INSPECTION & TESTING REQUIREMENTS REVISION: 04/05/2017 CODE NUMBER: PAGE:

SAUDI ARAMCO FORM-175 REPLACES: 06/16/2016 IR026400 1 of 2


SCOPE: FITTINGS: For Use In HOT TAP and/or Stopple Operations; Wet & Sweet Sour Services; Include - Split Tees, Stopple Fittings, Full
Encirclement Saddles, Flanges, Lock-O-Ring (LOR) Flanges

TEST AND INSPECTION PER: 02-SAMSS-006, & Specifications As Noted Below

(1).VISUAL INSPECTION BY BUYER INSPECTION REPRESENTATIVE


(2) REVIEW AND VERIFICATION OF MATERIAL CERTIFICATES AND INSPECTION RECORDS
(3) SUBMISSION OF MANUFACTURING, INSPECTION AND QUALITY RECORDS
0010
0010
***R X
Pre-Fabrication/Production Requirements
Material Test Reports (MTR#s)
Specification Details / Notes:
02-SAMSS-006: Includes chemical composition and
mechanical testing. The material for the flange shall conform
with 02-SAMSS-011. See Note 2.

0020 R Welder Qualification Records Per ASME Sec. IX.

0030 R X Welding Procedures Specifications (WPS#s) and Procedure Per ASME Sec. IX and 02-SAMSS-006
QualificationRecords (PQR#s)

0040 R X NDT Personnel & Procedures Check for valid personnel certification and procedure. RT Film
interpreter to meet SAEP-1142 requirements.

0020
0010
***R X
In process inspection & test requirement
Hardness test
Specification Details / Notes:
Per 02-SAMSS-006

0020 R X Heat treatment Per 02-SAMSS-006

0030 Nondestructive Testing: Per 02-SAMSS-006

0040 R X a) Radiographic Testing All butt welds in fabricated fittings shall be 100% radiographed
in accordance with ASME VIII Div.1, UW-51.

0050 R X b) Magnetic Particle Testing 02-SAMSS-006: For full penetration groove welds, in
accordance with ASME VIII Div. 1 Appx. 8.

0060 R X c) Magnetic Particle Testing or Dye Penetrant of Weld Ends for 02-SAMSS-006: All butt weld ends shall be tested PT (ASTM
Field Welding E165). Accept/reject to ASME Sec VIII, Div. 1, Appx. 8 or MT
(ASME Sec. VIII Div. 1 Appx. 8).

0070 R X d) Ultrasonic Testing of Plates In accordance with ASTM A578, acceptances level C or equal.

0080 R X Heat Treatment after Forming and Welding 02-SAMSS-006 and A234 or MSS SP-75: Limitations denoted
in SAMSS.

0090 X Repair Procedure of Defects Per 02-SAMSS-006. Vendor shall submit details of the repair
procedure and nondestructive testing of the repair area for
Inspection’s approval prior to making the repair.

0030 *** Final inspection & test requirements Specification Details / Notes:

IR026400 Continued...
INSPECTION & TESTING REQUIREMENTS REVISION: 04/05/2017 CODE NUMBER: PAGE:
SAUDI ARAMCO FORM-175 REPLACES: 06/16/2016 IR026400 2 of 2
(1).VISUAL INSPECTION BY BUYER INSPECTION REPRESENTATIVE
(2) REVIEW AND VERIFICATION OF MATERIAL CERTIFICATES AND INSPECTION RECORDS
(3) SUBMISSION OF MANUFACTURING, INSPECTION AND QUALITY RECORDS
0010 W R X Hydrostatic Tests Per 02-SAMSS-006

0020 H X Final Visual and dimensional Inspections Per 02-SAMSS-006

0030 W R X Marking Per 02-SAMSS-006

0040 W X Preparation for Shipping Per 02-SAMSS-006 and Purchase Order requirement.

0050 R X Compliance Certificate

0060 R X Product Test Certificate and records As per applicable SAMSS and IR

Notes:
(1) Refer detailed instruction sheet SA175 form IR000003 of inspection requirement for ideal use of this form.
(2) For sour service, Plates shall comply with 01-SAMSS-016, welded Pipes shall be HIC tested in accordance with 01-SAMSS-035 or
01-SAMSS-043 as applicable

End of IR026400