LAPORAN HARIAN

NAMA PAKET : PROYEK PEMBANGUNAN JALAN TOL RUAS SEKSI SIMPANG INDRALAYA - PRABUMULIH ZONA 2
PEKERJAAN : COMMON BORROW MATERIAL (CBM)
AREA : 5 (Lima) dan 6 (Enam)
PIC : FRANKLIN SIDABUTAR, ST HARI / TANGGAL : Rabu, 17/02/2021
PANJANG AREA : STA. 17+400 sd STA. 23+300 MINGGU : -

A.URAIAN PEKERJAAN
NO STA PANJANG SAAT INI LAYER SD CUACA
URAIAN KERJA
DIV AWAL FINISH (M) VOLUME (M3) LAYER SAAT INI JAM CERAH HUJAN
RENCANA 06:00 - 07:00 x
1 CBM (R + L) 19 + 900.0 19 + 925.0 25 192.34 2 12 07:00 - 08:00 X
2 CBM (R + L) 19 + 925.0 20 + 025.0 100 730.04 2 11 08:00 - 09:00 X
3 CBM (R + L) 20 + 250.0 20 + 475.0 225 6,861.74 4 6 09:00 - 10:00 X
4 10:00 - 11:00 X
5 11:00 - 12:00 X
6 12:00 - 13:00 X
13:00 - 14:00 X
JUMLAH : 7,784.11 14:00 - 15:00 X
15:00 - 16:00 X
REALISASI 16:00 - 17:00 X
1 CBM (R + L) 19 + 375.0 19 + 400.0 25.0 183.69 1 11 17:00 - 18:00 X
19 + 400.0 19 + 450.0 50.0 376.45 1 13 18:00 - 19:00 X
19 + 450.0 19 + 475.0 25.0 197.41 1 15 19:00 - 20:00 X
20:00 - 21:00 X
2 CBM (R + L) 19 + 925.0 20 + 075.0 150.0 1,409.32 1 10 21:00 - 22:00 X
22:00 - 23:00 X
3 CBM (R + L) 20 + 250.0 20 + 350.0 100.0 1,823.22 2 4 23:00 - 24:00 X
4 CBM (R + L) 20 + 350.0 20 + 450.0 100.0 1,801.05 2 4 24:00 - 01:00 X
5 CBM (R + L) 20 + 450.0 20 + 500.0 50.0 871.30 2 4 01:00 - 02:00 X
02:00 - 03:00 X
03:00 - 04:00
04:00 - 05:00
05:00 - 06:00
JUMLAH : 6,662.44

HUJAN 7 Jam
B. SUMBERDAYA MANUSIA C. PEMAKAIAN PERALATAN CERAH Jam

CACAH / JAM KERJA Jam


NO. PERSONIL ORG KETERANGAN NO. JENIS SAT KETERANGAN
VOLUME
Masuk Kerja JUMLAH ALAT DI LAPANGAN (A)
1 Pelaksana 1 1 Dump Truck Unit 15.00
2 Ass. Pelaksana - 2 Smooth Drum / Vibro Roller Unit
3 Surveyor 2 3 Sheap Foot Unit 1.00
4 Quality Controil 2 4 Excavator Unit 1.00
5 Safetyman 1 5 Motor Grader Unit 1.00
6 Harian 3 6 Bulldozer Unit 1.00
7 7 Water tank Unit 1.00
8 8
Tidak Masuk 9
1 - - 10
2 - - JUMLAH ALAT DI QUARRY (B)
3 - - 1 Dump Truck
2 Smooth Drum / Vibro Roller
3 Sheap Foot
4 Excavator 2.00
5 Motor Grader
6 Bulldozer
7 Water tank
8
9
10
JUMLAH TOTAL ALAT ( C) = A + B
1 Dump Truck 15.00
2 Smooth Drum / Vibro Roller -
3 Sheap Foot 1.00
4 Excavator 3.00
5 Motor Grader 1.00
6 Bulldozer 1.00
7 Water tank 1.00
8
9
10

KONTRAKTOR PELAKSANA
PT. HUTAMA KARYA INFRASTRUKTUR
Jalan Tol Indralaya - Prabumulih Zona 2

Dibuat Oleh, Mengetahui,

FRANKLIN SIDABUTAR, ST …………………………………………..


Koordinator Pelaksana SOM