Professional Documents
Culture Documents
Py51a06h DDR 10 08mar05
Py51a06h DDR 10 08mar05
Page 1 of 3
Daily Report
OFFSHORE ORIG DRLG
WELL NAME 24 HRS PROG TMD TVD DFS REPT NO. DATE
PANYU 5-1-A06H 236 1,838 1,759 9.00 10 2004-3-8
RIG NAME & NO. FOREMAN AFE NO. AUTH MD AUTH TVD API NO.
DEVON ENERGY PANYU 5-1 BUSH, BOB 111179 3,462 2,161 -
LAST CASING NEXT CASING DATE OF LAST SAFETY MEETING LAST BOP PRES TEST INCIDENT IDENTIFICATION
13.375 (in) @ 598.00 (m) 9.625 (in) @ 2,534.00 (m) 2004-3-8 2004-3-3 NONE
FIELD NAME LEAKOFF MW WI NRI
PANYU 5-1 9.10 24.50000 24.5000
LITHOLOGY DAILY DRLG DAILY COMP COST DAILY TOTAL COST
SD/SH/CLAY 89,264 0 89,264
CURRENT STATUS CUM DRLG CUM COMP COST CUM TOTAL WELL COST
POOH TO 205 M. 773,845 0 773,845
24 HR FORECAST AFE DHC AFE COMP COST AFE TOTAL PROJ COST
CONT. POH, CHANGE OUT PD & BIT, TEST PD,RIH, DRILL A 2,674,361 1,368,356 4,042,717
DAILY OPERATIONAL COMMENTS: DRILL AHEAD FROM 1602 M TO 1838 M. LOOSING ANGLE,CIRC, POOH TO 205 M.
OPERATIONS SUMMARY
FROM TO HOURS PHASE STEP OPER TASK DESCRIPTION
00:00 20:00 20.00 INTR1 DRLG DRLG DRILL AHEAD F/ 1602M TO 1838M, DROPPING ANGLE.
20:00 20:30 0.50 INTR1 DRLG CIRC CIRCULATE BOTTOMS UP, PUMP SLUG.
20:30 00:00 3.50 INTR1 DRLG TRIP POOH TO 205M. O/P 20K, HOLE SLICK.
NOTE 1:
0000 TO 0030 POOH TO ADN
0030 TO 0100 SAFETY MEETING, REMOVE R/A SOURCE.
0100 TO 0200 CONT. POOH, DOWNLOAD MWD DATA.
0200 TO 0300 L / D POWER DRIVE & BIT (POWER DRIVE WASH OUT).
0300 TO 0400 M/U BIT & POWER DRIVE, TEST, OK.
0400 TO 0500 SURF TEST MWD, OK. LOAD R/A SOURCES.
0500 TO 0600 RIH W/ BHA TO SHOE @ 598 M.
NOTE 2: DOWN HOLE LOSS LAST 24 HRS:190 BBLS.
TOTAL DOWN HOLE LOSS : 582 BBLS.
DENSITY(ppg) 9.10 PP ECD 9.30 MUD DATA DAILY COST CUM COST 8,525
FV PV/YP GELS WL/HTHP FC/T.SOL OIL/WAT %Sand/MBT Ph/pM Pf/Mf Cl Ca H2S LIME ES
66 19/25 8/9 4.30/ 1.00/ / 0.10/2.50 9.00/0.60 0.10/0.80 45,000 1,260
BITS
BIT / RUN SIZE MANUF. TYPE SERIAL NO. JETS OR TFA DEPTH IN DATE IN I-O-D-L-B-G-O-R
3/ 6 12.250 REED RSX163DGS
206276 14/14/14/15/15/15 1,509.00 2004-3-7 1-3-CT-S-D-1-BT-DTF
BIT OPERATIONS
BIT / RUN / CHK# WOB RPM GPM PRESS P BIT HRS 24Hr DIST 24Hr ROP CUM HRS CUM DEPTH CUM ROP
3/ 6/ 1 2,000 / 12,000 105 / 140 903 2,060 728 20.00 329.0 16.45 28.00 422.00 15.07
ITEM DESCRIPTION NO JTS LENGTH O.D. I.D. CONN SIZE CONN TYPE
CROSS OVER 1 0.710 7.380 2.8100
HEAVY WEIGHT DRILL PIPE 6 55.350 6.625 3.0000
DRILLING JAR 1 9.210 6.625 2.7500
HEAVY WEIGHT DRILL PIPE 9 83.120 6.650 3.0000
SURVEY DATA
M.D. INCL. AZIMUTH T.V.D. N/S CUM E/W CUM SECTION M.D. INCL. AZIMUTH T.V.D. N/S CUM E/W CUM SECTION
1,572.85 23.34 84.79 1,517.33 -58.61 241.87 239.28 1,717.40 24.36 84.74 1,648.87 -53.74 301.58 299.16
1,601.85 23.95 85.71 1,543.89 -57.65 253.46 250.90 1,746.44 23.60 85.42 1,675.40 -52.72 313.33 310.95
1,630.66 24.73 86.51 1,570.14 -56.84 265.30 262.77 1,775.41 23.63 85.13 1,701.94 -51.77 324.90 322.55
1,659.50 25.14 85.84 1,596.29 -56.03 277.43 274.93 1,804.48 23.25 84.42 1,728.62 -50.72 336.42 334.10
1,688.38 24.78 83.85 1,622.48 -54.94 289.57 287.10 1,817.52 23.05 84.26 1,740.61 -50.21 341.52 339.22
MATERIALS / CONSUMPTION
ITEM UNITS USAGE ON HAND ITEM UNITS USAGE ON HAND
DIESEL CU MT 165 CEMENT TONS 68
WATER, DRL BBLS 610 BENTONITE TONS 31
BARITE TONS 2 40 FUEL HELICOPTE LITRE 4,179
SUPPORT CRAFT
TYPE NO. REMARKS TYPE NO. REMARKS
BOAT, WORK 1 NANHAI 207 @ PPSO STBY BOAT, WORK 1 NANHAI 220 @ FPSO
BOAT, WORK 1 NANHAI 209 @ PY5-1 STBY BOAT, WORK 1 NANHAI 211 @ TOWN FOR LOAD
BOAT, WORK 1 NANHAI 219 @ PY 4-2 STBY.
REQUIREMENTS
EVACUATION TIME SCHEDULE
14 HRS TOTAL.