CHAPTER 6
RISK CONTRIBUTION
6.1 GENERAL
In this step, the risk contribution in terms of time, cost, quality and
safety in the project are arrived to find their impact on the project
correspondingly. It is essential, to monitor and control risks throughout the
stages of projects for the successful completion of project within the
stipulated time and estimated cost without compromising quality thereby
ensuring safety.
Pre-Construction Stage
S.No Risk factor Impact Time Cost Quality Safety
Completion Stage
S.No Risk factor Impact Time Cost Quality Safety
Will have to plan at the
Move Planning from earliest to avoid last moment
1
the existing facility changes/Sequence of shifting
equipment’s
Delay in rectification Will affect the quality of the
2
works building
Chances of Will have chance beyond the
3 reconciliation on final quantity & have impact on
bills for all vendors budget
Quantity variation
4 Will impact on budget
from BOQ
LD clause may
Will affect the pending
imposed to Vendors
5 completion works along
due to delay in
punch points & snag list
Completion of Project
Vendor in Critical
Will Impact the overall
path - due to delays in
6 schedule due to other vendor
executing target
depending activities
completion dates
Vendor may go
Will have change to get the
7 legally for their claim
claim if go legally
raised
Will affect cost & time if not
Vendor Snag list
8 do on time. Which will affect
completion issues
other vendors as well
Finalizing of Vendor
Additional Claim Will impact the Overall
9
beyond contract budget allotted
duration
11 Closeout in Hurry. Improper close out.
Delay in completion Delay in completion of
12 of machinery machinery installation works
installation works will delay in handing over
Delay in handing over Delay in handing over of one
of one area from one area to other vendor will
13 vendor to another delay the erection works and
vendor to start their in turn the handing over of
works the building
No proper documents
All proper test report and
of the Inspection test
documents must be
14 procedures done at
maintained at site as per
site maintained by the
client requirement
Vendors
Delay/improper
Will affect the handing over
Handing over
15 process from Projects to
documentation by the
Facility/maintenance team.
contractor
197
6.2.4 Result
From the table it is evident that during each stages significant impact is on
time and in all cases throughout the construction project it’s on time which is
highly affected. Hence it is recommended that the factors contributing to the
time has to be focused and eliminated.
2
Quantity variation
Will impact on budget
from BOQ
4 Finalizing of Vendor
Additional Claim Will impact the Overall
beyond contract budget allotted
duration
machines(3M)
199
20 Housekeeping / waste
Will impact the construction
disposal during
start up
construction stage
21 Defective work
Will affect cost and time of
the project
project
project
Similarly the risk contribution factors has been listed as in the table
below for Highway projects for all the three stages which are added together
to minimize the size of the study.
201
project
variations
The same procedure has been adopted for the all stages of construction in
apartment projects and correlated against Time, Cost, Quality and safety
based on their impact over the projects and further the results are tabulated as
follows:
facility
15
10
10 8
0
Time Cost Safety Quality
Category
6.6 RESULT
Various risk factors which are identified from literatures and field
observations for industrial, commercial, highway and apartment projects
contributed to some or all of the aspects viz. time, cost, quality and safety
during pre-construction, construction and completion stages of the
construction project. The majority of the risks are contributed mainly due to
time and cost.