Professional Documents
Culture Documents
CH 03 Preliminary Costs
CH 03 Preliminary Costs
, . . . ..
.. .
Vancouver, B. C .
Canada
ABSTRACT
INTRODUCTION
*
Currently under r e v i s i o n and expansion.
.PRELIMINARY C A P I T A L COSTS
a r e c o n s t a n t s . Such c o s t d a t a a r e u s e f u l t o e s t i m a t e t h e q t o t a l c o s t
of a processing p l a n t . .,
The c o s t equations i n t h i s chapter have a t l e a s t one t h i n g i n
common. Each was developed from p r i c e s a d j u s t e d t o a common cost
-
index value, namely, t h e Marshall & Swift index (Mining and Milling)
of 300. Towards t h e end of t h e c h a p t e r , t h e equations a r e employed
t o e s t i m a t e t h e c a p i t a l c o s t of a p l a n t from a rough flowsheet. B u t .
f i r s t , b e f o r e c a p i t a l c o s t e s t i m a t i o n s a r e considered, t h e n a t u r e and
u t i l i t y of c o s t i n d i c e s i s reviewed.
COST INDICES
Jan
Feb
Mar
A P ~
May
June
July
Aug
Sept
Oct
Nov
Dec
. .
CAPITAL'COST ESTIMATION
, .
The t o t a l c a p i t a l investment i n a mineral processing p l a n t con-
s i s t s of a fixed c a p i t a l p o r t i o n and a working.capita2 p o r t i o n . ' The
f i x e d c a p i t a l c o s t p o r t i o n i s t h e t o t a l amount of money needed t o pur-
chase t h e necessary p l a n t and a u x i l i a r y p l a n t f a c i l i t i e s . The work-
ing c a p i t a l c o s t p o r t i o n r e p r e s e n t s cash t h a t must be a v a i l a b l e t o be-
g i n t h e o p e r a t i o n . Of major importance i s t h e f a c t t h a t t h e t o t a l
c a p i t a l investment i s a sum t h a t i s s e p a r a t e from t h e t o t a l product
c o s t p a i d o u t p e r u n i t time from gross income p e r u n i t time. . T o t a l
product c o s t s include operating c o s t s such as d i r e c t production c o s t s ,
f i x e d charges and p l a n t overhead, and general expenses such as admin-
i s t r a t i v e c o s t s , d i s t r i b u t i o n and marketing c o s t s , research and dev-
elopment c o s t s and gross earnings expenses.
i n e e r s . These a r e :
1. Order-of -magnitude e s t i m a t e based on previous c o s t data,. I t is a
r a t i o e s t i m a t e of more than +30 percent probable accuracy.
2. Factored e s t i m a t e based on major equipment c o s t s with a probable
accuracy of +30 p e r c e n t .
3 . Budget a u t h o r i z a t i o n e s t i m a t e (preliminary e s t i m a t e ) based on
s u f f i c i e n t d a t a t o permit budgeting. Probable accuracy is +20 %.
.PRELIMINARY CAPITAL COSTS. 57
4 . D e f i n i t i v e o r p r o j e c t c o n t r o l e s t i m a t e based on almost complete
d a t a (no s p e c i f i c a t i o n s o r complete drawings). Probable accuracy i s
-110 p e r c e n t .
5. Detailed o r c o n t r a c t o r ' s e s t i m a t e based on complete engineering
drawings, s p e c i f i c a t i o n s , and s i t e surveys. Probable accuracy i s
?5 p e r c e n t .
6
(cost) = 60x10 (40,000/30,000) O e 6
6
= $ 7 1 . 3 ~ 1 0 a t a cost index of 303
To update t h e c o s t , t h e c u r r e n t , cost index must be employed. Table 2
shows t h a t t h e index a t t h e beginning of 1977 must be c l o s e t o 497.
Hence,
6
(cost)now = 7 1 . 3 ~ 1 0 (497/303)
= $117x106 . ' .
The exponent, 6/10, i s an average and depends on t h e type of ,
p l a n t . Such f a c t o r s a s type of s i t e , economic conditions p r e v a l e n t ,
geographic location and regional p r o d u c t i v i t y a r e responsible f o r a
substantial variation.
The c o s t of t h e t o t a l p l a n t i s c a l c u l a t e d from
cost = 2 F ~ X ~
-.-
,
. Manufacturers of mineral processing equipment were contacted and
e
c o s t = 132(diameter) 0.91
. .
.
'
,
. %
Chain
REPORT
. Item $ Cost
Conveyor b e l t s 535,000
Vibrating feeders 142,000
Surge b i n s 81 ,'OOO
Vibrating screens 150,000
Crusher motors 91,000
Cone crushers 1,380,000
Dust c o l l e c t o r s 123,000
REFERENCES