Daily Report
OFFSHORE ORIG DRLG
WELL NAME 24 HRS PROG TMD TVD DFS REPT NO. DATE
PANYU 5-1-A06H 243 3,121 2,162 24.00 25 2004-3-23
RIG NAME & NO. FOREMAN AFE NO. AUTH MD AUTH TVD API NO.
DEVON ENERGY PANYU 5-1 BUSH, BOB 111179 3,462 2,161 -
LAST CASING NEXT CASING DATE OF LAST SAFETY MEETING LAST BOP PRES TEST INCIDENT IDENTIFICATION
9.625 (in) @ 2,542.00 (m) (in) @ (m) 2004-3-22 2004-3-18 NONE
FIELD NAME LEAKOFF MW WI NRI
PANYU 5-1 9.30 24.50000 24.5000
LITHOLOGY DAILY DRLG DAILY COMP COST DAILY TOTAL COST
SANDSTONE 82,757 0 82,757
CURRENT STATUS CUM DRLG CUM COMP COST CUM TOTAL WELL COST
DRILL AHEAD. 2,337,993 0 2,337,993
24 HR FORECAST AFE DHC AFE COMP COST AFE TOTAL PROJ COST
DRILL AHEAD. 2,674,361 1,368,356 4,042,717
DAILY OPERATIONAL COMMENTS: DRILL AHEAD, SHORT TRIP, SERVE TDS, DRILL AHEAD TO 3121 M.
OPERATIONS SUMMARY
FROM TO HOURS PHASE STEP OPER TASK DESCRIPTION
00:00 13:00 13.00 INTR2 DRLG DRLG DRILL AHEAD F/ 2878 M TO 3051M.
13:00 13:30 0.50 INTR2 DRLG DEVSUR TAKE SURVEY & CIRC.
13:30 15:00 1.50 INTR2 DRLG TRIP POOH TO 2503 M.
15:00 16:00 1.00 INTR2 MISC RIGSER CHANGE OUT TD'S DIES & SERVICE TD.
16:00 17:00 1.00 INTR2 DRLG STRIP RIH F/ 2503 M TO 3023, WASH DOWN TO 3051M.
17:00 00:00 7.00 INTR2 DRLG DRLG DRILL AHEAD F/ 3051 M TO 3121M.
NOTE 1: 0000 TO 0200 DRILL AHEAD F/ 3121M TO 3137M.
0200 TO 0300 TROUBLESHOOT GRABBER PUMP ON TDS,
GRABBER NOT WORKING.
0300 TO 0500 DRILL AHEAD F 3137M TO 3166 M.
0500 TO 0600 CIRCULATE WHILE TROUBLESHOOTING
GRABBER PUMP,REMOVE SAME.
NOTE 2: DOWN HOLE LOSS LAST 24 HRS : 0 BBLS
TOTAL DOWN HOLE LOSS : 25 BBLS.
DENSITY(ppg) 9.30 PP ECD 10.20 MUD DATA DAILY COST CUM COST 8,525
FV PV/YP GELS WL/HTHP FC/T.SOL OIL/WAT %Sand/MBT Ph/pM Pf/Mf Cl Ca H2S LIME ES
59 18/44 11/12 3.00/ 1.00/ / 0.10/ 8.80/1.50 0.05/1.10 31,000 580
BITS
BIT / RUN SIZE MANUF. TYPE SERIAL NO. JETS OR TFA DEPTH IN DATE IN I-O-D-L-B-G-O-R
6/ 10 8.500 HUGHES HCR606 7202241 14/14/14/14/14/14 2,542.50 2004-3-19 1-1-WT-S-D-0-NO-TD
BIT OPERATIONS
BIT / RUN / CHK# WOB RPM GPM PRESS P BIT HRS 24Hr DIST 24Hr ROP CUM HRS CUM DEPTH CUM ROP
6 / 10 / 1 5,000 / 12,000 110 / 135 550 2,090 318 20.00 243.0 12.15 55.00 578.50 10.52
ITEM DESCRIPTION NO JTS LENGTH O.D. I.D. CONN SIZE CONN TYPE
SENSOR SUB 1 2.860 5.500
ORD SUB 1 2.430 6.690
CNN SUB 1 2.360 6.810 3.0000
MAP SUB 1 1.140 6.875 2.8750
STOP SUB 1 0.510 6.938 2.6250
FLOAT SUB 1 0.660 6.563 2.8750
FILTER SUB 1 1.720 6.938 3.0000
NM STABILIZER 1 1.530 6.500 2.8125
NMCSDP 1 9.200 5.000 2.8125
NMCSDP 1 9.430 5.000 2.8125
6-1/2 DRILLING JAR 1 9.800 6.500 2.7500
41 STANDS 5" DRILL PIPE 41 1,185.100 5.000 4.2500
HEAVY WEIGHT DRILL PIPE 18 166.240 6.625 3.0000
SURVEY DATA
M.D. INCL. AZIMUTH T.V.D. N/S CUM E/W CUM SECTION M.D. INCL. AZIMUTH T.V.D. N/S CUM E/W CUM SECTION
2,921.20 89.12 89.11 2,160.33 30.67 1,260.56 1,261.10 3,038.20 90.04 85.50 2,160.65 34.60 1,377.47 1,378.07
2,951.40 89.92 89.05 2,160.59 31.15 1,290.75 1,291.29 3,065.80 90.07 84.24 2,160.62 37.07 1,404.96 1,405.65
2,980.30 89.98 88.21 2,160.61 31.84 1,319.65 1,320.18 3,094.70 88.87 83.43 2,160.89 40.17 1,433.69 1,434.50
3,009.20 89.92 87.69 2,160.64 32.88 1,348.53 1,349.08 3,123.60 89.73 83.20 2,161.24 43.54 1,462.40 1,463.33
MATERIALS / CONSUMPTION
ITEM UNITS USAGE ON HAND ITEM UNITS USAGE ON HAND
CEMENT TONS 20 DIESEL CU MT 168
BENTONITE TONS 31 WATER, DRL BBLS 680
FUEL HELICOPTE LITRE 660 3,526 BARITE TONS 70
SUPPORT CRAFT
TYPE NO. REMARKS TYPE NO. REMARKS
BOAT, WORK 1 NH207 @ PY4-2 BOAT, WORK 1 NH221 @ TOWN
BOAT, WORK 1 NH209 @ TOWN BOAT, WORK 1 NH255 @ PY5-1
BOAT, WORK 1 NH219 @ PY5-1 BOAT, WORK 1 NH211@ TOWN