs 0 0.0 1 3.5 0 0.0 1 3.5 1 3.5 10.5
constructed and connect to
internet
No. of administration 1 3.5 0 0.0 1 3.5 0 0.0 1 3.5 10.5
blocks constructed
No. of VTCs equipped 3 4.5 3 4.5 3 4.5 3 4.5 3 4.5 22.5
No. of VTC hostels 0 0.0 1 4.0 1 4.0 0 0.0 1 4.0 12.0
constructed
No. of VTC buses 0 0.0 0 0.0 1 8.0 0 0.0 0 0.0 8.0
procured
No. of VTCs Renovated 1 1.5 1 1.5 1 1.5 1 1.5 1 1.5 7.5
No. of VTCs registered 2 0.5 2 0.5 2 0.5 2 0.5 2 0.5 2.5
demarcated and acquire
Title deeds
No of model VTCs 0 0.0 1 5.0 0 0.0 1 5.0 1 5.0 15.0
constructed
Sub Total 53.3 63.8 67.5 57. 75. 317.5
8 3
Programme 4: County Social Security and Services
Objective: To expand empowerment schemes, welfare and support systems in the County
Expected Outcome: empowered women, youth and PLWDs and improved social welfare
Social services No. of groups trained 5.5 300 2.0 30 2.0 300 2.0 30 2.0 300 2.0 10.0
Page 152
Sub Program Key Output Key Performance Linkage s Planned Targets and Indicative Budget (KSh. M) Total
Indicators to SDG 2023-2024 2024-2025 2025-2026 2026- 2027-2028 Budget
Targets* 2027 (KSh.
Tar Cost Ta Cost Tar Cost T Co Targ Co M)*
get rge get ar st et st
t ge
t
0 0
No of incubation centres 5.5 0 0.0 1 5.0 1 5.0 1 5.0 0 0.0 15.0
established
No of groups accessing 0.0 0 0.0 0 0.0 0 0.0 12 2.0 120 2.0 4.0
the affirmative action fund 0
No of GBV recovery/ 0.0 0 0.0 0 0.0 1 5.0 0 0.0 5.0
Children rescue centres
constructed equipped,
staffed and registered.
No of youth attending 8.5 30 2.0 30 2.0 30 2.0 30 2.0 30 2.0 10.0
innovation and investment
week
No of child rescue centre 16.2 1 1.0 0 0.0 0 0.0 0 0.0 0 0.0 1.0
operationalized
No of international days 6 1.8 6 1.8 6 1.8 6 1.8 6 1.8 9.0
celebrated
No of children assemblies 16.2 1 1.0 0 0.0 1 1.0 0 0.0 1 1.0 3.0
initiated
Sub Total 7.8 10.8 11.8 17. 8.8 57.0
8
Total 495.2 542.3 537.0 57 58 2,728.5
0.3 3.8
Page 153
4.2 Flagship Projects
Project name Location Objective Description of key Key outputs Time frame* Estimated cost Source of funds Lead Agency
activities (M)
Rice development project 1. Muluwa To increase Expanding area under 6,500 acres new land On-going under 5,478 National government National
Irrigation production & irrigation rice under rice Lower Nzoia (World Bank & Irrigation Board
Scheme in Alego streamline the rice Irrigation Project KfW)
Usonga sub- value chain (LNIP)
county Facilitate acquisition of Earth moving/ grading 2024 10 CGS/ Nat Gov. & CGS
land leveling machinery/ machinery Dev partners
equipment
Facilitate acquisition of Moldboard/ disc 2024 10 CGS/ Nat Gov. & CGS
land preparation ploughs, rotavators Dev partners
machinery/ equipment
Facilitate availability of Farm inputs revolving 2024 120 CGS/ Nat Gov. & CGS
farm inputs revolving fund in place Dev partners
fund
v. Facilitate acquisition Appropriate spraying 2024 5 CGS/ Nat Gov. & CGS
of spraying equipment equipment e.g. boom Dev partners
sprayer
Rehabilitate and expand Access road network 2024-2025 20 CGS/ Nat Gov. & CGS
scheme access road within the scheme Dev partners
network improved
Capacity building in Smooth operation of 2023-2027 10 CGS/ Nat Gov. & CGS
organizational and the cooperative Dev partners
technical development societies & profitable
value chain
development
Facilitate availability of Appropriate & 2024-2027 50 CGS/ Nat Gov. & CGS
adequate produce adequate produce Dev partners
handling facilities handling facilities
available e.g. drying
floors, stores
Facilitate access to Produce mopping fund 2024 165 CGS/ Nat Gov. & CGS
produce mopping fund established Dev partners
Facilitate availability of Milling, packaging 2024 CGS/ Nat Gov. & CGS
rice processing facilities machines in place Dev partners
Facilitate availability of Appropriate transport 2025 3 CGS/ Nat Gov. & CGS
appropriate transport means available Dev partners
Facilitate availability of Appropriate training & 2024-2026 10 CGS/ Nat Gov. & CGS
training facility & office office space available Dev partners
space
Sub-Total Muluwa 5,881
Scheme
Committed 5,478 LNIP phase 1
Required 403
Anyiko Irrigation To increase Expanding area under 2,000 acres under rice On-going under 478 National government Ministry of
Page 154
Project name Location Objective Description of key Key outputs Time frame* Estimated cost Source of funds Lead Agency
activities (M)
Scheme in production & irrigation rice Anyiko Scheme (Ministry of Water) Water
Ugenya sub- streamline the rice Expansion Project
county value chain ii. Facilitate acquisition Earth moving/ grading 2024 5 CGS/ Nat Gov. & CGS
of land leveling machinery Dev partners
machinery/ equipment
iii. Facilitate acquisition Moldboard/ disc 2024 5 CGS/ Nat Gov. & CGS
of land preparation ploughs, rotavators Dev partners
machinery/ equipment
iv. Facilitate availability Farm inputs revolving 2024 40 CGS/ Nat Gov. & CGS
of farm inputs revolving fund in place Dev partners
fund
v. Facilitate acquisition Appropriate spraying 2024 5 CGS/ Nat Gov. & CGS
of spraying equipment equipment e.g. boom Dev partners
sprayer
vi. Rehabilitate and Access road network 2024-2025 10 CGS/ Nat Gov. & CGS
expand scheme access within the scheme Dev partners
road network improved
vii. Capacity building in Smooth operation of 2023-2027 5 CGS/ Nat Gov. & CGS
organizational and the cooperative Dev partners
technical development societies & profitable
value chain
development
viii. Facilitate availability Appropriate & 2024-2027 10 CGS/ Nat Gov. & CGS
of adequate produce adequate produce Dev partners
handling facilities handling facilities
available e.g. drying
floors, stores
ix. Facilitate access to Produce mopping fund 2024 24 CGS/ Nat Gov. & CGS
produce mopping fund established Dev partners
x. Facilitate availability Milling, packaging 2024 25 CGS/ Nat Gov. & CGS
of rice processing machines in place Dev partners
facilities
xi. Facilitate availability Appropriate transport 2025 3 CGS/ Nat Gov. & CGS
of appropriate transport means available Dev partners
xii. Facilitate availability Appropriate training & 2024-2026 5 CGS/ Nat Gov. & CGS
of training facility & office space available Dev partners
office space
SUB-TOTAL 615
ANYIKO SCHEME
Committed 478 On-going scheme
expansion project
Required 137
COUNTY GRAND TOTAL 6,496
SUMMARY
Total committed 5,956
Page 155
Project name Location Objective Description of key Key outputs Time frame* Estimated cost Source of funds Lead Agency
activities (M)
Total required 540
Capital projects
Sector Projects Objective Geographical Location Expected Impacts Cost Implementing Agency
Agriculture and Provision of subsidy for farm input To provide affordable farm input and County wide Improved agricultural 813 County Government/Partners
Livestock Provision of subsidized tractor hire services tractor hire services County wide production 245 County Government/Partners
Development irrigation infrastructure To reduce dependance on rain fed Alego, Ugenya 280 County Government/Partners
agriculture
Enhance extension services To provide agriculture extension County wide 1104 County Government/Partners
services
Fish development To increase fish production and value Along the lake(Bondo, Improved income 100 County Government/Partners
addition Rarieda)
Cotton development To increase cotton production and Siaya, Rarieda 100 County Government/Partners
value addition
Sun flower development To increase sun flower production and Gem 100 County Government/Partners
value addition
Sugarcane development To increase sugarcane production and Yala Swamp, Siaya 300 Partners
value addition
Fertilizer Production and Animal Feed To increase uptake and utilization of Along the lake 250 Partners
fertiliser
Dairy production To improve daity production and value Ugunja and Ugenya 50 County Government/Partners
addition
Rehabilitation of Dams for Agricultural Production To improve food production Siaya county Enhanced Food security County Government/Partners
Environment, last mile connectivity on Ugunja-Sega-Ukwala and To increase access to safe water Ugunja, Sega, Ukwala Improved access to safe 482 County Government
Water and Natural last mile connectivity on SIBOWASCO Bondo and Siaya water 50 County Government
Resources Development of water master plan 150 County Government
Augmentation of Yala intake Yala 500 National Government
Wichlum water project Bondo 50 County Government
Construction of new solar powered boreholes County-wide 190 County Government
Augmentation and rehabilitation of community water County-wide 330 County Government
schemes
Transport and Tarmacking of roads To improve access to social and County-wide Enhanced public transport 5000 National Government
Energy productive areas
Acquisition of road construction machinery To improve access to social and
productive areas
Upgrading of airstrips To improve air transport Sega, Gombe, Migwena 100 County/ National
Government
Establishment of Asembo bay feeder port To improve water transport Rarieda 30 County/ National
Government
Construction of energy centres To improve uptake of energy solutions Siaya, Bondo and Sustainable energy 30 County/ National
Ugunja solutions Government
Page 156
Sector Projects Objective Geographical Location Expected Impacts Cost Implementing Agency
Development of energy master plan County-wide 45 County Government
Health and Construction of hospital complexes To improve access to specialized Siaya and Bondo Improved access to health 122 County Government
Sanitation health care care
Purchase of Medical supplies To improve access to health County-wide 1720 County Government
commodities
Construction and equipping of MRI centre To improve access to specialized Siaya 45 County Government
health care
Establishment of 30 model health centres To improve access to primary health County wide 120 County Government
care
Education, Social Establishment of ECD centres To improve access to early childhood County wide Improved ECD, secondary 609 County Government
Protection, culture education and tertiary education
and Recreation Establishment of VTC centres To improve access to vocational County wide 317 County Government
training
School feeding programme To improve retention in ECDs County wide 4875 County Government/Partners
Establishment of digital libraries
Provision of bursary and scholarships To provide support to needy school County wide 450 County Government
going children
Affirmative action fund for women, youth and PWD To provide support to special interest County wide Improved livelihood of County Government
groups special interest groups
Trade, Provision of credit to cooperative socities To improve access to credit for County wide Improved access to credit 228 County Government
Industrialization cooperative socities
and Tourism Establishment of Enterprise Development Fund To provide affordable credit for County wide 255 County Government
MSMEs
Development of market infrastructure To improve infrastructure in markets County wide Improved business 348 County Government
Establishment of Industrial Park To promote industrial growth Siaya environment 200 County/ National
Government
Establish Lake front Development Authority To drive investment around the lake Along L. Victoria 100 County Government
front
Development of Got Ramogi To develop tourist attraction sites Bondo Improved tourist numbers 152 County Government
Construction of phase II Siaya Stadium To improve sports infrastructure Siaya Improved sports and talent 200 County Government
Construction of Migwena talent Centre To promote talent development Bondo development 539 County/ National
Government
Lands, Housing Operationalization of the GIS laboratory To Siaya Improved management of 50 County Government
and Physical Digitization of public land records To ease management of public land Siaya public land 45 County Government/Partners
Planning records
Land banking To avail land for investment County wide 98 County Government
Implementation of Yala Land Use Plan To provide coordinated development of Bondo and Siaya 200
Yala swamp
Construction of affordable housing To provide affordable housing Bondo and Siaya Enhanced development of 3000 County/ National
government housing Government
Construction of office complex To provide adequate office space Siaya 440 County Government
Construction of state officer residence(Governor, Deputy To provide accommodation for state Siaya 80 County Government
Governor) officers
Siaya Municipality To improve management of urban areas Siaya, Bondo and Improved management of 697 County Government/Partners
Ugunja Municipality Ugunja urban areas 294
Bondo Municipality 294
Page 157
Sector Projects Objective Geographical Location Expected Impacts Cost Implementing Agency
Establishment of L.Kanyaboli Eco-city To drive Siaya into an urban enclave Siaya Improved livelihood 500 County Government/Partners
Administration Construction, renovation and equipping of sub county and To provide adequate office space County wide Improved service delivery 201 County Government
and ward offices
Intergovernmental Operationalization of village units To improve decentralized services to County wide 229 County Government
Relations the village label
Establishment of E-Government To automate government services County wide 181 County Government
Construction of speakers residence To improve accomodation for state Siaya 35 County Government
officers
Construction of County Assembly's complex To improve office accomodation Siaya 396 County Government
Page 158
4.3 CIDP Linkages with National Development Agenda, Regional and International
Development Frameworks.
National Development Aspirations/Goals County Government Contributions/ Interventions
Agenda/
Regional/International
Obligations
Kenya Vision 2030 To achieve an average Expansion of area under rice irrigation in Mulwa and Anyiko
economic growth rate of 10 schemes
percent per annum and Investment in culture and capture fisheries
sustaining the same until Value addition in agricultural produce
2030 provision of subsidized Agricultural inputs
Provision of extension services
Promotion of mechanized agriculture
establishment of cooperative and enterprise development
funds
development of market infrastructure
development of industrial parks
development of tourist attraction sites
marketing the county as a tourist destination
To engender just, cohesive Provision of early childhood and VTC education
and equitable social Provision of bursary and scholarships
development in a clean and Support to youth, women and PWDs
secure environment Development of siaya stadium and Migwena sports academy
Improvement of primary and referal health infrastructure
improvement of commodity supply and management
strengthening management of communicable and non-
communicable diseases
provision of universal healthcare
recruitment of healthcare workers
development of water master plan
Augmentation of Yala intake
Expansion of last mile connectivity
Construction of Wichlum water project
construction of solar powered boreholes
Reclamation of riparian land using bamboo and fruit trees
afforestation of degraded areas
beautification of urban areas
Establish climate change centers
implement climate change adaptation projects
development of affordable housing projects
development of office complexes
To realize an issue based, establish disaster response centre
people centered, result Strengthen human resource planning, management and
oriented and accountable development
democratic system Investment in e-government and promotion of e-commerce
Digitization of public land records
operationalization of GIS lab
preparation of land use plans for markets and urban centres
Construction of roads and bridges
upgrading of airstrips
construction of feeder port, jetties and harbors
construction of energy centers
Sustainable Goal 1 No Poverty Value addition in agricultural produce
Development Goals establishment of cooperative and enterprise development
funds
development of market infrastructure
development of industrial parks
Page 159
National Development Aspirations/Goals County Government Contributions/ Interventions
Agenda/
Regional/International
Obligations
development of tourist attraction sites
marketing the county as a tourist destination
Goal 2 Zero Hunger Expansion of area under rice irrigation in Mulwa and Anyiko
schemes
Investment in culture and capture fisheries
provision of subsidized Agricultural inputs
Promotion of mechanized agriculture
Goal 3 Good Health and Improvement of primary and referral health infrastructure
Well-being improvement of commodity supply and management
strengthening management of communicable and non-
communicable diseases
provision of universal healthcare
recruitment of healthcare workers
Goal 4 Quality Education
Provision of early childhood and VTC education
Provision of bursary and scholarships
Support to youth, women and PWDs
Development of siaya stadium and Migwena sports academy
Goal 5 Gender Equality Provision of affirmative action fund for women
Development Establishment of Gender rescue centers and child
Goal 6 Clean Water and development of water master plan
Sanitation Augmentation of Yala intake
Expansion of last mile connectivity
Construction of Wichlum water project
construction of solar powered boreholes
Completion of ongoing water projects
Construct water harvesting infrastructure
Goal 7 Affordable and Establishment of energy centres
Clean Energy Capacity building on sustainable energy sources
Preparation of off grid, on grid solar and Ndanu falls master
plans
Goal 8 Decent Work and Strengthen human resource planning, management and
Economic Growth development
Own source revenue collection
Timely payment of goods and services
Goal 9 Industry, Innovation Promotion of e-government and e-commerce
and Infrastructure Establishment of industrial parks
Promotion of agro-processing
Construction of roads and bridges
upgrading of airstrips
construction of feeder port, jetties and harbors
Goal 10 Reduced Inequality Provision of affirmative action fund for special interest
groups
Goal 11 Sustainable Cities development of affordable housing projects
and Communities preparation of land use plans for markets and urban centres
Development of urban infrastructure
Goal 12 Responsible Promotion of clean energy
Consumption and Development and implementation of agriculture value chains
Production Establishment of energy centres
Goal 13Climate Action Reclamation of riparian land using bamboo and fruit trees
afforestation of degraded areas
beautification of urban areas
Establish climate change centres
Page 160
National Development Aspirations/Goals County Government Contributions/ Interventions
Agenda/
Regional/International
Obligations
implement climate change adaptation projects
Goal 14 Life Below Water Protection of water towers and riparian reserves program and
stocking with fish
Invest in capture and culture fisheries
Goal 15 Life on Land afforestation of degraded areas
beautification of urban areas
Establish climate change centres
implement climate change adaptation projects
Development of urban infrastructure
Protection of natural resources
Goal 16 Peace, Justice and Strengthen oversight, representation and legislation
Strong Institutions Improve services at the decentralized units
Goal 17 Partnerships and Strengthen public service coordination and inter-
collaborations to achieve governmental relations
the goals
AU Agenda 2063 A peaceful and prosperous Development of Lake Kanyaboli eco-city
Africa based on inclusive Establishment of industrial park
growth and sustainable Development of infrastructure in urban centers
development Support to Lake Region Economic Bloc
Paris Agreement 2015 Combat climate change and Reclamation of riparian land using bamboo and fruit trees
adapt to its effects afforestation of degraded areas
beautification of urban areas
Establish climate change centres
implement climate change adaptation projects
EAC Vision 2050 A peaceful and prosperous Promote cultural events
East Africa based on Development of tourist sites
inclusive growth and Strengthen tourism product marketing
sustainable development Promote water sports
Promote urban infrastructure development
Improvement of county transport infrastructure
development of county museum
ICPD25 Kenya Comprehensive package of Improvement of primary and referal health infrastructure
Commitments sexual and reproductive improvement of commodity supply and management
health interventions provision of universal healthcare
recruitment of healthcare workers
Sendai Framework For Prevent the creation of new Establish Response Centres at county and sub county level
Disaster Risk Reduction risk, reduce existing risk Develop early warning systems
(2015-2030) and increase resilience Develop and implement disaster mitigation plans
against risks Provide disaster management equipment
Develop early warning systems
Page 161
Sector Linked Sectors Cross-sector impact Measures to Harness
Synergies Adverse Impact or Mitigate the
Impact
and natural resources pans desilted, lakes from farmlands through irrigation
Agriculture - Connection to water Chemical pollution Awareness creation
Livestock sources e.g water of water bodies Food production
pans and dams from farmlands through irrigation
desilted
Education Education facilities Connections through
water supply pipeline extensions
Health Use of sewerage Convening of WASH
services; stakeholder forums;
Collaboration in
supporting sanitation
projects
Agriculture Agroforestry Development of tree
nurseries;
Purchase and
distribution of tree
seedlings
Lands Gazettement of Gazettement of
community hills community hills to
increase forest cover in
Siaya county;
Identification of
sanitary landfills.
Governance Enforcement of Training of the
environmental laws enforcement officers
Transport and energy Education Construction of Reduction in Reforestation after
ECDs and VTCs vegetation cover, construction works
noise pollution
(All)Trade Connection to Pulling down of Continuous
market centers structures on road sensitization
reserve community against
erecting structures on
road reserves
Water Solarized Damage of Erection of marker
boreholes underground water posts at utility points
pipes
Health Connection to health Air pollution, noise Sprinkling of water
facilities, pollution and over the road surface.
construction of vibrations during
dispensaries, wards. compaction
staff houses,
laboratories, blood
banks
Trade, Roads and Public Access to market Pulling down Establishment of
industrialization and works centres of structures on market centres along
tourism road the roads;
reserve
Finance and Improve revenue Development of
Page 162
Sector Linked Sectors Cross-sector impact Measures to Harness
Synergies Adverse Impact or Mitigate the
Impact
Economic planning collection new market
infrastructures
Market solid waste
management
Lands Market infrastructure Demarcation and Market surveys
development market title deeds
Directorate water Developing Increase water
infrastructure coverage
SIBOWASCO Technical expertise Managing water
and water sources infrastructure
Agriculture Connection to water Using water for food
sources e.g water production
pans desilted
Tourism development State Dept of Technical support Lack of Enhanced Cooperation
& promotion Tourism, Wildlife & cooperation with various state and
Heritage leading to under non state actors
development
Shared strategies to Most hospitality Improved strategies on
Trade & Enterprise boost investment facilities are not the adoption of ICT as
standardised to a platform for
meet minimum marketing & exposure
operating
requirements
Design & layout Lack of
Public Works support compliance with
standards ie BSS &
heritage
restoration,
resulting in
destruction of
heritage sites
Heritage & Culture Public Works Design & layout Compromised
development support for quality of works
infrastructure, hinders
Accessibility ie accessibility to the
roads and trails sites
Social Services Community Community apathy
education on best on ownership of
practices projects meant to
improve
livelihoods
State Dept of Support on Avoid issues of de-
Tourism, Wildlife & gazettement & gazzetment.
Heritage inscription issues
Page 163
Sector Linked Sectors Cross-sector impact Measures to Harness
Synergies Adverse Impact or Mitigate the
Impact
State Dept of Youth Riverine & Maritime Culturally focussed
Affairs, Sports & the sports sports & arts being
Arts Arts Talents shunned by the
Management youth as not viable
Devolve financial
resources to the
departments
Page 164
Chapter Five
Implementation Framework
5.1 Introduction
The Chapter outlines the Institutional Framework and assigns specific roles to towards the
implementation of the CIDP. It also provides a resource mobilization and management
framework, assets management and risk mitigation measures. Implementation of the
development interventions in this plan will jointly be undertaken by the County Government
of Siaya and the National Government as envisaged in Article 6 of The Constitution of Kenya
2010. Other stakeholders who will be critical in the process are the development partners, the
private sector under the PPP framework as well as the non-profit organisations.
5.2: Institutional Framework
Implementation of this plan will be undertaken by the county government executive wing
through the departments, agencies and its decentralized structures up to the ward level as
provided for in the constitution of Kenya 2010 and the county government act 2012. The
county assembly will provide legislative and oversight role during the plan implementation.
In line with Part II of the Fourth Schedule of the Constitution of Kenya 2010 the CIDP will
be implemented through 10 departmental portfolios and three agencies as shown below.
Table: County executive departments and their roles
Department Role/ key mandate
Governance and Administration Provide strategic leadership on human resource management and
administrative service delivery
Finance and Economic Planning To promote efficient and effective management of public finances
and economic planning affairs
Agriculture, Irrigation, Food, Livestock To improve agricultural production and productivity
and Fisheries Promote commercial agriculture and agro-based industrialization
Education, Youth Affairs, Gender, Social Provide quality pre-primary education, and Vocational training
Services and Sports Provide support to special interest groups and promote and
develop sport and talent
Water, Environment and Natural Provision of safe water and sewerage services, build resilience to
Resources impacts of climate change and environmental conservation
Health and Sanitation To provide quality, accessible and affordable health care
Enterprise and Industrial Development Provides an enabling environment that facilitates competitive
trade, investment and industrialization
Lands, Physical Planning, Housing and Ensure sustainable land and urban management and provide
Urban Development quality, adequate and affordable housing
Public Works, Roads, Energy and Provide accessible and well managed transport system, quality
Infrastructure built environment and sustainable energy solutions
Tourism, Culture, Art and ICT Market siaya as a premier tourist destination
Page 165
During the plan implementation phase, all implementing departments will prepare Annual
Development Plans, Annual Budgets and thereafter develop work plans, cash flow plans and
procurement plans based on the approved budgets. Implementing agencies will also prepare
Quarterly and Annual Progress Reports on implementation of the CIDP.
County government service delivery points are at the headquarters, sub-counties, wards,
boards and a limited company. Village administration units as point of service delivery are
yet to be operationalized. Currently, the county has three agencies: Siaya County Public
Service Board; Siaya Municipal Board; and Siaya Bondo Water and Sanitation Company Ltd
(SIBOWASCO). Processes are underway to put in place additional municipality boards and
towns as service delivery points. The chart below illustrates the County Government of Siaya
structure within which lies implementation framework for the County Integrated
Development Plan.
Page 166
COUNTY GOVERNMENT
COUNTY
County ASSEMBLY
Assembly COUNTY EXECUTIVE
Governance Finance, Agriculture Water, Education, Health Lands Enterprise Tourism Roads,
and Public Planning Energy and Gender, and and
, Livestock and , Culture Transport,
Service and Vision Youth and
and Natural Sanitati Housing Industrial and Infrastructure
Social
Delivery 2030 Fisheries Resources on Devt Sports
Services and Energy
Page 167
Village Devolved Units
Table indicates specific roles of selected key institutions in the implementation of the Plan.
S/No Institution Role in the implementation of CIDP
1 County Executive Determine the organisation of county structures
Committee Leadership and policy direction
Resource mobilization
Put in place performance management plan
supervise the administration and delivery of services in the county and all decentralized units and agencies in
the county
Inter-governmental coordination
2 County Assembly Legislation, Oversight and representation
3 County Government Implement government policies and legislations in conformity with their mandate.
Departments Mobilise resources
4 County Planning Unit Coordinate planning function in the county
Conduct economic and fiscal analysis
Coordinate with other institutions on planning matters
Provide leadership on feasibility studies
Prepare statutory planning documents annually
Collect, collate and analyse statistics on sectors
Prepare County fact sheets, statistical bulletins and conduct county economic survey.
Develop a unified planning system, coordinate and align national plans, international plans, geospatial
development plans and county development plans
5 Office of the County Provide leadership to the National Government technical departments in the county
Commissioner Coordinate intergovernmental activities in the county
6 National Planning Office Work with Ministries, Departments, Agencies and County Organs on common development interventions
at the County Provide linkage with national devolved functions for joint planning.
7 Other National Provide policy guideline
Government Departments Support the County Government through Technical Training
and Agencies at the Linkages with other departments, Agencies and partners
county
8 Development Partners Resource mobilization to fund the projects and programmes
Provide technical support towards implementation of projects and programmes
9 Civil Society Ensure community involvement in the projects management cycle of public projects and programmes
Organisations Ensures prudent use of public resources
10 Private Sector Resource mobilization and funding of projects through PPP
Funding of community transformative projects as CSR
Page 168
5.3 RESOURCE MOBILISATION AND MANAGEMENT FRAMEWORK
5.3.1 RESOURCE REQUIREMENTS BY SECTOR
Department/Sector name Resource Requirement (Ksh. million
FY: 2023/24 FY: 2024/25 FY: 2025/26 FY: 2026/27 FY: 2027/28 Total % of total
budget
requirements
County Assembly 859,525,698 945,478,268 1,040,026,095 1,144,028,704 1,258,431,574 5,247,490,339 10
Governance and Administration 598,044,189 657,848,608 723,633,469 795,996,816 875,596,497 3,651,119,578 7
Finance and Economic Planning 782,147,673 860,362,440 946,398,684 1,041,038,553 1,145,142,408 4,775,089,758 10
Agriculture, Food, Livestock & Fisheries 812,566,096 893,822,706 983,204,976 1,081,525,474 1,189,678,021 4,960,797,273 10
Water, Irrigation, Environment & Natural 465,537,836 512,091,620 563,300,782 619,630,860 681,593,946 2,842,155,043 6
Resources
Education, Youth Affairs, Gender & Social 446,848,720 491,533,592 540,686,951 594,755,646 654,231,211 2,728,056,120 5
Services
County Health Services 2,406,976,398 2,647,674,038 2,912,441,442 3,203,685,586 3,524,054,144 14,694,831,607 29
Lands, Physical Planning, Urban Development 599,432,559 659,375,815 725,313,396 797,844,736 877,629,210 3,659,595,716 7
and Housing
Roads, Public Works, Energy and Transport 609,215,159 670,136,675 737,150,342 810,865,377 891,951,914 3,719,319,467 7
Enterprise and Industrial Development 355,840,011 391,424,012 430,566,413 473,623,055 520,985,360 2,172,438,851 4
Tourism, Culture, Sports and Arts 293,056,267 322,361,894 354,598,083 390,057,891 429,063,681 1,789,137,816 4
Total 8,229,190,606 9,052,109,667 9,957,320,633 10,953,052,697 12,048,357,966 50,240,031,569 100
5.3.2Revenue Projections
Type of Revenue Base Year 2022/23 FY: 2023/24 FY: 2024/25 FY: 2025/26 FY: 2026/27 FY: 2027/28 Total Kshs. In billion
Equitable Share 6,966 7,255 7,981 8,779 9,656 10,622 44,293
Conditional Grants 258 274 301 332 365 401 1,673
Own Source Revenue 700 700 770 847 932 1,025 4,274
Total 7,924 8,229 9,052 9,957 10,953 12,048 50,239
Page 169
5.3.4 Resource Mobilisation and Management Strategies
To effectively implement the CIDP 2023/2027, the County Government should address issues of
internal revenue generation, external financing, efficient and prudent utilisation of the available
resources, which may be achieved through the following resource mobilization strategies and
management:
a) Financing and budgeting for CIDP through;
i) Strengthening OSR management
(1) Review of taxes
(2) Creation of new Revenue streams
(3) Establish a Revenue Board
(4) Automation of revenue collection and management
(5) Mapping of revenue streams
ii) Providing Incentives to attract Diaspora Investment
iii) Exploring project financing through Public Private Partnerships
iv) Lobbying for increased funding from the National Government
v) Loans and Grants
vi) Lobbying for National Government for increased investment in the county
b) Human Resource
i) Enhanced and efficient utilization of available operational capacity, HR planning, use
of modern technology in Human Resource Management, strengthen Performance
Management System and enforce compliance with human resource policies, laws
and regulations.
c) Work supporting tools and equipment
i) Improved working conditions for effective and efficient service delivery
5.4 Asset Management
5.4.1 ASSETS AND FINANCIAL MANAGEMENT
Asset Management: This is a systematic process which allows for the operation, maintenance,
upgrading and disposing of physical assets in a cost effective manner. In order to keep track of
assets the county will prepare Assets register and also consider an option of preparing an Asset
Page 170
management policy to deal with the choice dimension and expected outcomes of such assets so
as to minimize operational costs thereby releasing funds to other programmes and projects with
positive impacts on the county populace.
Page 171
Risk Risk Risk Implication Risk Level Mitigation measures
Category (Low,
Medium,
High)
stakeholder not keeping processes programs
pace with rapid ICT
changes
Operational Inadequate operational Poor service delivery Medium Invest in operational tools, equipment,
Risks tools, equipment, machinery and office accommodation
machinery and office
accommodation
Limited number of Ineffective and Medium Develop and implement human resource
technical officers, poor inefficient service management plan
career progression and delivery
placement of officers. Demotivated staff
Ineffective and in
efficient use of
Delay in recruitment of Poor service delivery low Foster optimal utilization of resources
new staff or delay in
deployment of staff
Global Shift in priorities for Stalled projects and Low Develop and implement County PPP strategy
Economic development by partners programmes
Crisis Fund diversion and re- Develop and implement own source revenue
allocation enhancement strategy
Environment Floods Food insecurity High Soil and water conservation structures,
al Economic loss timely weather advisory, establish
Loss and property recommended livestock structures,
damage
Death
Drought Food insecurity Medium to Promotion of drought tolerant crops,
Economic loss high
Death
Crop, livestock and Food insecurity Low to Observe recommended good agricultural and
fisheries pests/diseases Economic loss Medium health practises
outbreak leading to Crop Establish recommended farm structures,
damage and livestock loss partnership with KWS.
from wild life capacity building on good farming practices.
Environmental Pollution Food insecurity Medium to Enforce NEMA and fisheries regulations,
Economic loss high capacity building on solid and liquid wastes
Diseases outbreak management and safe use of chemicals,
Unhealthy environment
Social Contractual Breach Loss of Government resources Medium Enhance supervision of contracted works and
services,
Donor Dependency by High Mainstream community contribution to the
our clients project, capacity building and change of
mindset to beneficiaries and development
partners, diversify sources of funding,
Page 172
Chapter Six
Monitoring, Evaluation and Learning
6.1 Overview
This chapter outlines how the plan will be monitored and evaluated during and after its
implementation. The M&E processes, methods and tools are guided by Section 232 of the
Constitution and all the legal provisions that provide for M&E, County M&E Policy in line with the
National M&E Policy, CIMES Guidelines, Kenya Norms and Standards for M&E and Kenya
Evaluation Guidelines. The chapter highlights the proposed M&E structure; data collection,
analysis, reporting and learning; M&E outcome indicators tracking; and dissemination and feedback
mechanism.
6.2 County Monitoring and Evaluation Structure
The Monitoring and Evaluation Framework for the plan is premised on the principles of results-
based management. The CIMES-Guidelines define institutional set up for county M&E. However,
the envisaged institutions are not well developed in the county. The Monitoring and Evaluation
function falls under the Directorate of Strategy, Monitoring and Evaluation in the Office of the
County Secretary, Department of Governance and Administration. At departmental level, the
function is coordinated by Monitoring and Evaluation Focal Persons who are responsible for
compiling periodic progress reports.
To effectively monitor, evaluate and report on results that will be generated by the implementation
of the plan, a robust and well-coordinated county-wide M&E system (c-wide M&E System) will be
put in place by operationalizing the CIMES Guidelines. This is to ensure that planning and M&E
processes are standardised, interconnected, fully internalised and applied by the relevant
departments and agencies with the view to generate coordinated development results to inform
decision-making processes.
The county M&E system is coordinated by the department of Governance and administration
through the directorate of Strategy, Monitoring and Evaluation. However, the county M&E
capacity is still sub-optimal. In the plan period, the county will invest in human resources and
institutional set-up for M&E and appropriate funds in its annual budget to meet the cost of the
Page 173
function. In line with CIMES Guidelines, focus will be on recruitment of additional staff; M&E
skill development in departments, agencies and devolved units; resource mobilisation; acquisition
of relevant working tools and equipment; establishment of M&E structures; and adoption of modern
data collection technology.
To further strengthen the County M&E capacity, the M&E Directorate will regularly assess the
M&E capacity and devise strategies to address emerging gaps through, among others, leveraging on
ongoing national government and partner-led M&E capacity building initiatives, existing
partnerships, and collaborations for M&E, and mobilizing more resources for the various M&E
initiatives.
Page 174
Progra Outcome Outcome indicator Baseline Midterm End Reporting
mme Value Year target term responsibility
2022 target
2027
Primary Transition rate 99% 2023 99% 99%
Education
Distance to the nearest ECD 600 Metres 2023 600 600
center Metres Metres
Improved No. of natural resources 2 (gazetted forests) 2022 2 No. 2 No. KFS, CGS and
natural protected Forests Forests Partners
resources I No. water fall
management in
the county No. of licensed mining 2 No. exploration 2022 1 1 NEMA, CGS
activities exploited in the License issued and Partners
county
No. Licensed mining
activity
Improved Number of household using 248,295 2022 258,295 268,295 CGS and
adaptation to clean energy solutions Partners
climate change (25%)
by the populace
in the county
Environmentall Percentage forest cover 0.23 (NFRA,2021) 2021 0.29 0.35 KFS, CGS and
y clean County Partners
(829 Ha)
Page 175
Progra Outcome Outcome indicator Baseline Midterm End Reporting
mme Value Year target term responsibility
2022 target
2027
Percentage tree cover 5.27 (NFRA,2021) 2021 5.71 6.15 KFS, CGS and
Partners
(18,676.37 Ha)
Income from roots and tubers 203,278,000 2022 240,000,0 300,000, CDA
00 000
Page 176
Progra Outcome Outcome indicator Baseline Midterm End Reporting
mme Value Year target term responsibility
2022 target
2027
Income from milk produced 2,371,077,066 2022 2,736,486, 2,940,13 CDLP
550 5,170
% increase in improved Exotic cattle: 10% 2022 10% 10% County Director
livestock breeds Beef cattle: 10% of Veterinary
Indigenous goats: Services and
10% Livestock
Dairy Goats: 10%
Improved local
chicken: 10%
No. of livestock breed variety 2022
in the county
Page 177
Progra Outcome Outcome indicator Baseline Midterm End Reporting
mme Value Year target term responsibility
2022 target
2027
Physical Sustainable Towns 2 Towns 4 through the
Planning Development CECM
Markets 5 Markets
10
Rural
Market Rural
Layouts Market
15 Layouts
30
Reduced Land Acreage of land available for 100 2023 110 120 Directorate of
Conflicts and investment lands and
Improved survey
Investor (Acres)
Confidence
Database of public land records 2,000 2023 3,000 4,000 Directorate of
established lands and
survey
Increased own source revenue 46,255,572 2023 55 million 70 Directorate of
from land rates million lands and
survey
Affordable No. of affordable housing units 0 2023 100 200 Directorate of
housing for all occupied Housing /Lands
Quality urban No. of urban centers with 3 2023 1 2 Municipalities
infrastructure quality infrastructure of Siaya, Bondo
and Ugunja
Trade, A conducive No. of markets with developed 180 EID-2023 180 180 Chief Officer
Industria environment for infrastructure and well
lization trade managed
and No. of new business ventures Chief Officer
Tourism and innovations promoted
Improved % compliance with weights 89 EID-2023 100 100 Chief Officer
Consumer and measures Act Cap 513 and
confidence on other subsidiary legislation
value for
money
Expanded No. of active cooperative 192 EID-2023 228 270 Chief Officer
cooperative societies
business Cooperative turn over for 320,000,000.00 EID-2023 410,000,0 500.000, Chief Officer
active societies in the county 00.00 00
Page 178
Progra Outcome Outcome indicator Baseline Midterm End Reporting
mme Value Year target term responsibility
2022 target
2027
Increased No. of households adopting
number of climate friendly energy
households solutions
adopting No. of households connected
climate friendly with electricity
sources of
energy
Administ Strengthened County human resource plan
ration human resource implemented
and management County HRM policy and
Intergov procedure manuals
ernmenta operationalized
l Improved No. of operational framework
Relations service delivery established for devolved units
at decentralised
units
Strengthened % Compliance with
inspectorate, Inspectorate and enforcement
compliance Act 2019
and
enforcement
services
Strengthened Operationalize the County
disaster Disaster & Emergency
management framework
and response
Enhanced % compliance with Public
public participation and grievances
participation Act 2019
and civic
education
Enhanced % increase in public
public awareness on government
information and programmes and projects
communication
services
Strengthened Data management system
evidence based established
decision
making (M&E)
Strengthen Improved own source
financial collection
management % Compliance to internal
system control system
Strengthened No. of legislations approved
legislative,
oversight and
representation
framework
Page 179
photography, videography, and observation, among others. The M&E Directorate will undertake
capacity building on data quality issues to ensure that the data collected meets the required quality
standards. The data collected will be analyzed and reports generated to help inform decision-
making. The M&E reporting will also be supported by e-CIMES.
The County will prepare the Quarterly M&E progress reports, donor programme/project reports,
back-to-office reports that will feed into the CAPR, mid-term reports and end term reports on CIDP
implementation. The CAPR will provide the overall status of the CIDP implementation on an
annual basis and subsequently inform preparation of Annual Development Plan (ADP) and budget
estimates.
6.6 Dissemination, Feedback Mechanism, Citizen Engagement and Learning
The County will make data and information available to stakeholders, government officials,
academic researchers, policymakers, senior management, project participants, and the public for use
in making evidence-based decisions through a data dissemination plan and a feedback and response
system.
The County will incorporate learning into the overall programme implementation by using the
information disseminated from the M&E processes and making it available for potential users. The
county will also utilize critical reflection sessions, after-action reviews, and peer-to-peer learning,
among others, as strategies for learning to improve the overall county performance and quality of
results of ongoing and future programs, strategies, and interventions.
6.7 Evaluation Plan
Plan implementation and impacts will be evaluated at mid-term and at end-term. Evaluation will
involve an analysis of both process and impact, to generate evidence to inform the development,
strategic focus and implementation of future development plans. The M&E Directorate will
coordinate preparation of comprehensive evaluation plans for each planned evaluation to support
the evaluation planning and will cover components like the purpose of the evaluation, evaluation
questions, evaluation criteria, timetable, and work plan, collecting data for an evaluation, data
collection methods to answer evaluation questions, data collection tools and activities, data analysis,
and reporting evaluation findings. Table 27 provides a summary of the Evaluation plan for the
various intended evaluations by the County.
6.7 EVALUATION PLAN
Policy/ Evaluatio Outcome(s) Use of the Commissionin Anticipate Anticipate Evaluatio Source of
Programme n Title Evaluation g Agency/ d d n Budget Funding
/ Project (specify Findings Partners Evaluation Evaluation (Kshs. M)
the type) start date end date
CIDP Midterm Improved Improve CEC Finance June 2025 Sept 2025 15 CG/ Donor
Review of implementatio implementatio and Economic
Page 180
Policy/ Evaluatio Outcome(s) Use of the Commissionin Anticipate Anticipate Evaluatio Source of
Programme n Title Evaluation g Agency/ d d n Budget Funding
/ Project (specify Findings Partners Evaluation Evaluation (Kshs. M)
the type) start date end date
the Third- n of the CIDP n of CIDP. Planning
Generation
CIDP
CIDP End-term Improved Inform CECM Finance June 2028 Sept 20 CG/Donor
of the decision- decision- and Economic 2028
Third- making making for planning
Generation approaches for future
CIDP the implementatio
implementatio n of Policies
n of future and programs
plans
Sectors / Mid-Term Improved To enhance CECM of June 2025 September 70 CG/GoK/Dono
Subsector. Programm implementatio programme Departments 2025 r
e Outcome n of the efficiency and
Evaluation programmes effectiveness
Sectors / End-Term Improved To enhance CECM of April 2024 July 2024 77 CG/GoK/Dono
Subsector , Programm implementatio programme Departments r
e Outcome n of the efficiency and
Evaluation programmes effectiveness
Page 181
Annex 1: Factsheet
DEMOGRAPHIC PROFILES
Total population 1,040,616 50,622,914
Total Male population 525,833 25,104,154
Total Female population 514,782 25,518,760
Total intersex Population
Sex ratio (Male: Female)
Projected Population Mid of plan period 1,097,141 53,330,978
(2025)
End of plan period 1,136,553 55,123,051
(2027)
Infant population (<1 year) Female 12,068
Male 12,257
Inter-sex
Total 24,324
Population under five Female 69,410 3,138,424
Male 68,930 3,162,892
Inter-sex
Total 138,339 6,301,316
Pre- Primary School population (3-5) Female 41,137 1,878,320
years Male 40,634 1,856,781
Inter-sex
Total 81,771 3,735,102
Primary school age group (6-13) years Female 106,322 4,842,910
Male 104,303 4,746,503
Inter-sex
Total 210,624 9,589,413
Secondary school age group (14 - 17) Female 49,476 2,274,083
years Male 50,558 2,239,405
Inter-sex
Total 100,994 4,513,488
School Going Population as per CBC Curriculum
Pre- Primary School population (3-5) Female 41,137 1,878,320
years
Male 40,634 1,856,781
Inter-sex
Total 81,771 3,735,102
Primary school age group (6-13) years Female 106,322 4,842,910
Male 104,303 4,746,503
Inter-sex
Total 210,625 9,589,413
Page 182
Information Category County Statistics National Average
(as at 2022) Statistics
Junior Secondary School age group (12 Female 38,797 1,760,448
- 14) years
Male 38,434 1,728,255
Inter-sex
Total 77,231 3,488,703
Senior Secondary School age group (15 Female 36,769 1,694,585
- 17) years
Male 37,816 1,669,813
Inter-sex
Total 74,585 3,364,399
Youthful population (15-29) years Female 162,848 7,670,391
Male 172,461 7,614,374
Inter-sex
Total 335,309 15,284,765
Reproductive age (15 - 49) years 533,141 26,889,578
Labour force (15-64) years Female 285,881 15,279,666
Male 301,850 15,066,238
Inter-sex
Total 587,731 30,345,904
Aged population(65+) Female 26,411 1,041,376
Male 24,740 939,807
Inter-sex
Total 51,151 1,981,183
Population aged below 15 years
Eligible Voting Population Name of constituency
Alego usonga 122,002 22,102,532
Bondo 104,035 22,102,532
Ugenya 69,027 22,102,532
Ugunja 60,114 22,102,532
Gem 93,568 22,102,532
Rarieda 84,849 22,102,532
Total (county) 533,595 22,102,532
No. of Urban (Market) Centres with population >2,000
Urban population (By Urban Centre)
Siaya Total 34,714 14,831,700
Bondo Total 23,777 14,831,700
Usenge Total 8,355 14,831,700
Ugunja Total 7,396 14,831,700
Sega Total 4,371 14,831,700
Nyandiwa beach Total 4,225 14,831,700
Ndori Female
Male
Intersex
Total 3,949 14,831,700
Urban Centre 8: Yala Female
Male
Intersex
Total 3,391 14,831,700
Rural population Female
Male
Total 946,951 32,732,596
Population Density (persons per ALEGO USONGA 392
km2) by Sub-county GEM 465
UGENYA 435
UGUNJA 543
BONDO 346
Page 183
Information Category County Statistics National Average
(as at 2022) Statistics
RARIEDA 397
Incidence of landlessness (%)
Percentage of farmers with title deeds (%)
Mean holding size (in Acres)
Labour force by sector (No.) Agriculture: Male
Female
Intersex
Rural self-employment: Male
Female
Intersex
Urban self-employment: Male
Female
Intersex
Wage employment : Male
Female
Intersex
Unemployment levels (%) Male
Female
Intersex
Total
Total number of households 245,139 13,478,733
Average household size 4.2450 3.7558
Female headed households (%) 47.7 38.2
Child headed households (%) 0.5 0.5
Children with special needs Male
Female
Intersex
Total
Children in labour (No) Male
Female
Intersex
Total
Number of PWDs Visual 14,005 333,520
Hearing 6,861 153,361
Speech 3,336 111,355
Mobility 14,749 385,416
Mental 7,945 212,797
Other
Total 35,439 916,692
Orphans and Vulnerable children
(OVCs) (No.)
Number of street Families
Orphanages (No.)
Rescue centres (No.) 19
Gender Protection Units (No.)
Correction/rehabilitation facilities
(No.)
Page 185
Information Category County Statistics National Average
(as at 2022) Statistics
ICU Beds 6
Doctor/patient ratio Alego Usonga 1: 12,526
Bondo 1:20,053
Gem 1:68,126
Rarieda 1:170,952
Ugenya 1: 138,626
Ugunja 1:118,315
Laboratory Technicians
LEVEL 4 63
LEVEL 3 31
LEVEL 2 8
Page 187