1.0 INTRODUCTION
All the works forming part of this consultancy will be carried out to meet the
standards of the Ethiopian Roads Authority (2013) as well as to the ISO 9001
standard. These standards are recognized by the international consulting industry
The project road is located in the Northern part of the country, and lies entirely in
the Tigray Regional State of the Federal Democratic Republic of Ethiopia,
particularly in Central and North-Western Administrative Zone. The road project
starts at Rama town; this town is located in Mereb Lekhe Woreda at 1047.6 km
from Addis Ababa. Chila is another town which is located in the same woreda
where Rama town found. The other towns is Semema which is located south west
of Rama about 78Km away found in Tahitay Qoraro woreda. The Project Ends at
two end points, Embatizu at junction from Shire – Shiraro road to Semema town
which is located 6.4Km from Shire town and At Adi Daero town the Woreda sete
of Laelay Adiabo which is located 25.7 Km from shire town The total project
length is 91.13 km. The purpose of the project is to upgrade the part of existing
road and construct new road to the appropriate design standard and surface type
that will connect Rama Chila Semema and Adidaro towns and provide access to
villages and large rural settlement areas in between these towns.
Time for completion of the project is 1095 calendar days including 90 calendar days
of mobilization.
ICONE Engineering 1
Detailed Engineering Design & Tender Documents Engineering Cost Estimate Report
Rama-Chila-Adi Daro-Semema Road Project
The main objectives of the services stated under each phase are:
Phase I
Phase II
02.01 Methodology
This Engineer’s Estimate is derived from applying prices to the tender document’s Bills of
Quantities and summating amounts in the same style that tenderer’s will compute their
bid price. In computing the unit rate of each activity itemized in the BOQ by the design
Engineers, studied standard crew and crew output/optimum crew production rate is
used. Firstly, the direct cost of the unit rate is computed and factored by the indirect
cost factor. The direct cost is the cost of equipment, material and lab our directly
involved in execution of the work specified, measured and quantified in the technical
specification whereas the indirect cost includes computed or assumed contractor’s head
office cost, contractor’s project cost including management and site establishment,
mobilization and demobilization cost, income tax, insurance cost, nonadjustable price
escalation, some work items which the contractor may be obliged to execute but not
itemized in the BOQ and contractor’s profit.
ICONE Engineering 2
Detailed Engineering Design & Tender Documents Engineering Cost Estimate Report
Rama-Chila-Adi Daro-Semema Road Project
The unit price for each BOQ items is derived from detail Cost break down considering all
the required resources such as equipment, manpower and materials and their respective
time or quantity and cost required for the crew. Haulage distances (table 4) are
considered in determining the unit rates. The hauling distances are determined by
referring to the location of material resources such as quarry sites, borrow sites ,
production sites etc and the transportation cost to the project sites for cement,
reinforcement and bitumen have been considered. The indirect costs are included in the
cost breakdown. The up-to-date prices of materials and equipment are collected from
market to determine the rental rates of equipment, base prices of materials and hourly
rates of manpower which directly used to compute the unit rate of each bill item.
An eight hours work time per day is use for estimation of unit rate determination. Before
determining the unit rates the collected direct raw data are processed to be used in the
analysis of the unit rate. The basic salary of each labor is fist factored as shown in table 1.
The hourly cost of each equipment to be used for any activity of the specified work is
determined taking into consideration all component of cost of equipment such as
investment cost, insurance cost, fuel cost, depreciation cost, salvage cost, service and
repair cost, tire cost (if any) and interest. The equipment breakdown cost finally
categorized in to two major cost group, owing cost and operating cost.
Equipment owning costs are all these costs in which the owner of the equipment
expends throughout the economic life of the equipment whether the equipment is
working or not. These costs include mainly the depreciation costs of the equipment with
the consideration of its salvage value, erection and installation costs, major repairs and
overhauling costs, property taxes and insurance charges.
Equipment operating costs are costs in which the owner of the equipment expends
throughout the economic life of the equipment when it is working. These costs include
the cost of the fuel, oils, filters, grease, normal repairs, tires and maintenance costs.
The unit rate for provision of Engineer’s vehicles, survey equipment, and radio for
communication and other furniture’s and equipment are obtained from market prices
and factored by an appropriate contractor’s profit and overhead costs. Cost for
maintenance of vehicles is determined from associated cost while utilizing the vehicle
such as fuel, insurances, service and repair and maintenance. To determine the services
and maintenance cost for housing office and buildings the cost of generators, running
cost of generators, cost of water tanks, provision of bottled water for engineer staff,
attendance costs etc. are first determined while the cost of the buildings are taken from
studied market prices in terms of cost per area of the building and computed for each
pay item.
ICONE Engineering 3
Detailed Engineering Design & Tender Documents Engineering Cost Estimate Report
Rama-Chila-Adi Daro-Semema Road Project
03.01 Computations
The cost of each work item is derived from the unit price (rate) applied to the measured
quantity. The measurable quantities for payment purposes are set down in the ‘method
of measurement’ which is embodied in the Measurement and Payment clauses for each
category of work in ERA Standard Technical Specification 2013.
The quantities of Earthwork, Subbase and Base Course and priming and surface dressing
are derived during design computations using computer software used for the geometric
design of the Road. Other quantities have been summed manually.
The ISO metric system is used throughout which is based on SI (Standard Internationale,
Fr.).
03.03 Currency
This estimate uses the fallowing (current in November 2017) exchange rates of
1USD=27.5776 Birr.
The contingencies are provisions that would take into account anticipated expenses, such as
quantities being higher than expected and unexpected expenses which cannot be quantified in
the contract agreement or resulting from delays. A 10% contingency, applicable to the
construction (Main cost) cost is used.
ICONE Engineering 4
Detailed Engineering Design & Tender Documents Engineering Cost Estimate Report
Rama-Chila-Adi Daro-Semema Road Project
4.01 Summary
The construction works contract costs have been determined based on the tender
document’s Bills of Quantities and summed as shown under table 5: Grand summary
which is computed from all the work items from division 1000 to 11000.
In addition to the above construction costs, the following additional costs to the
Contracting Authority are applicable:
ICONE Engineering 5
Detailed Engineering Design & Tender Documents Engineering Cost Estimate Report
Rama-Chila-Adi Daro-Semema Road Project
Input Qty
ICONE Engineering 6
Detailed Engineering Design & Tender Documents Engineering Cost Estimate Report
Rama-Chila-Adi Daro-Semema Road Project
Total
ICONE Engineering 7
Detailed Engineering Design & Tender Documents Engineering Cost Estimate Report
Rama-Chila-Adi Daro-Semema Road Project
ICONE Engineering 8
Detailed Engineering Design & Tender Documents Engineering Cost Estimate Report