Updated Work Schedule - DC Body Publika KL
Updated Work Schedule - DC Body Publika KL
WEEK & DATE Oct 23, 2023 Oct 30, 2023 Nov 6, 2023 Nov 13, 2023 Nov 20, 2023 Nov 27, 2023 Dec 4, 2023 Dec 11, 2023 Dec 18, 2023
23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
SCOPE OF WORK PROGRESS START END
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
PRELIMINARIES
ARCHITECTURE WORK
Brick Wall, Partitioning Work & Glass Partitioning Work 90% 10/31/2023 11/11/2023
CARPENTRY WORK
Treatment Room 1
Treatment Room 2
Treatment Room 3
Treatment Room 4
WEEK & DATE Oct 23, 2023 Oct 30, 2023 Nov 6, 2023 Nov 13, 2023 Nov 20, 2023 Nov 27, 2023 Dec 4, 2023 Dec 11, 2023 Dec 18, 2023
23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
SCOPE OF WORK PROGRESS START END
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
Consultation Room 5
Consultation Room 6
Staff Pantry
Salad Bar
LOOSE FURNITURE
POST CONSTRUCTION
NOTE: This Master Work Program is based on the overall planning of the design and construction phase. Any delays or changes to the masterwork program dateline, we will update and inform to the client.