NGC M5-R6 - Phase 2 Quadrant 3 RFI

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Project Title

Meadows Mechanical General Task List


Mechanical Pre-planning Tasking List - Detailed Activity

Anticipated Start TBD Anticipated Completion TBD


Space Serving Phase 2 Quadrant 3 Noise Level (1-3) 2

Services Affected Shut Down Tie-In Shut Down Tie-In


Domestic Water Nitrogen
Waste & Vent Oxygen
Underground Service Nitrous Oxide
Storm Medical Air
Ductwork Medical Vacuum
Heating HW CDA
Chilled Water Fire Protection - Sprinkler
Nat. Gas Fire Protection - Alarm
Fuel Oil Temperature Controls
High Pressure Steam Electrical
Low Pressure Steam Pumped Condensate

Safety Control Task Precautions - Level -


Considerations Temp/Poly Barrier Smoke Alarm
Drywall Barrier Fire Watch
Negative Airflow Traffic Control
HEPA Filter Vibration
Airborne Particle Sampling Handwashing Sinks
Lock Out/Tag Out Hot Work Permit
Fire Stopping

General Ladder
Construction Scaffold
Items Drills
Hand Tools
PPE

"Project Specific"
Items

Project Contacts Wyatt Saice 310-463-6258


Electrical Items N/A

Sequence of 1- Shutdown unit feeding ductwork in location (by others)


Construction 2- Erect scaffold (by others)
3- Remove ductwork in way of piping
4- Remove drain piping
5- Plug the roof drain
6- Reinstall ductwork
7- Patch any holes in ductwork neccesary
8- Turn unit(s) back on (by others)

Total time- 2 days

Areas Affected Phase 2- Quadrant 3

Attachments

Point of Contact Wyatt Saice 310-463-6258

Comments

By:

You might also like