FORM 'J` (COMPREHENSIVE)
UNDER S.B.M.-2.0 (I&D WORK)
Central State
Sl. Centa- Total Cost ULB Share
Description of item Share Share
No. ge (Rs. in Lakh) (17%)
(50%) (33%)
1 Basic Cost of work as per
1001.27
General Abstract of Cost
2 Deduction for Profficiency on '1' 5% -50.06
3 Total 951.21 475.60 313.90 161.71
4 Add Labour cess on '3' 1% 9.51 4.76 3.14 1.62
5 Add GST on '3' 18% 171.22 85.61 56.50 29.11
6 Total Cost of Work (3+4+5) 1131.94 565.97 373.54 192.43
7 Centage on '3' 10.00% 95.12 95.12
8 Power Connection With GST 89.35 44.68 29.49 15.19
9 Total Project Cost (6+7+8) 1316.41 610.64 498.15 207.62
10 Operation and maintenance for 5 year 571.44 571.44
11 Total Cost (8+9) 1887.85 610.64 498.15 779.06