MZ-000-CCX-HS-PRO-00011 Control of Hazardous Energy Procedure Rev 0
MZ-000-CCX-HS-PRO-00011 Control of Hazardous Energy Procedure Rev 0
Project
Revision Date Description Prepared by: Reviewed by: Approved by: Approval
by:
Contractor
For Contract No. Contractor Document No.
Rev.
Contractor
Documents 0
LNG19-00079, SSF19-00080 000-PP-E-085006
Company Project System Originator Discipline Doc. Type Sequence Language Revision
Document
No. MZ 000 CCX HS PRO 00011 - 0
This document is Work Product under the EPC Agreement between ANADARKO
MOÇAMBIQUE AREA 1, LIMITADA (“AMA1”) and CCS JV S.c.a.r.l. (“CCS JV”).
All rights, title and interest in this Work Product, including any and all copyrights therein, are owned by
AMA1, except as reserved under the Agreement.
Uncontrolled if Printed
Mozambique LNG - 5.99 MTPA
Document Title: Control of Hazardous Energy Procedure
Document No. MZ-000-CCX-HS-PRO-00011
Rev. 0 Rev Date: 21-AUG-2019
This document has been originated starting from the FEED document No. EA-
All
MZ-SR0000-CCV-C01-00052-00 Rev.0
All Update all the reference documents according to the EPC MDR.
HOLD LOG
TABLE OF CONTENTS
1.0 INTRODUCTION ................................................................................................................. 6
1.1 Purpose ................................................................................................................................. 6
1.2 Scope .................................................................................................................................... 6
2.0 ABBREVIATIONS ............................................................................................................... 6
3.0 RESPONSIBILITIES ........................................................................................................... 7
3.1 General Responsibility ........................................................................................................... 8
3.2 Senior Authorised Electrical/Mechanical Representative........................................................ 8
3.3 Authorized Isolators / Tagging Authority................................................................................. 8
3.4 Permit Authority ..................................................................................................................... 9
3.5 LOTO Coordinator ................................................................................................................. 9
3.6 Person in Charge of Work .................................................................................................... 10
3.7 Permit Coordinator ............................................................................................................... 10
3.8 Work crews .......................................................................................................................... 11
3.9 Managers ............................................................................................................................. 11
3.10 General Foreman / Superintendents .................................................................................... 11
3.11 Supervisors (Foreman) ........................................................................................................ 12
4.0 PROCEDURE ................................................................................................................... 12
4.1 General ................................................................................................................................ 12
5.0 ISOLATION HEIRARCHY APPLIED TO ENERGIZED SYSTEMS ................................... 13
6.0 TAGS ................................................................................................................................ 13
6.1 Personal Danger Tag / Personal Lock.................................................................................. 13
6.2 Isolation Tags ...................................................................................................................... 14
6.3 Out of Service Tags ............................................................................................................. 15
6.4 Information Tags .................................................................................................................. 16
6.5 Commissioning Tags ........................................................................................................... 16
7.0 LOCKS.............................................................................................................................. 17
7.1 Isolation / Control Locks ....................................................................................................... 17
7.2 Red Authorized Isolators / Tagging Authority Isolation Locks ............................................... 17
7.3 Personal Locks. ................................................................................................................... 17
7.4 Yellow Permit /LOTO Office Lock (Control Lock). ................................................................ 17
7.5 Purple Locks – Boundary Isolations (Electrical & Mechanical) ............................................. 17
7.6 Blue Control Locks ............................................................................................................... 18
8.0 ISOLATIONS .................................................................................................................... 18
8.1 Types of Systems Requiring Lock-out / Tag-out and/or Blinding / Blanking .......................... 19
8.2 Use of Lockboxes. ............................................................................................................... 19
9.0 CONDUCTING ISOLATIONS ........................................................................................... 20
9.1 Electrically Operated Systems ............................................................................................. 20
9.2 Mechanically Operated Systems .......................................................................................... 21
9.3 Proving Isolations – Test / Try (Mechanical) – Verify zero pressure ..................................... 22
Uncontrolled if Printed Page 3 of 63
Mozambique LNG - 5.99 MTPA
Document Title: Control of Hazardous Energy Procedure
Document No. MZ-000-CCX-HS-PRO-00011
Rev. 0 Rev Date: 21-AUG-2019
1.0 INTRODUCTION
1.1 Purpose
The purpose of this procedure is to define the minimum CONTRACTOR requirements for the
control of hazardous energy and to provide direction for Isolation and Tagging of energy sources
in order to minimize any risk to personnel, the environment or equipment to ensure a safe system
of work is established and maintained.
1.2 Scope
This procedure applies to Isolation and Tagging of all potential energy sources (electrical,
mechanical, hydrostatic, pneumatic, pressure and gravity) and defines the requirements for
Isolation prior to working on any system with the potential to become live during any
Construction, Maintenance, and Commissioning or associated project infrastructure activities on
the Mozambique LNG Project.
This procedure is inclusive of vehicles, mobile plant, tools and equipment powered by energy.
Energy sources of 24 volts (AC/DC) and below do not require LOTO Office control – personal
isolation are to be recorded on Isolation Log (i.e. personal lock, removal and personal retention
of ignition key from mobile plan, etc.).
This procedure shall be read in conjunction with the CONTRACTOR Permit to Work Procedure
for Construction and Commissioning
2.0 ABBREVIATIONS
Abbreviation: Meaning:
AC Alternating Current
ACGIH American Conference of Governmental Industrial Hygienists
AGT Authorised Gas Tester
ALARP As Low as is Reasonably Practicable
ANSI American National Standards Institute
CCS JV Chiyoda, McDermott and Saipem Joint Venture
COHE Control of Hazardous Energy
CMS CONTRACTOR Management Systems
COMPANY Anadarko
CONTRACTOR CCS JV
CSE Confined Space Entry
CV Curriculum Vitae
DBB Double Block and Bleed
DC Direct Current
ELV Extra Low Voltage
JHEA Job Hazard Environmental Analysis
HSE Health, Safety and Environment
HV High Voltage
IEC International Electrotechnical Commission
IFC Issued for Construction
IP International Protection
LEL Lower Explosive Limit
LOTO Lock Out Tag Out
LV Low Voltage
MV Medium Voltage
NATA National Association of Testing Authorities
NFPA National Fire Protection Association
NOE Notice of Energisation
PIC Person in Control
PPE Personal Protective Equipment
PTW Permit to Work
SBB Single Block and Bleed
SIA Senior Isolating Authority
SIMOPS Simultaneous Operations
SLD Single Line Diagram
V Volts
WMS Work Method Statement
3.0 RESPONSIBILITIES
The following personnel have responsibilities defined in this procedure:
• CONTRACTOR Managers;
• CONTRACTOR Supervisors;
• CONTRACTOR Employees;
• SUBCONTRACTOR Managers;
• SUBCONTRACTOR Supervisors;
• SUBCONTRACTOR Employees.
signature from Senior Management authorizing competent person(s) retained for reference and
audit purposes.
Authorized Isolators / Tagging Authorities are responsible for identifying, in conjunction with the
Permit Coordinator, isolations required to ensure safe access to the work area, including:
• Conduct and/or verify the integrity of isolations prior to recording the completion of the
isolations on the Isolation Certificate;
• Test for dead and confirming isolations are effective shall be carried out by the Authorized
Isolator /Tagging Authority and verified by the second Authorized Isolator / Tagging
Authority;
• Conduct and/or verify the de-isolation of the electrical / mechanical isolation on the relevant
PTW form(s), Certificates;
• Comply with the requirements of this procedure and work in accordance with
CONTRACTOR Permit to Work Procedure, single line drawings with engineering stamp
showing issued for construction (IFC);
• Undertake the energization of systems as required by the NOE system;
• Ensuring that at local distribution panels, any local tagging of circuits matches the
arrangements shown on the isolation certificate.
issued up to close out by communicating with all authorized Isolators / Tagging Authorities
and carrying out regular checks on live Lockboxes;
• Verifying the person(s) requiring control / custody of Lockboxes and locks are trained and
competent to do so;
• Checking isolation certificates and PTW to ensure compliance with CONTRACTOR
Construction Permit to Work Procedure;
• Monitoring and review of compliance with this procedure.
Note: The responsibility for final authorization and approval for work to proceed is retained
by the Permit Coordinator and control lock may be used when necessary. Where a safety
system is to be inhibited, the Permit Coordinator will liaise with the operations crew for
approval to place the inhibitor. This will be followed up by requiring operations to approve
the appropriate safety system override certificate.
3.9 Managers
Managers are responsible for:
• Conducting risk assessment / Work Method Statement (WMS) for tasks associated with this
procedure and ensure the implementation of recommended controls;
• Provide all isolation equipment and verify that it is available and used in accordance with
this procedure;
• Verify control measures in accordance with this procedure are implemented for all work
under their control;
• Verify personnel required to instigate electrical / mechanical isolations meet CONTRACTOR
requirements and are approved by the relevant authority to perform their job scope;
• Arrange appropriate training;
• Audit the effective implementation of this procedure.
4.0 PROCEDURE
4.1 General
CONTRACTOR Manager(s) shall appoint competent specific line managers and supervisors
who are responsible for ensuring the requirements of this procedure and other relevant systems
are established, maintained, improved, and communicated to all personnel under their control.
Whenever persons could be endangered by the energization of plant or equipment (i.e. operation
of machinery, flow of steam, electricity, gas, liquids, or use of faulty equipment etc.), the
equipment / plant shall be isolated and the effectiveness of the isolation shall be verified, Test /
Try (equipment de-energized, drained and/or de-pressured) before attachment of ‘Personal
Danger’ Tags and Locks to Isolation Point(s) or Lockbox.
Testing and confirming isolations are effective, shall be carried out by the Authorized Isolator
/Tagging Authority and verified by the second Authorized Isolator / Tagging Authority. The
Authorized Isolator / Tagging Authority shall sign the work certificate to indicate the Test and Try
has been completed.
The competent person planning the isolation shall ensure that he/she accurately records on the
relevant documentation the equipment required to be isolated and its associated isolation point
as a minimum. This information shall be made available to the person conducting the isolation.
If an energy isolating device is not capable of being locked out, an isolation tag shall be placed
at the isolation point and noted on the Isolation Certificate. All attempts must be made by using
chains, wires etc. to provide a higher level of security over the isolation.
If an energy isolation device is capable of being locked out, a lock shall be used and the Lock-
out procedures shall be used.
Affected workers, where LOTO and/or blinding / blanking are performed, shall be made aware
of systems that are being worked on in their areas.
No persons shall work on equipment, regardless of the isolation process employed, without
being able to exercise personal control over the isolation and its de-isolation while working on
the equipment.
Knowingly relinquishing personal control over an isolation and/or de-isolation may lead to
disciplinary action up to and including removal from the project.
6.0 TAGS
Tags are for a single use only and shall not be reused, but destroyed immediately upon removal.
No alterations to a tag are permitted. Written information on tags shall be in waterproof
permanent marker.
Danger Tags and Personal Locks shall be removed and Danger Tags destroyed immediately
when the work has been completed or at the end of the workday by tearing the Personal Danger
Tag and placing it in a suitable waste bin.
If a job is left incomplete at the end of shift, all personnel working on the job shall remove their
Personal Lock and Personal Danger Tag. The Forman / Supervisor shall verify that all personnel
have removed their Personal Locks and Personal Danger Tags. The Forman / Supervisor shall
then return the PTW to the Permit Control Officer for relinquishment. NOTE: The main controlling
isolation will remain in place until the work is complete.
If someone applies a personal lock over an isolation, an additional Personal Danger Tag shall
be applied.
The Permit Holder upon completion of the work will then return the PTW to the Permit
Coordinator for relinquishment and the Permit Office will determine one of the following:
• The isolation can be completely removed, including all personal locks;
• Any personal locks can be removed but the isolation needs to remain in place with the
Authorized Isolator / Tagging Authorities lock(s) still in place;
• Isolations remain in place with personal locks in place where permit is to be renewed the
following day;
• If none of the above apply, the isolation may be transferred to the long term isolation log.
Under no circumstances shall personnel undertake rectification work on any equipment with an
‘Out of Service’ tag attached that is connected to operating plant power sources, without an
appropriate Isolation Certificate (for group isolations) and PTW being issued.
Out of Service Tags can only be removed by a competent person authorized to carry out repairs
or by a supervisor familiar with the equipment, when that person or supervisor has checked to
ensure that equipment or machinery is safe to be returned to service.
Equipment with an ‘Out of Service’ tag attached shall not be operated.
7.0 LOCKS
8.0 ISOLATIONS
Where practicable, Positive Isolations shall always be undertaken at the energy source and not
rely on such items as control circuitry (e.g. stop switches, interlocks, emergency stops, lanyards,
instrument air, etc.). These items shall not be used as a primary means of isolation.
All isolations are to be transferred downstream prior to removing Boundary Isolations and
energizing a switchboard or other distribution board.
Due consideration is to be taken when pipeline isolations are being carried out. See examples
below and Appendix 5 Figures 1 and 2:
• Systems may have to be put on by-pass or recycle;
• Low spots that may not drain down (pipe still holds product);
• Valves alone should not be considered as positive isolations. Due consideration shall be
given to the use of spades, spectacle blinds or blank flanges and double block and bleed
(DBB) with a spade used as positive isolation.
Positive Mechanical Isolations may require the removal of a spool, the insertion of a spade
and/or the use of blind flanges. Initial valve isolation and tagging and depressurizing / emptying
of pipe work prior to disconnection taking place. This involves, but is not limited to, the following:
• Physical breaks (e.g. removal of spool pieces) shall be effected as close to the vessel as
practicable;
• Blinds flanges of the correct specification will be applied to all open pipe ends connected to
live systems;
• The insertion of spades between two flanges;
• Drains / vents physically connected to the vessel or tank shall be positively isolated by the
use of blinds and/or spades of the correct specification.
For Positive Electrical Isolations the initial isolation, tagging, and lock out of the energy source
is required prior to a positive isolation. This can be achieved by, but not limited to, the following:
• The removal of links, fuses, circuit breakers and/or cable tails.
Since some equipment is wired with dual controls and locking out one pushbutton does not
render that equipment inoperable, after tag and lockout try start buttons to be certain disconnect
is complete.
NOTE: Panel Doors protecting employees from gaining entry to exposed energized equipment
shall be kept under a control lock at all times until the equipment is de-energized. The system
shall be Locked out and Tagged out and proven Zero energy before entry. All power houses /
distribution centres with doors having energized equipment shall remain locked at all times
Only Authorized employees can be granted entry. A log shall be kept for all that enter and exit
the equipment centres.
Entry / Exit Log - This record shall reflect the following:
• Name;
• Time of arrival;
• Craft/Discipline;
• Time of departure;
• Date.
Even with positive isolations, it may be necessary for persons working downstream to take
control over open ends to prevent inadvertent removal of the positive isolation.
The test equipment used shall be a minimum of CAT III Rated, NATA Certified, and in current
Calibration date. The test equipment shall be prior to each test and following each test to ensure
the validity of the actual test and the continued functionality of the test equipment.
• Test equipment shall be verified on a known live source before Verify Zero Voltage task is
carried out on the equipment;
• Once the competent person has confirmed the equipment is safe to work on, the test
equipment is to be re checked on the same known live source to verify correct operation.
No Boundary Isolation shall be removed from an electrical board; energizing the board without
a “Permit Office Checklist” (HOLD 1) being completed and approved by the CONTRACTOR
Electrical Authority and Permit Office. The same process applies to the removal of Red Spades.
Before issue of the permit to remove a Boundary Isolation, the checklist shall be reviewed and
signed by the CONTRACTOR Electrical or Mechanical SIA and Permit Coordinator.
Upon completion of works, before close out of the permit, an Authorized Isolator, Authorized
Verifier and Permit Coordinator shall ensure safeguards are in place.
The checklist verifies, upon the request to remove an isolation that:
For Pre- commissioning tests or temporary removal:
• Authority to Energize is part of the NOE process for identified system/apparatus is approved
(if scope includes energization), where it is energized for the first time;
• Upstream and/or downstream isolations are in place and verified if required;
• Isolations removed during pre-commissioning testing activities are reinstated upon
completion of the task before the permit can be relinquished / closed. A new isolation tag
is to be installed by the Authorized Isolator / Tagging Authority.
For Energization:
• Isolation Locks are in place and verified on incomplete downstream scope of work for
systems/apparatus;
• Authority to Energize Certificate for identified system / apparatus is approved.
Subsequent final energization of outgoing circuits shall be managed individually through the
Notice of Energization Procedure MZ-000-CCX-HS-PRO-00026, and the Boundary Isolation
being modified accordingly and verified before any outgoing circuits are energized.
Boundary Isolations may be undertaken by CONTRACTOR isolators.
In pipework systems, the Boundary Isolation point takes the form of a ‘red spade’ isolation.
Where possible, utilization of red spades for isolation purposes where there exists practicable
isolation points closer to the work-front should not be undertaken. Where utilization of a red
spade for isolation purposes is required, approval from the relevant SIA is required.
Personnel may work under a single isolation provided they apply their own personal locks to the
hasp, and they have observed and understood that the isolation is correct.
Where a lockbox is used, the isolation lock key shall be placed inside the lockbox.
The Lockbox can only be in the custody of the PTW Office or an Authorized Isolator / Tagging
Authority.
Note 1: No isolations can be removed until any associated permits have been cancelled
by the person in charge of the work, once isolation has been removed, the PTW office
will close out the permit.
Note 2: HV Switching program development and sign off is peer to peer, same
authorization level, or above.
10.0 TESTING
There are situations where testing requires the removal and re-instatement of isolations for short
durations while testing takes place. This will be managed in the following manner:
10.1.1 On all systems, regardless of their completion status where a hazardous energy
is introduced into a system, the requirements set out in this section shall be
followed.
• All work will be under the control of a PTW;
• Any other PTW’s relevant to the system being tested will be suspended/withdrawn;
• A fully trained and authorized Tagging Authority will be allocated to work with the crew.
Tagging Authorities are appointed by Senior Management but will be further approved by
the LOTO Office. See Section 16 regarding authorization process;
• The PTW application will be accompanied by a Mechanical and/or Electrical Isolation list
(sanction to test section) defining those isolations which will:
o Be locked and tagged and will remain in LOTO status throughout the test. Such
isolation points will be locked using red isolation locks and be placed prior to the
test;
o Will be required to be adjusted during the test and will be managed by the crew
Tagging Authority using control locks, colored either Brass or Green depending
upon whether the system is under Commissioning or Construction control. These
are also to be in place prior to the start of the test;
o The nominated Tagging Authority for the test will be required to discuss the
isolation/control plan with the LOTO Office in order for the Isolation Control
Certificate to be registered and signed by the LOTO Office.
• The relevant system owners must approve the testing work to commence on their system
by approving the Isolation Control Certificate;
• The person in charge of the work must walk down the system and verify the positions of all
isolation and control locks. Crew members are required to apply personal locks to isolation
locks only;
• Throughout the testing period, isolation status changes under control locks must be
documented on the Isolation List at all times;
• Upon completion of the test, the Tagging Authority must return all isolation points to their
original status prior to closure of the Isolation List;
• The person in charge of the work must verify final isolation point status before closing the
PTW;
• The LOTO office will assign a Tagging Authority to remove the control and isolation locks
from the system if not pre agreed for the testing team to do so.
All cores of the cable, where practicable are to be connected to the cable earth conductor, by
means of terminal strip or connectors.
The supply end is to be isolated from the supply distribution board. If the supply end is already
de-energized, i.e. the source is isolated upstream, a personal isolation lock is to be applied to
the supply Cabinet Hasp / Lockbox and reference to the upstream isolation point made on the
isolation certificate by an approved Isolation Authority / Tagging Authority.
• Area shall be flagged off and personal in the area to be notified of the activity;
• A Commissioning Work Permit will be required for the task.
If you are required to work in a panel with live circuits and not all terminals are IP 2X rated, the
following shall apply:
• Follow NFPA 70E Guidelines and include barriers over the non IP rated equipment and use
of IP rated tools, rubber mats, etc.;
• Barriers to be of a non-conductive type and compliant with the American National Standards
Institute (ANSI)/ International Electrotechnical Commission (IEC) 60529-2004.
Refer to Appendix 6 for Degrees of Protection against access to hazardous parts.
13.1 Access into Junction boxes / equipment with energized ELV Cables only.
If an ELV Junction Box / Equipment is required to be open to carry out fault finding, inspection,
tightness checks, instrument loop checks or minor rectifications work the following shall apply:
• An assessment of the associated risks shall be made. The risk assessment (JHEA) shall
include, but not be limited to, the determination as to whether the use of suitable barriers or
a safety observer is required;
• Isolations will not be required unless identified during the risk assessment before work is
started;
• Workers shall be competent in the work to be carried out;
• Precautions shall be taken, or procedures put into place to prevent the possibility of
simultaneous contact with conductors at different voltages or to earth;
• Personal protective equipment (PPE) that is appropriate and suitable for the task shall be
worn. PPE shall be of correct fit and in good condition.
• The Emergency Lock Out Device Removal Form shall be completed and signed prior to
removal;
• The Tagging Authority, the Commissioning Startup Supervisor, and Area Operator (as
required), shall remove all safety tags and locks;
• The Tagging Authority shall close the LOTO PTW after ensuring that all tags, locks, and
keys have been returned and that special protective measures have been restored;
• The Tagging Authority shall identify the PTW as an emergency closure, destroy the tags,
file the closed PTW, and file locks and keys for future use;
• The Supervisor of the unavailable Permit Requestor or Authorized Employee shall notify the
unavailable Permit Requester or Authorized Employee of the emergency closure upon
his/her return, prior to start of work.
To implement an emergency change:
• All available Requestors (Permit and Supplemental) shall approve the PTW change by
signing the LOTO PTW and all authorized employees shall be physically accounted for;
• The supervisor of the unavailable Requestor(s) shall ensure that authorized employees
working under the PTW held by the unavailable Requestor are physically accounted for,
either by removing their tag from the Lockbox, or by signing the LOTO PTW;
• The Tagging Authority and the Area Construction Manager/Commissioning Startup
Manager (or designee) shall approve the emergency change;
• The Tagging Authority, Commissioning Startup Supervisor, shall modify all safety tags and
locks and system configuration to incorporate the change;
• The Tagging Authority shall identify the PTW as an emergency change;
• The Tagging Authority shall notify the Permit Requester of the emergency changes;
• The Supervisor of the unavailable Permit Requester shall notify the unavailable Permit
Requester or Authorized Employee(s) of the emergency change upon his/her return and
shall ensure that the Permit Requester or authorized employee sign the changed LOTO
PTW or hang their tag on the Lockbox prior to restarting work;
• If an emergency change/closure is not issued, all work within the PTW scope shall be
discontinued until the LOTO PTW can be closed or changed by the standard closure/change
procedure.
An alternative to applying a red spade is a Double Block and Bleed (DBB) arrangement. In
applying a DBB, the facility must have an approved ‘Redsheet’ authorizing the use of this
alternative isolation method. See diagram below.
16.1 Electrical
The process for authorization of proposed Isolators on the Project is for relevant Isolators to
present to the SIA the following evidence of competence:
ELV (<50V) LV (<1000v AC) HV (>1000 v AC) Mechanical
Current CV Current CV Current CV Current CV
NFPA 70Electrical NFPA 70Electrical NFPA 70Electrical Trade certificates
CONTRACTOR CONTRACTOR CONTRACTOR CONTRACTOR LOTO/COHE
LOTO/COHE LOTO/COHE LOTO/COHE
Isolating experience HV Switching Experience Mechanical Isolation experience
Instrument Qualification Electrical License Electrical License
CONTRACTOR Management are then responsible for ensuring that the proposed Isolator has
the required Level of qualifications and experience.
16.2 Mechanical
The process for authorization of proposed Authorized Mechanical Isolators on the Project is for
the relevant CONTRACTOR Management to provide the following to the SIA.
• Evidence of previous experience as a mechanical / process isolator;
• Evidence of appointment at the level of Foreman either currently or in the past working on
piping systems.
Once evidence is available the applicant can be scheduled to undertake a written and practical
Assessment.
Based on the assessments and previous experience, the SIA will approve the appointment which
will then be recorded in the Isolators register.
The PTW office will have access to the most up to date version of the Isolators register.
For testing purposes, the PIC of the testing will apply for the appropriate PTW in accordance
with the requirements set out for ‘sanction to test’.
The equipment to be tested and energized is to be barricaded and labelled to indicate that the
equipment is to be energized. “Electrical or Mechanical Testing / Energization on-going. Only
authorized entry allowed”.
No person may enter the testing area other than those signed onto the controlling PTW.
The PIC of the work shall be present at all times during testing and energization.
Testing personnel may operate the main power supply isolator and associated control supplies
as detailed and in accordance with the PTW. The main power supply isolator may be located
outside the testing area (i.e. substations, Power houses etc.). Rotating equipment that has been
disconnected should be subject to a rotation check as part of the re-energization process.
17.1 General
The PTW Coordinator, in conjunction with the Lock out/Tag Out (LOTO) Coordinator, will
conduct regular reviews of the LOTO process. The ‘Checklist for Monitoring of Isolations’ at
Appendix 14 will be used for this purpose. On a daily basis the PTW Coordinator and LOTO
Coordinator will determine the isolation reviews to be conducted during that working day and will
assign the relevant resources accordingly. No Tagging Authority will be allowed to review his
own work. The frequency of such reviews will be as follows:
17.2 Records
Records of all reviews will be maintained in a logbook held by the LOTO Coordinator.
19.0 APPENDIXES
19.1 Appendix 1: Carbon Steel Blanks - (16.1 ksi stress - ASTM A283-C/A36)
19.2 Appendix 2: Stainless Steel Blanks - (20 ksi stress - ASTM A240 type 304/316)
19.3 Appendix 3: Minimum Temperature for Blanks W/O Impact Testing - (A283 C/A36)
Figure 1.0
CONTRACTOR personnel shall not be permitted to work on any structure or pipeline unless it
is physically isolated from potential sources of energy and contamination and is clean1 and gas
free2. A FREE AIR SPACE as shown in Figure 1.0 is the preferred method of blinding. All blinds
shall be ASME 16.5/16.47 matching the flange class and diameter. The blind shall be installed
with a single gasket and a tag attached meeting the requirements of this procedure.
Caution: On pipelines containing an expansion joint, qualified/responsible engineer shall
approve the method of isolation before the disconnection is made.
When the physical isolation method shown in Figure 1.0 is not possible, an alternate method is
shown in Figure 2.0.
Figure 2.0
The use of the Figure 2.0 isolation method requires the following:
• Authorization by the local Operations or Construction Manager and local HSE Manager.
Prior to installation of the blank, it shall be examined by a qualified CONTRACTOR
employee to determine that it is appropriate for the application and service, and to confirm
it is installed in the correct location.
• In addition, a qualified CONTRACTOR employee shall confirm the blank is installed correctly
with Gaskets on each side and a tag is attached meeting the requirements of this procedure.
• For isolation exceptions in which appropriately sized blanks cannot be installed, approval
shall be obtained from Corporate HSE using the Extra Hazardous and Repair Work Report
form. Isolation exceptions will only be considered when an Extra Hazardous and Repair
Work Report and a written Safety Plan/procedure is completed and submitted to Corporate
HSE.
• The safety plan/procedure shall provide adequate safety supervision to control potential
hazards. (A minimum of one full time safety supervisor is required). Additional supervisors
may be required to insure complete control of safety on large turnarounds, special projects,
process facilities, etc. This safety supervision shall be furnished by CONTRACTOR.
CONTRACTOR personnel shall not be permitted to work on any structure or pipeline unless it
is physically isolated from potential sources of energy and contamination and is clean1 and gas
free2.
• 1CLEAN – No product residue on surfaces (i.e. tank shell, bottom, sump, nozzles, valves,
columns, rafter, roof, or pipe, pipe components, etc.).
• 2GAS FREE – Atmosphere with less than 1% of the Lower Explosive Limit (LEL), 19.5% to
23.5% Oxygen, and less than the permissible exposure limits and the threshold limit values
as required by OSHA and ACGIH.
The following isolation standards for Mechanical systems may apply to the project following
corporate approval being obtained.
0 Non-protected – –
1 Protected against access to The access probe, sphere of 50 mm 12.2
hazardous parts with the , shall have adequate clearance
back of a hand from
hazardous parts
19.8 Appendix 8: Isolation Hierarchy – More than 24V DC, Less than 50V DC
19.9 Appendix 9: Isolation Hierarchy – More than 50V DC, Less than 1000V AC
Doc# 10000000000000000 A B C D E A B C D E
# UNIT, BRK, PERMIT NUMBER LOCK LOCK LOCK LOCK LOCK LOCK LOCK LOCK LOCK LOCK
LOCK EQUIPMENT ID BUCKET# DEVICE, CIR. # ON Int. OFF Int. ON Int. OFF Int. ON Int. OFF Int. ON Int. OFF Int. ON Int. OFF Int.