Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

The 19th International Symposium on High Voltage Engineering, Pilsen, Czech Republic, August, 23 – 28, 2015

BUSHING MONITORING TO PROTECT POWER TRANSFORMER


AGAINST BUSHING FAILURES
1* 1 1
S. Coenen , T. Stirl , B. Dolata
1
Alstom Grid GmbH, Rheinstr. 73, 41065 Moenchengladbach, Germany
*Email: <Sebastian.coenen@alstom.com>

Abstract: High voltage condenser bushings of power transformers, according to their


construction and age, are amongst the most endangered components from all operating
equipment used. In the past, off-line measurements like the measurement of bushing
insulator capacitances and measurement of the dissipation factor were carried out for
determining the operational state. Today, modern microprocessor and computer
technology makes it possible to carry out the measurements and analysis continuous
within a monitoring concept. The monitoring of the electrical measurement quantities is
achieved by a voltage measurement consisting of a bushing adaptor, directly connected
to the measurement tap of the bushing and connected voltage sensor. The output signal
of one phase is compared with two remaining phases. Short and long term grid
unbalances can be filtered by certain algorithms. The paper discusses the preconditions
when modern bushing monitoring solutions are ready to protect bushing from failures
caused by breakdown of layers. The thresholds criteria can be distinguished by the
design of condenser bushings as the measured voltage jump caused by breakdown of
capacitive layers is depending on the number of layers. As the resulting dielectric stress
on the remaining layers increases, the operation of the bushing leads to increased risk for
failure, i.e. at least a warning should be generated automatically. The breakdown of
further layer might lead in a cascade breakdown ending with a catastrophic bushing
failure, i.e. an alarm should be generated and the transformer should be de-energised.

1 INTRODUCTION analyse conditions and to initiate subsequent


actions.
Today, utilities focus, on one hand, on improving or
maintaining system security by preventing outages,
and on the other, reducing operation and
maintenance costs of their assets. Both objectives
rely on information about asset conditions. As
such, an increasing number of power transmission
and power generation utilities are equipping their
power transformers with continuous on-line
monitoring systems. Step-by-step, this equipment
becomes a standard configuration of power Figure 1: Example of expert system with alarm
transformers. message caused by increased bushing
capacitance of transformer 1. Information and
A power transformer consists of several recommendations for service and maintenance can
components: transformer tank with active part and be displayed and data can be correlated to further
oil-paper insulation, conservator, cooling unit, on- information or other transformers
load tap changer and bushings, to mention some.
These components can be fitted with various The next step to prevent failures could be an
sensors, which are integrated into one monitoring automatic activation of protection by means of a
IED (Intelligent Electronic Device) by means of continuous on-line monitoring system. The paper
analogue or digital signals and different protocols, discusses the preconditions when modern bushing
building a comprehensive on-line condition monitoring solutions are ready to protect bushing
monitoring and expert system. against failures caused by breakdown of layers.
The thresholds criteria can be distinguished by the
Raw data acquired from a wide range of demand- design of condenser bushings as the measured
specific selectable sensors are analysed by means voltage jump caused by breakdown of capacitive
of implemented models, and stored in the on-line layers is depending on the number of layers. As
condition monitoring and expert system. Data the resulting dielectric stress on the remaining
acquisition and processing alone are of limited layers increases, the operation of the bushing
value. An expert system, see Figure 1, included in leads to increased risk for failure, i.e. at least a
the monitoring device becomes a powerful tool to warning should be generated automatically. The
breakdown of further layer might lead in a cascade
breakdown ending with a catastrophic bushing 2.2 Bushing capacitance C and dielectric
failure, i.e. an alarm should be generated and the dissipation factor tanδ
transformer should be de-energised.
The measurement of the bushing capacitance C
2 BUSHINGS and the dielectric dissipation factor tan δ, see
Figure 2, are important parameters for evaluating
High voltage condenser bushings of power trans- the operational state of a high voltage bushing.
formers, according to their construction and age, The dissipation factor is obtained from
are amongst the most endangered components tan δ = 1/RωC. In the case of a new resin-bonded
from all operating equipment used. In the past, off- paper bushing, it is in the range 0.5 ... 0.7 %. In the
line measurements like the measurement of case of resin-impregnated bushings, it is in the
bushing insulator capacitances and measurement range 0.25 ... 0.45 %, and for oil-impregnated
of the dissipation factor were carried out bushings, values between 0.25 ... 0.5 % are
successfully for determining the operational state. normal.
Today, modern microprocessor and computer
technology makes it possible to carry out these
procedures on-line with the help of a monitoring
system.

2.1 Capacitive controlled insulator bushings

In the voltage range from 110 kV upwards, modern


bushings are generally designed with closely
stepped capacitive control layers [1]. The insulator
body is manufactured in a coil winding process.
The basic insulating systems of capacitive Figure 2: Equivalent circuit diagram and vector
controlled high voltage bushings can be classified diagram of the dielectric loss factor tan δ
as:
Dielectric losses in the insulation result in a
• Resin-bonded paper bushings (RBP) capacitive loss current in the dielectric material.
• Resin-impregnated paper bushings (RIP) The reason for this can be found in the electrical
• Resin-impregnated synthetic bushings (RIS) properties of the insulation structure [1].
• Oil-impregnated paper bushings (OIP)
Depending on the ageing, the bushing capacitance
The inner insulation structure of resin-bonded and the tan δ can change. Table 1 shows guide
paper bushings consists of resin-coated material, values for tan δ and capacitance values as
which is glued under high temperature and examples for resin-bonded paper bushings. When
pressure in normal ambient conditions. In the case these limiting values are reached, continued
of resin-impregnated bushings, the insulator operation is not recommended.
consists of crepe paper with wrapped aluminium
coatings. This is dried and impregnated in vacuum. Table 1: Limit values for the dielectric loss factor
A resin-impregnated synthetic bushing the major tan δ and capacitive increase Δ C for resin-bonded
insulation consists of a core wound from synthetics paper bushings [6]
subsequently impregnated with a curable resin. In
the case of oil-impregnated bushings, the UN [kV] tan  [%]  C [%]
insulating body consists of kraft paper with 123 2.0 20
wrapped aluminium or graphite coatings, which are 245 1.5 15
dried and oil-impregnated in vacuum. The outer 420 1.0 10
insulation structure is generally made up of
porcelain or, more recently, of silicon.
For protection purpose periodic off-line testing of
What is common to all constructions is that they bushings is not sufficient and those changings
are subjected to very high mechanical, electrical need to be detected during operation of power
and thermal stresses during operation. This results transformers with on-line monitoring systems.
in ageing and hence to a change in the operational When detecting those changes, the protection of
state [2]. Thus, partial breakdowns in the insulation bushings and transformers can only be guaranteed
system can affect the operational safety to such an by direct de-energization of the transformer.
extent that further safe operation is not guaranteed Therefore the discussion is necessary to involve
any more [3, 4]. bushing monitoring into the protection devices of
power transformers. The possibility of false alarms
by external environmental influences, the
necessary and achievable accuracy is discussed in
the following. A focus of discussion in the following The voltage sensor, see Figure 3 right, essentially
is also on the reliability and acceptability of consists of a capacitance CM, which normally has
threshold values. values of 1...2 µF, see sketch in Figure 4.

Other reasons for a change in the values of tan δ


and Δ C are external environmental influences like
moisture and dirt on the outside on the porcelain.
An increase in the Δ C can also be caused by an
oil-impregnation in the case of resin-bonded paper
bushings. Apart from a consideration of the
absolute values of tan δ and Δ C, an analysis of
the trend is of great importance.

Thus, an increase in the Δ C for all bushing types


indicates partial breakdowns between control
layers (Table 2). Hence, for instance, if one of the
60 control layers of a typical 420 kV bushing
Figure 4: Sketch of bushing and equivalent circuit
breaks down, its capacitance changes by a value
diagram of the bushing and the voltage sensor
of 1.7 %. A short-circuit between two control layers
does not directly result in bushing failure, but the
Since CM >> C2 (with C2 ≈ 300 pF), I2 is practically
likelihood of a complete break-down of the
0. The resistance R terminates the connected
insulation raises with increasing number of
coaxial cable with a surge impedance of 50 Ω. The
defective layers and a safe operation of the
potential divider ratio between C1 and CM is
bushing and the whole transformer cannot be
dimensioned that a measurement voltage UM of
guaranteed any more.
57 V AC is set. In addition, there is an overvoltage
suppressor (Ü) installed, which protects the sensor
Table 2: Increase in capacitance delta C in case of
and the cable from overvoltages, and as there are
a partial breakdown between control layers for oil-
no electronic components used in the sensor at the
impregnated bushings.
bushing, this measurement procedure is not
sensitive to electromagnetic emission. Another
UN [kV] Number of control layers [n]  C [%] advantage of the technology used is in the high
123 28 3.6 signal-to-noise ratio owing to the transmission of a
245 42 2.4 voltage signal of about 57 V AC.
420 60 1.7
3.1 OPERATING VOLTAGES AND
OVERVOLTAGES
Hence the internal design of bushings defines the
thresholds of change in capacity for generating trip For the measurement of operating voltages, the
signals and in the following a suitable capacitive voltage sensor already described is
measurement set-up with reachable accuracy is used. In addition overvoltages can also be
presented. detected. Transient overvoltages represent a
significant endangerment potential for the
3 MONITORING VALUES insulation. Therefore, the detection and evaluation
of these transients is of great significance for the
The monitoring of the electrical measurement evaluation of the bushing insulator reliability [5] and
quantities is achieved with a voltage adaptor and besides this also for the insulation system of the
voltage sensor. The adaptor is connected directly active part of the transformer.
to the measurement tap of the bushing, see
Figure 3, left. This design allows a reliable Overvoltages can be caused by lightning impulses
measurement with a bandwidth of up to 2 MHz. and switching actions, e. g. the switching on of
overhead lines and chokes. In particular, bushings
of transformers in GIS or HVDC-switchgear are
subjected to fast transient overvoltages. Since their
size and shape are often not known, there can be
a failure of operating equipment, which can be
avoided by taking specific countermeasures.
Furthermore, information about the amplitude of
overvoltages and the combination with the on-line
measures and analysing data of e.g. transient
Figure 3: Bushing voltage adaptor fitting for
overvoltage monitoring modules is of great
different types of bushings and voltage sensor with
importance in case of root cause analysis after the
adopted measuring capacity
occurrence of a damage.
Figure 5 shows, as an example, three-phase very high resolution in terms of time in order to
operating voltages on the 275 kV bushings of a achieve this accuracy. In this case, the sampling
185 MVA generator transformer together with rate is 10 µs, to detect the zero crossing of the
detected overvoltages recorded over a period of 4 50/60 Hz AC voltage.
days.
For the acquisition of the Δ tan δ, an accuracy of at
least ± 0.15 % must be reached. The reason for
this is that the dissipation factor for the various
types of construction of bushings moves in the
range of about 0.5 % and a maximum warning
threshold has to be assumed at about 0.7 %. In the
case of offline measurements, it is in keeping with
the current state-of-the-art to determine the
dissipation factor using a reference capacitance
and a reference voltage. These aids are not
available on-line. Rather, in the case of an on-line
measurement, as in the process described here,
the voltage of another phase is used as a
reference.

Different types of interpretation methods (e.g.


Figure 5: Continuously monitored 3-phase change of dissipation factor vs. sum current
operating voltages (phases L1, L2, L3) with phasor) with their advantages and disadvantages
overvoltages, voltage fluctuations and network are discussed in [7, 9] and it is the authors opinion
asymmetries (period 4 days) that the tan δ value cannot be a protection criteria.
As there is no comparable link to internal design
What can be seen are some voltage spikes in the which allows a clear threshold. A condition
graph, which are caused by the overvoltages that assessment by tan δ measurements needs the
occur. In addition voltage fluctuations in the line consultancy of an expert, like e.g. PD
voltage and network asymmetries of up to 1 % can measurement analysis, and an automatic tripping
be clearly seen from the graph. is not meaningful. Furthermore there are no case
studies known to the authors, where only the
3.2 Change of Capacity – Δ C change of on-line measured tan δ values indicated
a bushing failure.
The monitoring of the change in the bushing
capacitances (Δ C) is achieved by means of a 4 CASE STUDIES
three-phase voltage measurement. Here, the
output signal of the presented voltage sensor is 4.1 350 MVA, 420 kV Transformer
compared with the two remaining phases. The
result of the algorithm is based on an averaging in The effect of a partial flashover of 2 layers of a
order to eliminate voltage fluctuations in the 420 kV bushing is depicted in Figure 6. The 3-
network in this manner. The influences of phase operating voltages (phase L1, L2, L3)
temperature can be compensated by the three- together with overvoltages of the 350 MVA
phase measurement principle. In consequence, the regulating transformer are shown.
relative change in capacitance is used for
determining the Δ C. This method has also proven
itself over a prolonged time in the field [7] also
impressing through its high signal-to-noise ratio.

Hence the change of capacity can be chosen as


protection criteria and two available case studies
will demonstrate in the following that possibility.

3.3 Change of dissipation factor – tan δ

The measurement of the phase angle between the


three phases makes it possible to detect changes
in the dielectric dissipation (loss) factor tan δ. The
difficulty in the measurement technique is in being
able to detect even very slight changes. For
example, a change in the loss factor tan δ by 0.1 % Figure 6: Detection of partial flashover of 420 kV
means that the phase angle changes by 0.057 °. bushing and avoidance of collateral damage of
The measurement data has to be recorded with a 350 MVA regulating transformer, 3-phase
operating voltages (phase L1, L2, L3) with In Figure 7 it can be seen that overvoltages have
overvoltages (large figure), identified by change of been detected prior to the fault, which might have
capacitance Δ C (small figure) been a possible root cause for the bushing failure.
Therefore comprehensive monitoring systems can
On 27.11.2004 after only 1 ½ years of bushing be used to correlate transient overvoltages and
operation a warning was generated automatically capacity change of bushings for a deeper
by the on-line monitoring system identified by a understanding of those additional dielectric
change in the bushing capacitance by 3.6 % stresses.
(Figure 6, small figure).
In case the monitoring system would have been
After switching off the transformer an off-line used to protect the bushing with appropriate
measurement was performed and proved the on- thresholds, the system might have protected the
line determined value. The bushing was shipped to transformer for that unscheduled tripping by raising
the manufacturer who also confirmed the result. a warning 3 days in advance and an alarm 6 hours
Due to the installation of an on-line monitoring in advance with a possible de-energization of the
system a collateral damage could be prevented. In transformer.
addition the system indicated that the transformer
has been affected by overvoltages which could 5 CONCLUSION
have been the most probable reason for the
damage. The focus in this paper was to demonstrate how
capacitive controlled bushings can be protected by
4.2 850 MVA, 400 kV Transformer on-line monitoring devices. The underlying
principle of the measurement technique is based
In the evening of 28th of June 2013 a 850 MVA, on the use of a capacitive voltage sensor that is
400/27kV transformer, manufactured in 2000, was installed at the measurement tap of the bushing. In
tripped due to a catastrophic bushing failure of high this manner, the operational voltages can be
voltage side in phase V. Analysing the measured, and deriving therefrom, overvoltages
measurement data of the monitoring system and transient voltages can be detected.
reveals that the catastrophic failure was detectable
approximately 3 days in advance, see Figure 7. The change in the bushing capacitance as the
most important characteristic quantity for
determining the operational state can be analyzed
reliably on this basis. Hence the change of
capacitance can be chosen as protection criteria
and thresholds are clear distinguished by bushings
internal design and number of layers.

Practical examples have shown that the change in


the dielectric dissipation factor can be acquired,
but provides less information than the
recommended simple on-line monitoring of the
Figure 7: Increase of measured voltage (phase to change in the bushing capacitance. Hence the
ground voltage measurement on bushing test tap change of tan δ is not seen as protection criteria as
at high voltage side) on a failed bushing of a possible threshold are not linkable to internal
850 MVA transformer design and there is no case study available for
bushing failures linked to only tan δ changes.
On 26th of June, the voltage measurement on Tan δ monitoring might still be used to monitor the
phase V showed a voltage rise of approx. 2.5 % bushing condition on a long time period, i.e.
what correlates to one layer breakdown in the monitor the aging of bushings.
condenser bushing. Beginning approximately 6
hours in advance of the trip a cascade breakdown Case studies demonstrated, that a critical damage
inside the bushing occurs and the voltage rose up of a 350 MVA grid coupling transformer could be
to additional 15 % of nominal voltage. However, in avoided by a detection of a partial flashover of
this case the alarm management functionality of layers of a bushing indicated by a change in the
the on-line condition monitoring system was not bushing capacitance. Another collateral damage of
implemented into the SCADA system. The active an 850 MVA transformer bushing might have been
use of the bushing monitoring functionality would prevented in case the bushing monitoring system
have avoided that major bushing failure and the based on capacitive voltage measurements would
unscheduled outage. Due to that experience the have been authorized to trip the transformer.
utility decided to implement from now on the
bushing monitoring into the active alarm For certain types of bushings in case of certain
management. chance of on-line monitored capacity automated
alarming and tripping of transformers seems to
become feasible. This article aims to start
discussions between bushing and transformer
manufacturer and users about thresholds, concrete
preconditions and subsequent actions including
automated tripping.

This article states that the monitoring principal


which it´s so far used technology might be a base
for future development of protection devices, as
the specification for protection devices is different
to monitoring devices, e.g. real time
communication.

REFERENCES
[1] D. Kind, H. Kärner: “High voltage Insulation
Technology”, Friedr. Vieweg & Sohn,
Braunschweig, 1982
[2] ”An International Survey on Failures of Large
Power Transformers in Service”, CIGRE
Working Group 12.05, Electra, No. 88, 1983
[3] K. Widmaier: “Bushing – a very highly stressed
compo-nent”, MICAFIL Symposium, Stuttgart,
2002
[4] [8] R. Krump, H. Frielingsdorf: “Dry type
Bushings for Operation under difficult
Conditions”, Transform, Munich, 2001
[5] S. Tenbohlen, T. Stirl et al.: “Experience-based
Evaluation of Economic Benefits of On-line
Monitoring Systems for Power Transformers”,
CIGRE Session 2002, paper 12-110, Paris,
2002
[6] S. Tenbohlen et al.: “Enhanced Diagnosis of
Power Transformers using On- and Off-line
Methods: Results, Examples and Future
Trends”, CIGRE Session 2000, paper 12-204,
Paris, 2000
[7] T. Stirl, et al.: “On-line Condition Monitoring
and Diagnosis for Power Transformers their
Bushings, Tap Changer and Insulation
System”, CMD 2006, Korea 2006
[8] F. Lachman et al.: „On-Line Diagnostics of
High Voltage Bushings and Current
Transformers Using the Sum Current method“,
IEEE Transactions on Power Delivery, Vol. 15,
No. 1, January 2000
[9] J. Watson et al.: “Interpretation of Data from
On-line Bushing Monitoring Systems”, Cigre
Session 2014, paper A2-111, Paris 2014

You might also like