Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 6

Earned value analysis, for the rest of us

Applies To: Project Professional 2016 Project Professional 2013 Project Standard 2013 More...

Earned value is a powerful tracking and budgeting feature in Project. Despite the slew of
intimidating acronyms that defines it (like AC, BCWP, TPI, EV, and the like), it isn’t
especially complicated. Earned value helps you answer questions like, “Looking at the
amount of work done so far in this project, how much money were we supposed to have
spent?” Which then leads to other questions like, "Will we finish on time?"

A simple example You’re working on a gardening project for 10 homes in a cul-de-


sac, and you expect to get the entire project of 10 homes done in 10 months. Further,
you need to complete one home’s garden in each month. Let’s walk through some of
the details on this project.

 $10,000 is your total budget for all 10 homes.


 $1,000 is budgeted for each home, which means you plan to spend $1,000 per month
on the entire project. This includes money spent on plants, tools, and a gardener.
 You ask your account for a report after 2 months have passed. The accountant tells you
$1,500 has been spent on the project so far. You think, “Great, I’m saving money.”
 Then you realize your mistake. After 2 months’ time, 20 percent of the project should
have been done, because 2 months is 20 percent of the 10 months that you had
originally planned to spend on the project. But only one and a half gardens are actually
done, not 2.
 So, after two months, you should have spent 20 percent X $10,000 (or $2,000) on the
project to get it done on time, and two gardens should be complete—not $1,500 for
one and half gardens. Now you realize you’re actually behind schedule. Yikes! Time to
have a talk with the gardener.

Here’s the tricky thing (and great thing) about earned value. It marries time with money
because it multiplies currency by scheduled time (or percent complete, in the jargon of
professional project managers).

The lesson? “Time is money,” as the old saying goes. Now, you can’t boast your
prowess with earned value quite yet. You need to read on . . .

More on earned value


Display earned value

Using reports

Using views

Interpret earned value

Some advice on using earned value

Further reading

Display earned value

Project displays earned value information two ways: with views and with reports. But first
you need to do a few things to set up earned value for reporting.

 Set a baseline
 Set a status date
 Specify the earned value method for percent complete (optional)

Using reports

1. Click Project > Reports > More Reports.


2. Click Costs, and then click Earned Value.

Using views
1. Click View > Table, then click More Tables.

2. In the Tables list, click Earned Value, Earned Value Cost Indicators, or Earned Value
Schedule Indicators.
If you’re not sure which table, just pick Earned Value.
3. Click Apply.

Top of Page

Interpret earned value

Three key values are at the root of earned value analysis, and you pretty much need to
know at least these three values to use earned value.

Planned value This is the budgeted (or baseline) cost of tasks estimated at the start
(PV) This also the project plan, based on the costs of resources assigned to those
known by the tasks, plus any fixed costs associated with the tasks, up to the status
acronym BCWS. date you choose.

For example, the total planned budget for a 4-day task is $100 and it
starts on a Monday. If you set the status date to the following
Wednesday, you’ll see that the PV is $75. However, with this value,
you don’t know how well your project is doing.
Actual Cost This is the actual cost required to complete all or some portion of the
(AC) This is also tasks, up to the status date. For example, if the 4-day task actually
known by ACWP. incurs a total cost of $35 during each of the first 2 days, the AC for this
period is $70 (but the PV is still $75).

However, with this value, you don’t know how well your project is
Planned value This is the budgeted (or baseline) cost of tasks estimated at the start
(PV) This also the project plan, based on the costs of resources assigned to those
known by the tasks, plus any fixed costs associated with the tasks, up to the status
acronym BCWS. date you choose.

For example, the total planned budget for a 4-day task is $100 and it
starts on a Monday. If you set the status date to the following
Wednesday, you’ll see that the PV is $75. However, with this value,
you don’t know how well your project is doing.

doing. For example, if you planned to get a lot more work done for that
same $70, that doesn’t sound good. You need to know (you guess it)
earned value to fully assess the efficiency of your project.
Earned Value This is the value of the work performed by the status date, measured in
(EV) This is also currency.
known as BCWP
For example, if after 2 days 60% percent of the work on a task has been
completed, you might expect to have spent 60 percent of the total task
budget, or $60. If it turns out that you spent $80, then you can safely
say you’re over budget and behind schedule. Ouch!

An important theme running through these common earned value terms is the status
date. Earned value analysis assumes you want to see the progress on your project prior
to a specific point in time that you choose.

Because a picture is worth a thousand words, let’s look at this graphically. Here’s a chart
showing a steady accumulation of cost over the lifetime of a project. The dotted line
shows a steady expenditure over the lifetime of the project.
After work on the project has begun, a chart of the key values of earned value analysis
may look like this.

The status date determines the values Project calculates. The actual cost (AC) of this
project has exceeded the budgeted cost. The earned value (EV) reflects the true value of
the work performed. In this case, the value of the work performed is less than the
amount spent to perform that work.

Top of Page

Some advice on using earned value

Do this How
Take The earlier in a project's life cycle you identify such discrepancies between
action actuals costs, budgeted costs, and earned value the sooner you can take steps
soon to remedy the problem.
Work Easier said than done. The more work you get done before the next status date
harder for determining earned value, the better. Simply hiring more workers may not
help, but hiring cheaper workers might. Or you may need to “walk the floor,” to
find out why workers aren’t being more productive. Or maybe the problem is
with the managers who are providing machinery that needs more maintenance
than expected. There could be many reasons, but the point is, using a “numbers
approach” with earned value will help you spot negative trends.
Do this How
Work Don’t chase after productivity problems on those tasks that are less important
smarter than others. Check tasks on the critical path first for the greatest impact on
positive earned value numbers.
Re-run An earned value analysis at the end of a project really has little value. The
your sources of your project’s problems is likely early in it, and will likely have had
reports too much impact to correct without incurring great cost and frustration from
your team, manager, and other stakeholders. Get in the habit of running earned
value reports monthly, if you’re going to do them at all.
Don’t If you see problems very early in the project, it could just be ramp-up costs, or
sweat the the costs of training, getting everyone on-board, abundant but necessary early
early stuff collaboration with your team, and other housekeeping chores. Don’t ignore
these early signs of trouble, but they may be more understandable early in the
project than later.

You might also like