INFRA DEPARTMENT
MEYNARD L. ASPA
Student Trainee
THE ASSIGNED UNIT
INFRA DEPARTMENT
Operation they operate the cooling system, water and air supply of the SEMPHIL. In
into 3 the Mechanical, Civil and Electrical. In mechanical it’s handle the ducting of the
exhaust and ahu supply air ducting, piping’s of the water and air. In electrical it is the one
that work the electrical wiring of the new projects and the internet cables of the
SEMPHIL. And in the planning they are the one that checks the updates of as-built of the
buildings and manage the cost or estimate the new projects that has been approved of
Mechanics Philippines, Corps, before getting approved for our individual departments
and processes. The opening three days of the orientation program offered by the HR
the fundamental laws, security, and health protocols. The Safety, Health, and
Environment (SHE) group discusses Occupational Safety and Health (OSH) on the
second day of orientation. It is important for the company, each other because it was
mandated by RA 110581 and because it ensures the safety of every single employee. It
cite the fact that they created a list of things to prevent and installed safety guards on
each machine for several forms of safety, such as fire safety, chemical safety, and
machine safety.
After the orientation it was the exciting part of the OJT time for our endorsement
in our designated department and process. I was endorse in the Infra Department, first
we met Sir Jayson the department manager of the Infra department welcome us and
introduced us to our supervisors and our mentor technicians. In our first month we are
to the supervisors and technician. They teach us the diagram of how the cooling system
works and familiarize the machines and equipment’s that they use. The cooling system
is compose of cooling tower, turbo chiller, and AHU (Air Handling Unit) & MAU (Make-
up Air Unit). The work cooling tower is remove the heat of the water and the turbo chiller
the one that makes the chilled water and the chilled water it goes to the Ahu & Mau that
makes a cool air that supply the building of SEMPHIL. They also teach us the parts of
turbo chiller they are the condenser, evaporator, compressor, control panel and
expansion valve. They also teach the difference between Ahu & Mau, the Ahu has a
return supply air from the production and the Mau does not have a return supply air.
The parts of the two are the same they are copper tube, fan blower and air pre & final
filter. The everyday task that given to me is checking and monitoring the data
parameters of the turbo chiller, cooling tower, pumps and the supply pressure of the
chilled water, we monitor it hourly to check if the equipment’s reach the assigned set
point and need to be add another backup equipment. I am also assigned in the
maintenance of the Ahu and Mau, the task here is when there is a call from the
production that need to adjust the room temperature, we are the one who fix that and
also the maintenance of them like changing the belt of the motor fan blower and
cleaning the filter of Ahu and Mau. The second month of our OJT I was assigned in the
projects; Ms. Emelyn introduce me to sir Herson the supervisor of the mechanical
projects. My first week here is just familiarization of the mechanical project that they are
working and Sir Herson introduced me to the contractors, they are the ones who work
the given mechanical projects. My daily task in here is check the updates of the
of it and make a report of the job done and findings and submit it to Sir Herson. And the
third or last month of my OJT I was assigned in planning, I was introduced to Sir
Raymund he is the supervisor and Ma’am Shanelle, Ma’am Kate and Ma’am Maris they
are the ones who give us task to do. Our task that we do is check the as-built of all the
building in SEMPHIL and also updates the locations of the CCTV, emergency light and
exit, smoke detector, speaker and fire alarms of all the building in SEMPHIL.
system of SEMPHIL and maintaining a clean, safe and secure working environment of
all employees. I also familiarized all process in all the building in SEMPHIL, Data
training, such gathering of data parameters and maintenance of the machine and
equipment also learning how the cooling system of Samsung works, learn some
electrical circuit sequence, analytical skills, analyzing the floor plan of SEMPHIL, and
Being one of the technologist student and a machinist student I can say that our
knowledge that we gain from school is our advantage wherein I can easily understand
some functions of the machine and how to work with it also the tools and its function in
repairing.
I totally appreciate this training program such it helps me a lot on how to live
outside the box of not being a student anymore that I am entering a new level of life.
RECOMMENDATIONS
Based on what I've learned, I recommend that the agency base the trainee's
course and competence on their assignment area. This is not a significant problem,
though, because we are gaining new knowledge and skills that are not taught at our
school.
The would-be student-trainees, if they want to make the most of the training
experience
I highly endorse this company since it will provide them the opportunity to work
on a real project that will complement their studies, just like I did in the infrastructure
departments.
The faculty members handling the course to further improve learning experience
I would suggest the faculty to improve the curriculum for courses that would be
more effective in training. If at all possible, include classes on new and sophisticated
technology.