RIGGER LOG

Project: ____________________________ Address: ____________________________ Prime: ______________________________________


Rigger Name (print):

Type: Model: Serial Number:


Week Start Date: Week End Date: Year:
Inspect Daily M T W Th F Sa Su
Radios
Pigtails
Shackles
Chains
Slings
***Load block, connection of hook
**Inspect GFCI lighting
WEEKLY VISUAL INSPECTION 1st Wk 2nd Wk 3rd Wk 4th Wk 5th Wk
A-frame
*Gang form lifting cable/point
TASK INSPECTIONS – every time used or weekly
visually check the following
CONCRETE
Bucket condition
Bucket operation
Washout Box condition
Truck Ramps
EQUIPMENT
Garbage Box condition & Capacity
Bolt Box condition
Nail Box condition
Job Box condition
Form Oil Container condition
Outrigger condition
Formwork Panels
Safety Box

* Lifting cables must be re-torqued after one (1) week of service and then every three (3) months.
** If GFCI is installed for crane power it should be checked at regular intervals during the shift.
*** Coordinate with crane operator.
Maintenance Required/Completed:

Comments:
______________________________________________________________________________________________________________
______________________________________________________________________________________________________________
_____________
______________________________________________________________________________________________________________
__________
______________________________________________________________________________________________________________
__________
______________________________________________________________________________________________________________
_____________
______________________________________________________________________________________________________________
__________
SUPERVISOR REVIEWED RIGGER HSE ADVISOR