Work Program of 2 Storied 10 Nos RCC Wash Block

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Work Schedule

ID Task Name Duration Start Finish Predecessors Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
1 10 nos 2 storied RCC Wash Block 323 days Mar 31 '24 Mar 4 '25
2 Mobilization of all Equipment, 20 days Mar 31 '24 Apr 28 '24
Materials & Manpower
3 Wash Block-01 108 days Apr 29 '24 Aug 21 '24
4 Earth Excavation 4 days Apr 29 '24 May 2 '24 2
5 Footing 4 days May 3 '24 May 6 '24 4
6 Short column & Beam 7 days May 7 '24 May 13 '24 5
7 Column & Slab of 1st floor 10 days May 14 '24 May 23 '24 6
8 Column & Slab of 2nd floor 10 days May 24 '24 Jun 2 '24 7
9 Brick work 10 days Jun 3 '24 Jun 12 '24 8
10 Sanitary & Electric work 7 days Jun 13 '24 Jun 26 '24 9
11 Interior work 7 days Jun 27 '24 Jul 3 '24 10
12 Tiles 6 days Jul 4 '24 Jul 9 '24 11
13 Boring work 3 days Jul 10 '24 Jul 12 '24 12
14 Others work 40 days Jul 13 '24 Aug 21 '24 13
15 Wash Block-02 111 days May 3 '24 Aug 28 '24
16 Earth Excavation 4 days May 3 '24 May 6 '24 4
17 Footing 4 days May 7 '24 May 10 '24 16
18 Short column & Beam 7 days May 14 '24 May 20 '24 6
19 Column & Slab of 1st floor 10 days May 21 '24 May 30 '24 18
20 Column & Slab of 2nd floor 10 days May 31 '24 Jun 9 '24 19
21 Brick work 10 days Jun 10 '24 Jun 26 '24 20
22 Sanitary & Electric work 7 days Jun 27 '24 Jul 3 '24 21
23 Interior work 7 days Jul 4 '24 Jul 10 '24 22
24 Tiles 6 days Jul 11 '24 Jul 16 '24 23
25 Boring work 3 days Jul 17 '24 Jul 19 '24 24
26 Others work 40 days Jul 20 '24 Aug 28 '24 25
27 Wash Block-03 114 days May 7 '24 Sep 4 '24
28 Earth Excavation 4 days May 7 '24 May 10 '24 16
29 Footing 4 days May 11 '24 May 14 '24 28
30 Short column & Beam 7 days May 21 '24 May 27 '24 18
31 Column & Slab of 1st floor 10 days May 28 '24 Jun 6 '24 30
32 Column & Slab of 2nd floor 10 days Jun 7 '24 Jun 23 '24 31
33 Brick work 10 days Jun 24 '24 Jul 3 '24 32
34 Sanitary & Electric work 7 days Jul 4 '24 Jul 10 '24 33
35 Interior work 7 days Jul 11 '24 Jul 17 '24 34
36 Tiles 6 days Jul 18 '24 Jul 23 '24 35
37 Boring work 3 days Jul 24 '24 Jul 26 '24 36
38 Others work 40 days Jul 27 '24 Sep 4 '24 37
39 Wash Block-04 108 days Jul 10 '24 Oct 25 '24
40 Earth Excavation 4 days Jul 10 '24 Jul 13 '24 12
41 Footing 4 days Jul 14 '24 Jul 17 '24 40
42 Short column & Beam 7 days Jul 18 '24 Jul 24 '24 41
43 Column & Slab of 1st floor 10 days Jul 25 '24 Aug 3 '24 42
44 Column & Slab of 2nd floor 10 days Aug 4 '24 Aug 13 '24 43
45 Brick work 10 days Aug 14 '24 Aug 23 '24 44
46 Sanitary & Electric work 7 days Aug 24 '24 Aug 30 '24 45
47 Interior work 7 days Aug 31 '24 Sep 6 '24 46
48 Tiles 6 days Sep 7 '24 Sep 12 '24 47
49 Boring work 3 days Sep 13 '24 Sep 15 '24 48
50 Others work 40 days Sep 16 '24 Oct 25 '24 49
51 Wash Block-05 108 days Jul 17 '24 Nov 1 '24
52 Earth Excavation 4 days Jul 17 '24 Jul 20 '24 24
53 Footing 4 days Jul 21 '24 Jul 24 '24 52
54 Short column & Beam 7 days Jul 25 '24 Jul 31 '24 53
55 Column & Slab of 1st floor 10 days Aug 1 '24 Aug 10 '24 54
56 Column & Slab of 2nd floor 10 days Aug 11 '24 Aug 20 '24 55
57 Brick work 10 days Aug 21 '24 Aug 30 '24 56
58 Sanitary & Electric work 7 days Aug 31 '24 Sep 6 '24 57
59 Interior work 7 days Sep 7 '24 Sep 13 '24 58
60 Tiles 6 days Sep 14 '24 Sep 19 '24 59
61 Boring work 3 days Sep 20 '24 Sep 22 '24 60
62 Others work 40 days Sep 23 '24 Nov 1 '24 61
63 Wash Block-06 108 days Jul 24 '24 Nov 8 '24
64 Earth Excavation 4 days Jul 24 '24 Jul 27 '24 36
65 Footing 4 days Jul 28 '24 Jul 31 '24 64
Work Schedule
ID Task Name Duration Start Finish Predecessors Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
66 Short column & Beam 7 days Aug 1 '24 Aug 7 '24 65
67 Column & Slab of 1st floor 10 days Aug 8 '24 Aug 17 '24 66
68 Column & Slab of 2nd floor 10 days Aug 18 '24 Aug 27 '24 67
69 Brick work 10 days Aug 28 '24 Sep 6 '24 68
70 Sanitary & Electric work 7 days Sep 7 '24 Sep 13 '24 69
71 Interior work 7 days Sep 14 '24 Sep 20 '24 70
72 Tiles 6 days Sep 21 '24 Sep 26 '24 71
73 Boring work 3 days Sep 27 '24 Sep 29 '24 72
74 Others work 40 days Sep 30 '24 Nov 8 '24 73
75 Wash Block-07 108 days Sep 13 '24 Dec 29 '24
76 Earth Excavation 4 days Sep 13 '24 Sep 16 '24 48
77 Footing 4 days Sep 17 '24 Sep 20 '24 76
78 Short column & Beam 7 days Sep 21 '24 Sep 27 '24 77
79 Column & Slab of 1st floor 10 days Sep 28 '24 Oct 7 '24 78
80 Column & Slab of 2nd floor 10 days Oct 8 '24 Oct 17 '24 79
81 Brick work 10 days Oct 18 '24 Oct 27 '24 80
82 Sanitary & Electric work 7 days Oct 28 '24 Nov 3 '24 81
83 Interior work 7 days Nov 4 '24 Nov 10 '24 82
84 Tiles 6 days Nov 11 '24 Nov 16 '24 83
85 Boring work 3 days Nov 17 '24 Nov 19 '24 84
86 Others work 40 days Nov 20 '24 Dec 29 '24 85
87 Wash Block-08 108 days Sep 20 '24 Jan 5 '25
88 Earth Excavation 4 days Sep 20 '24 Sep 23 '24 60
89 Footing 4 days Sep 24 '24 Sep 27 '24 88
90 Short column & Beam 7 days Sep 28 '24 Oct 4 '24 89
91 Column & Slab of 1st floor 10 days Oct 5 '24 Oct 14 '24 90
92 Column & Slab of 2nd floor 10 days Oct 15 '24 Oct 24 '24 91
93 Brick work 10 days Oct 25 '24 Nov 3 '24 92
94 Sanitary & Electric work 7 days Nov 4 '24 Nov 10 '24 93
95 Interior work 7 days Nov 11 '24 Nov 17 '24 94
96 Tiles 6 days Nov 18 '24 Nov 23 '24 95
97 Boring work 3 days Nov 24 '24 Nov 26 '24 96
98 Others work 40 days Nov 27 '24 Jan 5 '25 97
99 Wash Block-09 108 days Sep 27 '24 Jan 12 '25
100 Earth Excavation 4 days Sep 27 '24 Sep 30 '24 72
101 Footing 4 days Oct 1 '24 Oct 4 '24 100
102 Short column & Beam 7 days Oct 5 '24 Oct 11 '24 101
103 Column & Slab of 1st floor 10 days Oct 12 '24 Oct 21 '24 102
104 Column & Slab of 2nd floor 10 days Oct 22 '24 Oct 31 '24 103
105 Brick work 10 days Nov 1 '24 Nov 10 '24 104
106 Sanitary & Electric work 7 days Nov 11 '24 Nov 17 '24 105
107 Interior work 7 days Nov 18 '24 Nov 24 '24 106
108 Tiles 6 days Nov 25 '24 Nov 30 '24 107
109 Boring work 3 days Dec 1 '24 Dec 3 '24 108
110 Others work 40 days Dec 4 '24 Jan 12 '25 109
111 Wash Block-10 108 days Nov 17 '24 Mar 4 '25
112 Earth Excavation 4 days Nov 17 '24 Nov 20 '24 84
113 Footing 4 days Nov 21 '24 Nov 24 '24 112
114 Short column & Beam 7 days Nov 25 '24 Dec 1 '24 113
115 Column & Slab of 1st floor 10 days Dec 2 '24 Dec 11 '24 114
116 Column & Slab of 2nd floor 10 days Dec 12 '24 Dec 21 '24 115
117 Brick work 10 days Dec 22 '24 Dec 31 '24 116
118 Sanitary & Electric work 7 days Jan 1 '25 Jan 7 '25 117
119 Interior work 7 days Jan 8 '25 Jan 14 '25 118
120 Tiles 6 days Jan 15 '25 Jan 20 '25 119
121 Boring work 3 days Jan 21 '25 Jan 23 '25 120
122 Others work 40 days Jan 24 '25 Mar 4 '25 121