Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 13

Name: Jayvanz Villacarlos BSCE – 4 Date: January 8, 2024

Title: Plate #6 Float Calculation for CPM Subject: CE412 – Contr. Method & Project Mgmt.

ACTIVITY
EARLY EARLY LATE LATE
NUMBER DURATION TOTAL
START FINISH START FINISH
ARROW (DAYS) FLOAT
(ES) (EF) (LS) (LF)
DIAGRAM
Critical
1−2 2 0 2 0 2 0
Path
Critical
2−3 1 2 3 2 3 0
Path

2−5 1 2 3 5 6 3

Critical
3−4 2 3 5 3 5 0
Path

4–6 3 5 8 7 10 2

Critical
4–7 3 5 8 5 8 0
Path

5–6 4 3 7 6 10 3

6–8 2 8 10 10 12 2

Critical
7–8 4 8 12 8 12 0
Path
Critical
8–9 2 12 14 12 14 0
Path

9 – 10 3 14 17 19 22 5

Critical
9 – 11 4 14 18 14 18 0
Path

10 – 13 2 17 19 22 24 5

Critical
11 – 12 5 18 23 18 23 0
Path
Critical
12 – 14 3 23 26 23 26 0
Path

13 – 14 2 19 21 24 26 5

Critical
14 – 15 8 26 34 26 34 0
Path

14 – 15 6 26 32 28 34 2

Critical
15 – 16 3 34 37 34 37 0
Path
Critical
16 – 17 2 37 39 37 39 0
Path

17 – 18 2 39 41 42 44 3

Critical
17 – 19 3 39 42 39 42 0
Path

18 – 20 2 41 43 44 46 3

Critical
19 – 20 4 42 46 42 46 0
Path
Critical
20 – 21 1 46 47 46 47 0
Path
Critical
21 – 22 5 47 52 47 52 0
Path
Critical
22 – 23 6 52 58 52 58 0
Path
Critical
23 – 24 3 58 61 58 61 0
Path

23 – 24 2 58 60 59 61 1

Critical
24 – 25 6 61 67 61 67 0
Path
Critical
25 – 26 2 67 69 67 69 0
Path
Critical
26 – 27 6 69 75 69 75 0
Path

26 – 27 3 69 72 72 75 3

Critical
27 – 28 4 75 79 75 79 0
Path
Critical
28 – 29 2 79 81 79 81 0
Path
Critical
29 – 30 4 81 85 81 85 0
Path

29 – 31 6 81 87 82 88 1

Critical
30 – 32 7 85 92 85 92 0
Path

31 – 32 4 87 91 88 92 1

31 – 32 3 87 90 89 92 2

Critical
32 – 33 2 92 94 92 94 0
Path
Critical
33 – 34 1 94 95 94 95 0
Path

34 – 35 7 95 102 96 103 1

Critical
34 – 37 12 95 107 95 107 0
Path

35 – 36 1 102 103 103 104 1

36 – 37 3 103 106 104 107 1

Critical
37 – 38 10 107 117 107 117 0
Path
Critical
38 – 39 3 117 120 117 120 0
Path
Critical
39 – 40 4 120 124 120 124 0
Path

39 – 41 5 120 125 122 127 2

39 – 42 10 120 130 125 135 5

Critical
40 – 41 3 124 127 124 127 0
Path
Critical
41 – 42 8 127 135 127 135 0
Path
Critical
42 – 43 14 135 149 135 149 0
Path
Critical
43 – 44 2 149 151 149 151 0
Path

44 – 45 2 137 139 149 151 12


Name: Jayvanz Villacarlos BSCE – 4 Date: January 8, 2024
Title: Plate #4 Duration & Costing Subject: CE412 – Contr. Method & Project Mgmt.

DURATION TOOLS &


ACTIVITIES COST (₱) (Day/s) MANPOWER
EQUIPMENT

(1) Foreman/Leadman
(1) Dump truck
(1) Operator
1. Mobilization 82,800 2 (1) Backhoe
(2) Driver
(4) Laborers
(1) Foreman/Leadman
2. Land/Site Clearing 22,000 1 (1) Operator (1) Backhoe
(2) Laborers
(1) Foreman/Leadman
3. Layout 3,900 2 (1) Carpenter
(2) Laborers
(1) Foreman/Leadman
4. Construction of
2,450 1 (2) Carpenters
Bunkhouse
(2) Laborers
(1) Foreman/Leadman
5. Excavation of (1) Backhoe
66,000 3 (1) Operator
Footings
(2) Laborers
(1) Foreman/Leadman
6. Lean Concreting 8,300 2 (3) Mason (1) Bagger Mixer
(2) Laborers
(1) Foreman/Leadman
7. Excavation of Tie
72,000 4 (1) Operator (1) Backhoe
Beams
(2) Laborers
8. Fabrication of (1) Foreman/Leadman
(1) Bar Cutter/Cut-
Column Footing 9,450 3 (2) Steelman
off Machine
Rebars
(1) Foreman/Leadman
9. Installation of Column (1) Bar Cutter/Cut-
16,200 4 (3) Steelman
Footing Rebars off Machine
(1) Laborers
(1) Foreman/Leadman
10. Concreting of Column
9,700 2 (3) Mason (1) Bagger Mixer
Footing
(3) Laborers
(1) Foreman/Leadman
11. Fabrication of Tie (1) Bar Cutter/Cut-
7,950 3 (1) Steelman
Beam Rebars off Machine

(1) Foreman/Leadman
12. Fabrication of Tie
10,200 4 (1) Carpenter (1) Jigsaw
Beam Forms
(1) Laborer
(1) Foreman/Leadman
13. Installation of Tie (1) Bar Cutter/Cut-
7,100 2 (2) Steelman
Beam Rebars off Machine
(1) Laborer
(1) Foreman/Leadman
14. Installation of Tie
15,250 5 (2) Carpenter (1) Jigsaw
Beam Forms
(1) Laborer
15. Installation of (1) Foreman/Leadman
Scaffoldings @ 11,850 3 (3) Carpenter (1) Jigsaw
Ground Floor (2) Laborer
(1) Foreman/Leadman
(4) Mason
16. Concreting of Tie (1) Bagger Mixer
13,300 2 (2) Laborers
Beams (1) Vibrator
(1) Heavy Tool
Operator
17. Fabrication & (1) Foreman/Leadman
(2) Bar Cutter/Cut-
Installation of Column 50,800 8 (3) Steelman
off Machine
Rebars @ G.F. (3) Laborer
18. Fabrication & (1) Foreman/Leadman
Installation of Column 29,700 6 (3) Carpenter (2) Jigsaw
Forms @ G.F. (2) Laborer
(1) Foreman/Leadman
(4) Mason
19. Concreting of (1) Bagger Mixer
21,150 3 (3) Laborer
Columns @ G. F (1) Vibrator
(1) Heavy Tool
Operator
(1) Foreman/Leadman
20. Backfill 44,700 2 (1) Operator (1) Backhoe
(3) Laborer
21. Installation of (1) Foreman/Leadman
Electrical Roughing- 5,700 2 (2) Electrician
Ins @ G.F. (2) Laborer
22. Installation of (1) Foreman/Leadman
Plumbing Roughing- 5,700 2 (2) Plumber
Ins @ G.F. (2) Laborer
(1) Foreman/Leadman
23. Fabrication of Ground (1) Bar Cutter/Cut-
9,450 3 (2) Steelman
Floor Slab Rebars off Machine

(1) Foreman/Leadman
24. Installation of Ground (1) Bar Cutter/Cut-
17,400 4 (2) Steelman
Floor Slab Rebars off Machine
(3) Laborer
(1) Foreman/Leadman
25. Concreting of Ground
5,150 1 (5) Mason
Floor Slab
(5) Laborer
26. Fabrication & (1) Foreman/Leadman
(2) Bar Cutter/Cut-
Installation of Mid- 29,250 5 (2) Steelman
off Machine
Beam Rebars (3) Laborer
27. Fabrication & (1) Foreman/Leadman
(2) Bar Cutter/Cut-
Installation of Slab 35,700 6 (3) Steelman
off Machine
Rebars (2) Laborer
28. Installation of (1) Foreman/Leadman
Plumbing Roughing- 9,750 3 (2) Plumber
Ins @ 2nd Floor (3) Laborer
29. Installation of (1) Foreman/Leadman
Electrical Roughing- 6,500 2 (2) Electrician
Ins @ 2nd Floor (3) Laborer
30. Fabrication & (1) Foreman/Leadman
Installation of Mid- 48,300 6 (6) Carpenters (2) Jigsaw
Beam & Slab Forms (6) Laborers
(1) Foreman/Leadman
31. Concreting of Mid- (1) Bagger Mixer
25,300 2 (6) Mason
Beam & Slab (1) Vibrator
(12) Laborer
32. Fabrication & (1) Foreman/Leadman
(2) Bar Cutter/Cut-
Installation of Column 43,500 6 (4) Steelman
off Machine
Rebars @ 2nd Floor (4) Laborer
33. Installation of (1) Foreman/Leadman
Scaffoldings @ 2nd 11,550 3 (4) Steelman
Floor (3) Laborer
34. Fabrication & (1) Foreman/Leadman
Installation of Column 23,400 4 (4) Carpenters (2) Jigsaw
Forms @ 2nd Floor (3) Laborers
(1) Foreman/Leadman
(5) Mason
35. Concreting of (1) Bagger Mixer
16,700 2 (5) Laborer
Columns @ 2nd Floor (1) Vibrator
(1) Heavy Tool
Operator
36. Fabrication & (1) Foreman/Leadman
(2) Bar Cutter/Cut-
Installation of Roof 25,400 4 (3) Steelman
off Machine
Beam Rebars (3) Laborer
37. Fabrication & (1) Foreman/Leadman
(2) Bar Cutter/Cut-
Installation of Slab 47,950 7 (4) Steelman
off Machine
Rebars (3) Laborers
38. Fabrication & (1) Foreman/Leadman
Installation of Roof (5) Carpenters
36,900 6 (2) Jigsaw
Beam & Slab Forms (5) Laborer
(for Roof Deck)
39. Fabrication & (1) Foreman/Leadman
(2) Bar Cutter/Cut-
Installation of Stair 25,400 4 (3) Steelman
off Machine
Rebars (3) Laborer
40. Fabrication & (1) Foreman/Leadman
Installation of Stair 14,550 3 (2) Carpenters (2) Jigsaw
Forms (3) Laborer
(1) Foreman/Leadman
41. Concreting of Roof (1) Bagger Mixer
19,700 2 (5) Mason
Deck (1) Vibrator
(10) Laborer
(1) Foreman/Leadman
(1) Bagger Mixer
42. Concreting of Stairs 6,050 1 (3) Mason
(1) Vibrator
(3) Laborer
43. Installation of CHB (1) Foreman/Leadman
Firewalls & Walls @ 51,000 12 (4) Mason
G.F & 2ND Floor (4) Laborer
(1) Foreman/Leadman
44. Excavation of Septic (2) Laborer
24,150 7 (1) Jack Hammer
Tank (1) Heavy Tool
Operator
(1) Foreman/Leadman
45. Base Course 1,950 1 (1) Mason
(2) Laborer
(1) Foreman/Leadman
46. Removal of Scaffolds 9,150 3 (6) Laborer

47. Plastering of CHB (1) Foreman/Leadman


Walls @ G. F. & 2ND 34,500 10 (4) Mason
Floor (2) Laborer
(1) Foreman/Leadman
(1) Steelman
48. Construction of (1) Mason (1) Bar Cutter/Cut-
15,450 3
Septic Tank (1) Carpenter off Machine
(1) Plumber
(2) Laborer
49. Installation of (1) Foreman/Leadman
(1) Electric
Plumbing Fixtures @ 15,400 4 (2) Plumber
Hammer Drill
G.F. & 2ND Floor (2) Laborer
50. Installation of (1) Foreman/Leadman
(1) Electric
Electrical Fixtures @ 11,550 3 (2) Electrician
Hammer Drill
G.F. & 2ND Floor (2) Laborer
51. Installation of Glass (1) Foreman/Leadman
(1) Grinder
Panels, Doors, & (3) Carpenter
71,500 10 (1) Electric
Windows @ G.F. & (2) Glass Installer
Hammer Drill
2ND Floor (3) Laborer
(1) Foreman/Leadman
52. Installation of (1) Welding
(3) Steelman
Railings @ G.F. & 2ND 35,500 5 Machine
(1) Welder
Floor (1) Grinder
(2) Laborer
(1) Foreman/Leadman
53. Installation of Floor
(3) Mason (1) Grinder
Tiles @ G.F. & 2nd 52,400 8
(2) Tile Installer
Floor
(4) Laborer
(1) Foreman/Leadman
54. Painting Works @
53,200 14 (3) Painter
G.F. & 2ND Floor
(3) Laborer
(1) Foreman/Leadman
(3) Carpenter
55. Clearing 47,800 2 (1) Backhoe
(1) Operator
(3) Laborer
(1) Foreman/Leadman
(2) Carpenter (1) Dump truck
56. Demobilization 58,850 1 (2) Operator (1) Boom Truck
(1) Driver (1) Backhoe
(5) Laborer

223
TOTAL ₱ 1,456,500
Total Days
MANPOWER

1 - FOREMAN
1 - LEADMAN
SKILLED WORKERS:
(6) Steelman
(2) Driver
(6) Mason
(2) Operator
(5) Carpenter
(2) Tile Installer
(4) Painter
(1) Welder
(2) Plumber
(2) Glass Installer
(2) Electrician
12 - LABORERS
Name: Jayvanz Villacarlos BSCE – 4 Date: January 8, 2024
Title: Plate #5 Material Costs Subject: CE412 – Contr. Method & Project Mgmt.

ACTIVITIES COST (₱) MATERIALS

(24 pcs) Lumber 2”x3”x12’


(2.5 kgs) CWN 5”
Layout 7,200
(1 roll) Nylon String
(1 pack) Cutting Disc
(33 pcs.) Coco Lumber 2’’x3’’x12’
(14 pcs.) Corrugated G.I Sheet Gage 26
x8’
(2.5 kgs.) Umbrella Nails
Construction of Bunkhouse 22,883
(3 kgs.) CWN 5’’
(12 pcs.) Marine Plywood ½”x4’x8’
(2 kgs.) #1-1/2 CWN
(1 pack) Cutting Disc

(39 bags) Cement (40 kg)


Lean Concreting 1,950
(2.5 cu.m) Sand

Fabrication & Installation of (31 L) 16 mm Ø def. bars x 6m


16,865 (5 kgs.) #16 G.I Tie Wire
Column Footing Rebars (1 pack) Cutting Disc
(27 bags) Cement
Concreting of Column Footing 13,610 (2 cu.m.) Sand
(3 cu.m.) Gravel
(41 L) 16 mm Ø def. bars
Fabrication & Installation of Tie (82 L) 10 mm Ø def bars
39,855
Beam Rebars (8 KGS.) #16 G.I Tie Wire
(2 pack) Cutting Disc
(25 pcs.) Marine Plywood
Fabrication & Installation of Tie (157 pcs.) Coco Lumber 2”x2”x12’
49,497.50
Beam Forms (9.5 kgs.) #1-1/2 CWN
(2 pack) Cutting Disc
(24 pcs.) Marine Plywood
Installation of Scaffoldings @ (431 pcs.) Coco Lumber 2”x2”x12’
172,460 (214 pcs.) Coco Lumber 2”x3”x12’
Ground Floor (46 kgs.) CW 20D Nails
(3 packs) Cutting Disc
(62 bags) Cement
Concreting of Tie Beams 29,660 (3.5 cu.m.) Sand
(7 cu.m.) Gravel
(78 L) 16 mm Ø def. bars x 6m
Fabrication & Installation of (78 L) 10 mm Ø def. bars x 6m
59,260
Column Rebars @ G.F. (16.5 kgs.) #16 G.I Tie Wire
(2 pack) Cutting Disc
(29 pcs.) Marine Plywood ¼ “x4’x8’
Fabrication & Installation of (216 pcs.) Coco Lumber 2”x2”x12’
63,840
Column Forms @ G.F. (2 kgs.) CW 2D Nails
(1 pack) Cutting Disc
(46 bags) Cement Portland
Concreting of Columns @ G. F 23,780 (3 cu.m.) Sand
(6 cu.m.) Gravel
(190 LM) 38 mm2 THHN Wire
(20 LM) 14.0 mm2 THHN Wire
(1 box) 5.5 mm2 THHN Wire
(13 boxes) 3.5 mm2 THHN Wire
(13 boxes) 2.0 mm2 THHN Wire
(26 pcs.) 40 mm Ø PVC Pipe, Fittings &Support
Installation of Electrical
(1 pc.) 40 mm Ø Entrance Cap
Roughing-Ins @ Ground Floor 350,550 (112 pcs.) 25 mm Ø PVC Pipe, Fittings
& 2ND Floor &Support
(149 pcs.) 20 mm Ø PVC Pipe, Fittings
&Support
(3 L) 32 mm Ø RSC
(149 pcs.) 4”x4” Octagonal Pipe
(143 pcs.) 2”x4” Utility Box
(3 sets) Panel Board (LPA/PPA)
(16 L) 32 mm Ø, PPR Pipe & Fittings
(24 L) 25 mm Ø, PPR Pipe & Fittings
(20 L) 20 mm Ø, PPR Pipe & Fittings
Installation of Plumbing
(14 pcs.) 13 mm Ø, Faucet
Roughing-Ins @ G.F. & 2nd 209,346 (8 pcs.) 32 mm Ø, Gate Valves
floor (4 pcs.) 32 mm Ø, Check Valves
(30 L) 100 mm Ø, PPR Pipe & Fittings
(36 L) 75 mm Ø, PPR Pipe & Fittings
(24 L) 50 mm Ø, PPR Pipe & Fittings
Fabrication & Installation of (157 L) 12 mm Ø def. bars
47,890 (14 kgs.) #16 G.I Tie Wire
Ground Floor Slab Rebars (2 packs) Cutting Disc
Concreting of Ground Floor (82 bags) Cement
40,160 (5 cu.m.) Sand
Slab (9.5 cu.m.) Gravel
(51 L) 16 mm Ø def. bars
Fabrication & Installation of (88 L) 10 mm Ø def. bars
46,345
Mid-Beam Rebars (10 kgs.) #16 G.I Tie Wire
(1 pack) Cutting Disc
Fabrication & Installation of (220 L) 12 mm Ø def. bars
67,560 (24 kgs.) #16 G.I Tie Wire
Slab Rebars (2 packs) Cutting Disc
(48 pcs.) Marine Plywood ¼ “x4’x8’
Fabrication & Installation of (256 pcs.) Coco Lumber 2”X2”X12’
84,850
Mid-Beam & Slab Forms (18 kgs.) CWN 2d
(3 packs) Cutting Disc
Concreting of Mid-Beam & 68,770 (139 bags) Cement
Slab (9 cu.m.) Sand
(16 cu.m.) Gravel
(48 L) 16 mm Ø def. bars
Fabrication & Installation of (64 L) 10 mm Ø def. bars
40,320
Column Rebars @ 2nd Floor (14 kgs.) #16 G.I Tie Wire
(1 pack) Cutting Disc
(24 pcs.) Marine Plywood
Installation of Scaffoldings @ (431 pcs.) Coco Lumber 2”x2”x12’
172,460 (214 pcs.) Coco Lumber 2”x3”x12’
2nd Floor (46 kgs.) CW 20D Nails
(3 packs) Cutting Disc
(18 pcs.) Marine Plywood ¼ “x4’x8’
Fabrication & Installation of (134 pcs.) Coco Lumber 2”x2”x12’
39,665
Column Forms @ 2nd Floor (1 kgs.) CW 2d Nails
(1 pack) Cutting Disc
Concreting of Columns @ 2nd (30 bags) Cement
15,000 (2 cu.m.) Sand
Floor (3.5 cu.m.) Gravel
(41 L) 16 mm Ø def. bars
Fabrication & Installation of (82 L) 10 mm Ø def. bars
39,855
Roof Beam Rebars (8 kgs.) #16 G.I Tie Wire
(2 pack) Cutting Disc
Fabrication & Installation of (176 L) 12 mm Ø def. bars
53,680 (16 kgs.) #16 G.I Tie Wire
Slab Rebars (2 packs) Cutting Disc
Fabrication & Installation of (49 pcs.) Marine Plywood ¼ “x4’x8’
Roof Beam & Slab Forms (for 119,640 (268 pcs.) Coco Lumber 2”X2”X12’
(19 kgs.) # 1-1/2 CWN
Roof Deck) (3 packs) Cutting Disc
(13 L) 12 mm Ø def.bars
Fabrication & Installation of (38 L) 10 mm Ø def. bars
10,640
Stair Rebars (5.5 kgs.) #16 G.I Tie Wire
(1 pack) Cutting Disc
(8 pcs.) Marine Plywood ¼ “x4’x8’
Fabrication & Installation of (25 pcs.) Coco Lumber 2”x2”x12’
10,185
Stair Forms (1 kg.) #1-1/2 CWN
(1 pack) Cutting Disc
(202 bags) Cement
Concreting of Roof Deck 99,260 (12 cu.m.) Sand
(24 cu.m.) Gravel
(10 bags) Cement
Concreting of Stairs 6,700 (1 cu.m.) Sand
(2 cu.m.) Gravel
(2889 pcs.) 10x20x40 CHB
(138 bags) Cement
Installation of CHB Firewalls & (10 cu.m.) Sand
185,980
Walls @ G.F & 2ND Floor (179 L) 10 mm Ø def. bars x 6m
(6.5 kgs.) #16 G.I Wire
(4 packs) Cutting Disc
Plastering of CHB Walls @ G. (192 bags) Cement
70,560
F. & 2 ND
Floor (16.5 cu.m.) Sand

(113 pcs.) 10x20x40 CHB


(14 bags) Cement
(1.5 cu.m.) Sand
Construction of Septic Tank 14,875 (0.5 cu.m.) Gravel
(13 L) 10 mm Ø def. bars x 6m
(1 kg.) #16 G.I Tie Wire
(2 packs) Cutting Disc
(2 sets) Water Closet & Accessories
(2 sets) Lavatory & Accessories
(2 sets) Kitchen Sink & Accessories
(10 sets) Floor Drain 4” Ø
(2 sets) Roof Drain 3” Ø
Installation of Plumbing (6 sets) Catch Basin
224,435
Fixtures @ G.F. & 2ND Floor (1 set) Cistern Tank Accessories
(1 set) Septic Tank Accessories
(1 set) Booster Pump Accessories
(1 set) Pressure Tank and Accessories
(4 sets) Water Meter
(1 set) Storage Tank & Accessories
(3 pcs.) Fluorescent lighting fixture w/ 1x18 W
(75 pcs.) 100mm Ø Pinlight w/ 11 W energy
saving lamp
(2 pcs.) Pinlight Halogen Lamp, 50 W
(12 Pcs.) Wall mounted lighting fixture w/ 11 W
energy saving lamp
(2 pcs.) Garden Light (weatherproof) w/ 18 W
PAR 38 energy saving lamp
Installation of Electrical
134,773 (2 pcs.) Surface mtd. Lighting fixture w/ 2x11 W
Fixtures @ G.F. & 2ND Floor energy saving lamp
(1 pc.) Chandelier w/ 10-5 W energy saving
lamp
(35 pcs.) Duplex Convenience Outlet (C.O)
(8 pcs.) Duplex C.O w/ weatherproof cover
(3 pcs.) Duplex C.O. w/ GFI
(8 lot) Single Outlet
(3 set) Single Switch
(9 set) 2-Gang Switch
Installation of Glass Panels, 283,493 (5 sets) PVC Door (w/ jamb & comp. acc.)
Doors, & Windows @ G.F. & (4 sets) Flush Type Door w/ jamb & comp. acc.
(1 set) Panel Type Door (0.80x2.10m w/ jamb &
2ND Floor comp. acc.)
(2 sets) Sliding Door w/ Alum. Frame
(5 units) Tinted Glass Sliding Wdo. w/ alum.
Frame (incld. Installation & comp. acc.)
(1 set) Transparent Fixed Window & Analok FD
Frame w/ comp. acc.
(7 units) Tinted Glass Double Window (incld.
Inst. & comp. acc.)
(4 sets) 0.60x0.90 Tinted Glass Sliding Window
(incld. Inst. Comp. Acc.)
(6 pcs.) 2x2 Tubular Stainless
Installation of Railings @ G.F. (15 pcs.) Tubular Stainless
12,456.50 (3.5 kgs.) Stainless Welding Rod
& 2ND Floor
(3 pcs.) Cutting Blade
(3 pcs.) Grinding Blade
(659 pcs.) Glazed Ceramic Tiles 60x60 cm
(195 pcs.) Glazed Ceramic Tiles 30x30 cm for
Installation of Floor Tiles & CR Floor Tiles
(578 pcs.) Unglazed Ceramic Tiles 30x30 cm for
C.R Floor Tiles & Walls @ G.F. 99,896
CR Wall Tiles 1.5m High
& 2nd Floor (8.5 bags) Cement Mortar
(43 kgs.) White Cement
(11 bags) Tile Adhesive
(3 L) Boysen-Neutralizer
(11 gallons) Surface Primer
Painting Works (Interior & (11 gallons) Gloss Latex Final Coating
250,225 (5 pcs.) Roller Brush (9”) with pan
Exterior) @ G.F. & 2ND Floor (5 pcs.) Roller Brush (9”) refill
(6 pcs.) Paint Brush #1.5”
(6 pcs.) Paint Brush #2”

TOTAL MATERIAL COSTS ₱ 3,260,270.00

Project: Two - Storey Residential Building (52.5 sq.m.) with 3 -Bedrooms and 2 -T&B

OVERALL COST FOR TWO-STOREY MODERN HOUSE:


= (Duration & Costing) + (Material Costs)
= ₱ 1,456,500 + ₱ 3,260,270

= ₱ 4,716,770.00

You might also like