Critical Path Critical Path
Critical Path Critical Path
Title: Plate #6 Float Calculation for CPM Subject: CE412 – Contr. Method & Project Mgmt.
ACTIVITY
EARLY EARLY LATE LATE
NUMBER DURATION TOTAL
START FINISH START FINISH
ARROW (DAYS) FLOAT
(ES) (EF) (LS) (LF)
DIAGRAM
Critical
1−2 2 0 2 0 2 0
Path
Critical
2−3 1 2 3 2 3 0
Path
2−5 1 2 3 5 6 3
Critical
3−4 2 3 5 3 5 0
Path
4–6 3 5 8 7 10 2
Critical
4–7 3 5 8 5 8 0
Path
5–6 4 3 7 6 10 3
6–8 2 8 10 10 12 2
Critical
7–8 4 8 12 8 12 0
Path
Critical
8–9 2 12 14 12 14 0
Path
9 – 10 3 14 17 19 22 5
Critical
9 – 11 4 14 18 14 18 0
Path
10 – 13 2 17 19 22 24 5
Critical
11 – 12 5 18 23 18 23 0
Path
Critical
12 – 14 3 23 26 23 26 0
Path
13 – 14 2 19 21 24 26 5
Critical
14 – 15 8 26 34 26 34 0
Path
14 – 15 6 26 32 28 34 2
Critical
15 – 16 3 34 37 34 37 0
Path
Critical
16 – 17 2 37 39 37 39 0
Path
17 – 18 2 39 41 42 44 3
Critical
17 – 19 3 39 42 39 42 0
Path
18 – 20 2 41 43 44 46 3
Critical
19 – 20 4 42 46 42 46 0
Path
Critical
20 – 21 1 46 47 46 47 0
Path
Critical
21 – 22 5 47 52 47 52 0
Path
Critical
22 – 23 6 52 58 52 58 0
Path
Critical
23 – 24 3 58 61 58 61 0
Path
23 – 24 2 58 60 59 61 1
Critical
24 – 25 6 61 67 61 67 0
Path
Critical
25 – 26 2 67 69 67 69 0
Path
Critical
26 – 27 6 69 75 69 75 0
Path
26 – 27 3 69 72 72 75 3
Critical
27 – 28 4 75 79 75 79 0
Path
Critical
28 – 29 2 79 81 79 81 0
Path
Critical
29 – 30 4 81 85 81 85 0
Path
29 – 31 6 81 87 82 88 1
Critical
30 – 32 7 85 92 85 92 0
Path
31 – 32 4 87 91 88 92 1
31 – 32 3 87 90 89 92 2
Critical
32 – 33 2 92 94 92 94 0
Path
Critical
33 – 34 1 94 95 94 95 0
Path
34 – 35 7 95 102 96 103 1
Critical
34 – 37 12 95 107 95 107 0
Path
Critical
37 – 38 10 107 117 107 117 0
Path
Critical
38 – 39 3 117 120 117 120 0
Path
Critical
39 – 40 4 120 124 120 124 0
Path
Critical
40 – 41 3 124 127 124 127 0
Path
Critical
41 – 42 8 127 135 127 135 0
Path
Critical
42 – 43 14 135 149 135 149 0
Path
Critical
43 – 44 2 149 151 149 151 0
Path
(1) Foreman/Leadman
(1) Dump truck
(1) Operator
1. Mobilization 82,800 2 (1) Backhoe
(2) Driver
(4) Laborers
(1) Foreman/Leadman
2. Land/Site Clearing 22,000 1 (1) Operator (1) Backhoe
(2) Laborers
(1) Foreman/Leadman
3. Layout 3,900 2 (1) Carpenter
(2) Laborers
(1) Foreman/Leadman
4. Construction of
2,450 1 (2) Carpenters
Bunkhouse
(2) Laborers
(1) Foreman/Leadman
5. Excavation of (1) Backhoe
66,000 3 (1) Operator
Footings
(2) Laborers
(1) Foreman/Leadman
6. Lean Concreting 8,300 2 (3) Mason (1) Bagger Mixer
(2) Laborers
(1) Foreman/Leadman
7. Excavation of Tie
72,000 4 (1) Operator (1) Backhoe
Beams
(2) Laborers
8. Fabrication of (1) Foreman/Leadman
(1) Bar Cutter/Cut-
Column Footing 9,450 3 (2) Steelman
off Machine
Rebars
(1) Foreman/Leadman
9. Installation of Column (1) Bar Cutter/Cut-
16,200 4 (3) Steelman
Footing Rebars off Machine
(1) Laborers
(1) Foreman/Leadman
10. Concreting of Column
9,700 2 (3) Mason (1) Bagger Mixer
Footing
(3) Laborers
(1) Foreman/Leadman
11. Fabrication of Tie (1) Bar Cutter/Cut-
7,950 3 (1) Steelman
Beam Rebars off Machine
(1) Foreman/Leadman
12. Fabrication of Tie
10,200 4 (1) Carpenter (1) Jigsaw
Beam Forms
(1) Laborer
(1) Foreman/Leadman
13. Installation of Tie (1) Bar Cutter/Cut-
7,100 2 (2) Steelman
Beam Rebars off Machine
(1) Laborer
(1) Foreman/Leadman
14. Installation of Tie
15,250 5 (2) Carpenter (1) Jigsaw
Beam Forms
(1) Laborer
15. Installation of (1) Foreman/Leadman
Scaffoldings @ 11,850 3 (3) Carpenter (1) Jigsaw
Ground Floor (2) Laborer
(1) Foreman/Leadman
(4) Mason
16. Concreting of Tie (1) Bagger Mixer
13,300 2 (2) Laborers
Beams (1) Vibrator
(1) Heavy Tool
Operator
17. Fabrication & (1) Foreman/Leadman
(2) Bar Cutter/Cut-
Installation of Column 50,800 8 (3) Steelman
off Machine
Rebars @ G.F. (3) Laborer
18. Fabrication & (1) Foreman/Leadman
Installation of Column 29,700 6 (3) Carpenter (2) Jigsaw
Forms @ G.F. (2) Laborer
(1) Foreman/Leadman
(4) Mason
19. Concreting of (1) Bagger Mixer
21,150 3 (3) Laborer
Columns @ G. F (1) Vibrator
(1) Heavy Tool
Operator
(1) Foreman/Leadman
20. Backfill 44,700 2 (1) Operator (1) Backhoe
(3) Laborer
21. Installation of (1) Foreman/Leadman
Electrical Roughing- 5,700 2 (2) Electrician
Ins @ G.F. (2) Laborer
22. Installation of (1) Foreman/Leadman
Plumbing Roughing- 5,700 2 (2) Plumber
Ins @ G.F. (2) Laborer
(1) Foreman/Leadman
23. Fabrication of Ground (1) Bar Cutter/Cut-
9,450 3 (2) Steelman
Floor Slab Rebars off Machine
(1) Foreman/Leadman
24. Installation of Ground (1) Bar Cutter/Cut-
17,400 4 (2) Steelman
Floor Slab Rebars off Machine
(3) Laborer
(1) Foreman/Leadman
25. Concreting of Ground
5,150 1 (5) Mason
Floor Slab
(5) Laborer
26. Fabrication & (1) Foreman/Leadman
(2) Bar Cutter/Cut-
Installation of Mid- 29,250 5 (2) Steelman
off Machine
Beam Rebars (3) Laborer
27. Fabrication & (1) Foreman/Leadman
(2) Bar Cutter/Cut-
Installation of Slab 35,700 6 (3) Steelman
off Machine
Rebars (2) Laborer
28. Installation of (1) Foreman/Leadman
Plumbing Roughing- 9,750 3 (2) Plumber
Ins @ 2nd Floor (3) Laborer
29. Installation of (1) Foreman/Leadman
Electrical Roughing- 6,500 2 (2) Electrician
Ins @ 2nd Floor (3) Laborer
30. Fabrication & (1) Foreman/Leadman
Installation of Mid- 48,300 6 (6) Carpenters (2) Jigsaw
Beam & Slab Forms (6) Laborers
(1) Foreman/Leadman
31. Concreting of Mid- (1) Bagger Mixer
25,300 2 (6) Mason
Beam & Slab (1) Vibrator
(12) Laborer
32. Fabrication & (1) Foreman/Leadman
(2) Bar Cutter/Cut-
Installation of Column 43,500 6 (4) Steelman
off Machine
Rebars @ 2nd Floor (4) Laborer
33. Installation of (1) Foreman/Leadman
Scaffoldings @ 2nd 11,550 3 (4) Steelman
Floor (3) Laborer
34. Fabrication & (1) Foreman/Leadman
Installation of Column 23,400 4 (4) Carpenters (2) Jigsaw
Forms @ 2nd Floor (3) Laborers
(1) Foreman/Leadman
(5) Mason
35. Concreting of (1) Bagger Mixer
16,700 2 (5) Laborer
Columns @ 2nd Floor (1) Vibrator
(1) Heavy Tool
Operator
36. Fabrication & (1) Foreman/Leadman
(2) Bar Cutter/Cut-
Installation of Roof 25,400 4 (3) Steelman
off Machine
Beam Rebars (3) Laborer
37. Fabrication & (1) Foreman/Leadman
(2) Bar Cutter/Cut-
Installation of Slab 47,950 7 (4) Steelman
off Machine
Rebars (3) Laborers
38. Fabrication & (1) Foreman/Leadman
Installation of Roof (5) Carpenters
36,900 6 (2) Jigsaw
Beam & Slab Forms (5) Laborer
(for Roof Deck)
39. Fabrication & (1) Foreman/Leadman
(2) Bar Cutter/Cut-
Installation of Stair 25,400 4 (3) Steelman
off Machine
Rebars (3) Laborer
40. Fabrication & (1) Foreman/Leadman
Installation of Stair 14,550 3 (2) Carpenters (2) Jigsaw
Forms (3) Laborer
(1) Foreman/Leadman
41. Concreting of Roof (1) Bagger Mixer
19,700 2 (5) Mason
Deck (1) Vibrator
(10) Laborer
(1) Foreman/Leadman
(1) Bagger Mixer
42. Concreting of Stairs 6,050 1 (3) Mason
(1) Vibrator
(3) Laborer
43. Installation of CHB (1) Foreman/Leadman
Firewalls & Walls @ 51,000 12 (4) Mason
G.F & 2ND Floor (4) Laborer
(1) Foreman/Leadman
44. Excavation of Septic (2) Laborer
24,150 7 (1) Jack Hammer
Tank (1) Heavy Tool
Operator
(1) Foreman/Leadman
45. Base Course 1,950 1 (1) Mason
(2) Laborer
(1) Foreman/Leadman
46. Removal of Scaffolds 9,150 3 (6) Laborer
223
TOTAL ₱ 1,456,500
Total Days
MANPOWER
1 - FOREMAN
1 - LEADMAN
SKILLED WORKERS:
(6) Steelman
(2) Driver
(6) Mason
(2) Operator
(5) Carpenter
(2) Tile Installer
(4) Painter
(1) Welder
(2) Plumber
(2) Glass Installer
(2) Electrician
12 - LABORERS
Name: Jayvanz Villacarlos BSCE – 4 Date: January 8, 2024
Title: Plate #5 Material Costs Subject: CE412 – Contr. Method & Project Mgmt.
Project: Two - Storey Residential Building (52.5 sq.m.) with 3 -Bedrooms and 2 -T&B
= ₱ 4,716,770.00